PK0-005 CompTIA Practice Test Questions and Exam Dumps


Question No 1:

A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization’s reluctance could jeopardize the success of the project. 

Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Choose two.)

A. Train users on the proper use of the system.
B. Escalate the issue to the CCB.
C. Hold sessions to understand user challenges.
D. Track system usage and report user activity.
E. Log the issue in the project risk register.
F. Create a memorandum of acceptable use.

Correct answers: C, E

Explanation:

When facing reluctance from a team or department in adopting a new system, particularly with the implementation of a Customer Relationship Management (CRM) system, it's essential to take actions that help understand the root causes of the reluctance and address concerns effectively. Let's go through the options to determine which actions would be most appropriate for resolving the adoption issues:

  • A. Train users on the proper use of the system:
    While training is important and can certainly help with system adoption, it might not address the core reluctance or resistance to using the system. Training assumes that users are already ready to adopt the system but doesn’t address potential underlying issues, such as poor user buy-in, usability concerns, or specific challenges. This step is useful in a broader adoption strategy but is not the first action to take when dealing with reluctance.

  • B. Escalate the issue to the CCB:
    The Change Control Board (CCB) generally manages scope changes and project-related issues, but reluctance to adopt a system is more of an organizational and human factor issue. Escalating this issue to the CCB might not be the most appropriate first step. Understanding the root causes of the reluctance is more important at this stage, so escalating the issue might not directly address the problem.

  • C. Hold sessions to understand user challenges:
    This step is crucial because it allows the project manager to directly engage with the sales team to understand their concerns, frustrations, and challenges with the new system. These feedback sessions provide insights into the reasons for reluctance and create an opportunity to discuss potential solutions. This approach will help foster engagement and can be a way to gain buy-in from the users.

  • D. Track system usage and report user activity:
    While tracking system usage could give insights into who is or isn’t using the system, this action alone does not directly address the core issue of reluctance. Tracking alone won’t help understand why the sales team is hesitant to adopt the CRM. In fact, it might just create further friction if users feel they are being monitored without addressing their concerns.

  • E. Log the issue in the project risk register:
    Reluctance to adopt the system represents a potential risk to the project’s success. Logging this issue in the project risk register ensures that the problem is formally recognized and tracked, and it allows the project manager to take steps to mitigate this risk. This can include assigning appropriate actions, such as understanding the challenges or working on engagement strategies to help with system adoption.

  • F. Create a memorandum of acceptable use:
    A memorandum of acceptable use could help define the rules around system usage, but it does not address the core problem of why the users are reluctant to adopt the system in the first place. It’s a more policy-oriented solution that might not be effective in overcoming reluctance, especially if the reluctance stems from practical challenges or user resistance.

Conclusion: The best approaches to address the adoption issues are to hold sessions to understand user challenges (C) and to log the issue in the project risk register (E). These steps focus on gathering insights and formally addressing the issue, which are critical to resolving the reluctance and gaining acceptance from the sales organization.

Question No 2:

Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?

A. Daily stand-up
B. Project momentum
C. Performance feedback
D. Meeting minutes

Correct answer: C

Explanation:

After the successful release of a project, sending out a survey to gather feedback from stakeholders is a valuable tool for improvement. It helps the project manager identify areas where the team can improve and make data-driven decisions for future work. Let’s go through each option to determine where the survey results would be the most useful as an input:

Option A: Daily stand-up
A daily stand-up is a quick, focused meeting where the team discusses progress, blockers, and priorities for the day. While survey results could potentially influence decisions or changes, they are not typically discussed in the context of a stand-up. Stand-ups are for short-term issues, immediate tasks, and quick updates, rather than long-term or strategic feedback. Therefore, survey results are not a typical input in a daily stand-up.

Option B: Project momentum
Project momentum refers to the overall progress and pace of the project, often determined by the successful completion of milestones and tasks. While stakeholder feedback might influence the pace of future projects, it does not directly impact the current project's momentum unless immediate actions are taken based on the feedback. Survey results can indirectly affect future momentum, but they do not directly contribute to the current momentum of the project.

Option C: Performance feedback
Performance feedback is the most relevant option. Survey results are designed to gather feedback on how well the team performed, areas where the team can improve, and the effectiveness of the project processes. These results are directly related to performance feedback because they can help the team understand their strengths and areas for improvement. The survey responses can serve as an important input for performance reviews, process improvements, and identifying action items for team growth.

Option D: Meeting minutes
Meeting minutes are a record of what was discussed during a meeting, including decisions made, actions assigned, and any important points. While survey results might be referenced in meeting minutes, they are not typically used as an input. The minutes document the discussions, but they do not form the basis of the meeting’s content unless explicitly addressed. Therefore, survey results are not directly used as an input for meeting minutes.

In conclusion, performance feedback is the most appropriate area where the survey results would be used as an input. This is because the survey is focused on gathering feedback about team performance and areas for improvement. Therefore, the correct answer is C.

Question No 3:

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

A. Evaluating the project

B. Releasing the resources

C. Closing the contracts

D. Reconciling the budget

Answer: D

Explanation:

The project triple constraint refers to the three primary constraints of project management: scope, time, and cost. In the closing phase of a project, the focus is on formally completing the project, ensuring all objectives have been met, and finalizing all aspects of the project to deliver a successful outcome. Activities performed in this phase help assess whether the project has adhered to its planned scope, timeline, and budget.

Let’s evaluate each option based on its relevance to the closing phase and the triple constraint:

A. Evaluating the project:

Evaluating the project is an important activity, but it is generally part of the project review and lessons learned process rather than the final closure of the project. This evaluation typically happens after the project has been completed, often during the closing phase, but it focuses more on learning and future improvements rather than directly supporting the project triple constraint.

B. Releasing the resources:

Releasing resources is a necessary task during the closing phase, especially in terms of human and physical resources. While this helps with project completion and ensures that project resources are freed up for future use, it doesn't directly relate to managing the triple constraint of scope, time, and cost.

C. Closing the contracts:

Closing contracts is also an essential activity in the closing phase. It ensures that all vendor and supplier contracts are completed, resolved, and signed off. While important, it is not the most direct activity that supports the triple constraint, as it deals more with contractual obligations and agreements rather than the constraints of scope, time, and cost.

D. Reconciling the budget:

Reconciling the budget is the activity that directly supports the cost aspect of the project triple constraint. During the closing phase, it's essential to review all financial records and finalize the project budget to determine whether the project was completed within the planned financial scope. This ensures that the project stayed within its budgetary constraints and helps in reporting any financial variances. This activity is crucial for understanding if the project was delivered on time, within scope, and within budget, which aligns directly with the project triple constraint.

The activity that most directly supports the project triple constraint in the closing phase is reconciling the budget (option D), as it deals specifically with managing the cost constraint of the project and ensures that the project was completed within its financial limits. Therefore, the correct answer is D.

Question No 4:

During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

A. Ishikawa diagram
B. Scatter diagram
C. Pareto chart
D. Decision tree

Correct Answer: C

Explanation:

In quality analysis and improvement processes, it is crucial to prioritize issues based on their impact. Identifying the most significant causes allows the project manager to address the most impactful problems first, optimizing resource allocation and time.

A. Ishikawa diagram

Also known as a fishbone diagram, the Ishikawa diagram is useful for identifying potential causes of problems. It helps in visually organizing different possible causes of an issue by categorizing them (e.g., people, process, equipment). While it helps in brainstorming and categorizing causes, it doesn't directly prioritize them based on their significance or frequency. Thus, while valuable for root cause analysis, it is not the best tool for identifying the most important causes in terms of priority.

B. Scatter diagram

A scatter diagram is used to show the relationship between two variables. It helps in identifying correlations or trends (e.g., whether increasing one variable impacts another). While it can be useful in understanding relationships between variables, it does not prioritize causes or identify the most important issues from a list of causes. Therefore, it's not the most appropriate tool in this context.

C. Pareto chart

The Pareto chart is a powerful tool for identifying and prioritizing issues. Based on the Pareto principle (80/20 rule), it helps to identify the most significant causes by displaying them in descending order of frequency or impact. The idea is that a small number of causes (typically around 20%) are responsible for the majority (around 80%) of the issues. The Pareto chart allows the project manager to focus on the most important causes, which is exactly what is needed in this situation.

D. Decision tree

A decision tree is a graphical representation used for decision-making, helping to visualize different options and their possible outcomes. It is particularly useful in decision analysis and understanding the consequences of various actions. While helpful for decision-making, it is not the right tool for identifying and prioritizing causes of issues, especially in the context of quality analysis.

To identify the most important causes of the issues, the Pareto chart is the best tool. It helps to visualize the most significant problems by focusing on those that occur most frequently or have the greatest impact. Therefore, the correct answer is C.

Question No 5:

Which of the following BEST describes how an organization should coordinate management of multiple related projects?

A. Apply the SDLC process.
B. Establish a program.
C. Consult the CCB.
D. Use different frameworks.

Correct answer: B

Explanation:

The best way for an organization to coordinate the management of multiple related projects is to establish a program. A program is a collection of related projects that are managed in a coordinated way to achieve benefits that would not be available if the projects were managed independently. The program management approach ensures that resources, timelines, and risks are aligned across the projects, and it facilitates strategic coordination to achieve the organization's broader objectives.

Here’s why the other options are not the best fit:

Option A (Apply the SDLC process): The System Development Life Cycle (SDLC) process is specifically used for managing the lifecycle of software development projects. It defines the stages of software development (e.g., planning, design, implementation, testing, maintenance) but is not typically used to coordinate multiple related projects that may span various areas of the organization. The SDLC is a methodology for individual projects rather than a broader coordination approach.

Option C (Consult the CCB): The Change Control Board (CCB) is typically a governance body that reviews and approves changes to the scope, schedule, or resources of a project. While the CCB is essential for managing changes within projects, it does not address the coordination of multiple projects. It focuses more on controlling project changes rather than overseeing the integration and coordination of related projects.

Option D (Use different frameworks): Using different frameworks can be effective for managing specific projects, but it doesn’t provide the unified structure needed to manage multiple related projects. Applying multiple frameworks without a comprehensive coordination approach could result in fragmentation, inconsistency, and inefficiency, rather than the synergy needed for successful program management.

Therefore, establishing a program (Option B) is the best approach to coordinate the management of multiple related projects, as it allows for alignment, resource optimization, and risk management across the projects within the program.

Question No 6:

Which document is the project manager most likely to have prepared to ensure team members who are absent remain informed about assignments?

A. Status report
B. Project plan
C. Change log
D. Meeting minutes

Correct Answer: D

Explanation:

In a project, effective communication is crucial to keep all team members on the same page, especially when some team members are unable to attend regular meetings. The goal is to ensure that those absent are still aware of the progress made, the decisions taken, and the assignments given. Let's analyze each option in this context:

Option A: Status report

A status report provides an overview of the current state of the project, including progress, completed tasks, and issues. While this document is helpful for providing a snapshot of the project’s health, it typically does not go into the level of detail required to update team members on specific assignments or the specifics of what was discussed during a meeting. Therefore, while a status report could be useful, it doesn't fully replace the detailed communication of meeting minutes. A is not the most appropriate choice in this context.

Option B: Project plan

The project plan outlines the entire scope, schedule, resources, and objectives of the project. While it is a crucial document for guiding the project, it does not provide updates on the latest meetings, discussions, or assignments. The project plan is more about the overall strategy and framework, not about specific weekly progress. As a result, B is not the most likely document the project manager would prepare for team members who miss meetings.

Option C: Change log

A change log records any changes to the project, such as alterations to scope, timelines, or requirements. While important for tracking changes and updates, it doesn't provide detailed information about specific assignments or what was discussed in the weekly meetings. It is more about tracking modifications to the project than about maintaining communication between team members. Therefore, C is not the most appropriate choice.

Option D: Meeting minutes

Meeting minutes are a detailed record of what transpired during a meeting. This document includes decisions made, assignments given, actions required, and other relevant discussions. It is the most effective document for ensuring that absent team members are kept informed about what was discussed and what their responsibilities are. The minutes provide a clear, concise summary of assignments, which is exactly what the project manager would want to share with team members who were unable to attend.

In conclusion, to ensure that absent team members are updated on the assignments and discussions from the meeting, the project manager is most likely to have prepared the meeting minutes. Therefore, the correct answer is D.

Question No 7:

Which communication method should the project manager use if they prefer immediate contact with team members for faster response times and more interactive discussions?

A. Synchronous
B. Informal
C. Asynchronous
D. Formal

Correct Answer: A

Explanation:

When managing a project, the method of communication plays a significant role in how efficiently information is exchanged among team members. Since the project manager wants immediate contact and values faster response times and more interactive discussions, they would require a communication method that supports real-time interaction.

Let's analyze each option:

Option A: Synchronous
Synchronous communication refers to communication that happens in real time, where all parties involved interact and exchange information simultaneously. Examples include phone calls, video conferences, and instant messaging. This method allows for immediate feedback and interactive discussions, making it ideal for the project manager’s goal of quick responses and real-time collaboration. Therefore, A is correct.

Option B: Informal
Informal communication refers to a more casual, unstructured form of communication, often used for day-to-day interactions. While informal communication can sometimes occur synchronously (e.g., through chat or casual conversation), it does not necessarily guarantee immediate contact or the level of interactivity desired. It can also lack the structure needed for project-related discussions. Therefore, B is not the best option.

Option C: Asynchronous
Asynchronous communication occurs when there is a delay between when a message is sent and when it is received. Examples include emails and forum posts. This method is ideal for communication that does not require immediate responses and is used for more thoughtful or planned discussions. However, for the project manager’s need for immediate contact and faster responses, asynchronous communication would not be suitable. Therefore, C is incorrect.

Option D: Formal
Formal communication is structured and follows a specific protocol, often used for official project documentation, reports, or communications that require a record. While formal communication can be important for specific project activities, it is typically not as interactive or quick as synchronous communication. Formal methods, such as written reports, are generally not suited for real-time discussions. Therefore, D is incorrect.
The most suitable communication method for the project manager, who needs immediate contact and values interactive discussions, is synchronous communication, as it allows for real-time feedback and faster response times.

Question No 8:

After defining tasks, durations, resources, and costs as part of the planning phase, what is the next step in the project management process?

A. Update the work breakdown structure.
B. Review the backlog.
C. Seek baseline approval.
D. Establish the resource pool.

Answer: C

Explanation:

Once the project manager (PM) has defined the tasks, durations, resources, and costs, the next logical step is to seek baseline approval. The project baseline is a reference point for measuring and monitoring the project's performance. It includes the approved version of the project’s schedule, scope, and cost, and establishes benchmarks for tracking progress and managing changes. Before the project moves forward into execution, the baseline needs to be formally approved by stakeholders. This approval signifies that all involved parties have agreed on the project's scope, timeline, and budget, providing a foundation for performance measurement and future decision-making.

Here’s why the other options are not the immediate next step:

Option A – Update the work breakdown structure (WBS):
The WBS is typically defined early in the planning phase, and it helps to break down the project into manageable sections. If the WBS was already created as part of the planning phase (as indicated in the question), there is no need to update it at this stage. The focus at this point should be on finalizing the baseline, not updating the WBS.

Option B – Review the backlog:
Reviewing the backlog typically applies to agile or iterative project management methodologies, where a backlog consists of a prioritized list of tasks or features to be completed. In traditional project management, the next step would generally be seeking baseline approval. While reviewing a backlog may be part of an agile process, it's not the next step in a typical planning process for a project with defined tasks, durations, resources, and costs.

Option D – Establish the resource pool:
The resource pool, which refers to the available resources (e.g., people, equipment) for the project, should have been established earlier in the planning phase when tasks and resources were defined. It is not the immediate next step after defining tasks, durations, and costs. If the resource pool has not been established yet, it is a sign that planning is still in progress, but typically this would have been addressed prior to baseline approval.

In conclusion, the next step after defining tasks, durations, resources, and costs is to seek baseline approval from stakeholders. This is necessary before proceeding to the execution phase, ensuring everyone is aligned with the project scope, schedule, and budget. Therefore, Option C is the correct answer.

Question No 9:

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

A. Trigger the contingency plan and communicate with the stakeholders.
B. Work with the functional managers to create a work-around.
C. Submit a change request to the change control board.
D. Transfer the risk by hiring a new vendor who was successful on a previous project.
E. Set up an escalation meeting with the sponsor.

Correct answer: E

Explanation:

When a project manager realizes that the project will not be completed on time due to resource constraints, the next step is to communicate with the project sponsor and escalate the situation. Escalation is necessary because resource constraints can have significant impacts on the project's success, and the sponsor is the key person who can make critical decisions about how to address these constraints, whether through reallocating resources, adjusting the project scope, or providing additional funding or time.

Let’s break down why E is the best option and why the others are not immediately appropriate:

  1. Escalation meeting with the sponsor (E):
    Setting up an escalation meeting with the sponsor is the most appropriate action to take next. The sponsor holds the authority to make critical decisions that may include providing more resources, extending deadlines, or adjusting the project scope to align with available resources. The project manager needs to inform the sponsor of the issue and work together to determine a path forward. Escalation ensures that the issue is given the proper attention at the appropriate level of authority.

  2. Trigger the contingency plan and communicate with the stakeholders (A):
    While triggering the contingency plan is an important step if a risk event occurs, it may not always be the best immediate action when the issue is resource constraints. The contingency plan typically applies to risks identified in advance, and it may not address the underlying issue of resource allocation. While communicating with stakeholders is important, the first step should be to escalate the issue to the sponsor to ensure that the right decisions are made at the right level.

  3. Work with the functional managers to create a work-around (B):
    Working with functional managers to create a work-around could be a useful step after discussing the situation with the sponsor. However, the project manager should first escalate the issue to the sponsor, who can provide higher-level guidance on how best to address the resource constraints. A work-around may be needed, but it’s not the immediate next step without first seeking the sponsor’s approval or input.

  4. Submit a change request to the change control board (C):
    A change request could be part of the solution after the sponsor has been consulted and if the project scope, timelines, or resources need to be adjusted. However, submitting a change request is not the first step when resource constraints are discovered. It should come after the sponsor’s involvement and direction on how to handle the issue.

  5. Transfer the risk by hiring a new vendor who was successful on a previous project (D):
    While hiring a new vendor may be a possible solution, it is not necessarily the first course of action to address resource constraints. Transferring the risk (i.e., changing vendors) would require careful evaluation of vendor capabilities, costs, and timelines. This decision should be made in consultation with the sponsor and after considering other more immediate solutions, such as adjusting project timelines or reallocating resources internally.

In conclusion, the next step the project manager should take when realizing that a project will not be completed on time due to resource constraints is to set up an escalation meeting with the sponsor (E). The sponsor’s input and decision-making authority are crucial to resolving the issue effectively.

UP

LIMITED OFFER: GET 30% Discount

This is ONE TIME OFFER

ExamSnap Discount Offer
Enter Your Email Address to Receive Your 30% Discount Code

A confirmation link will be sent to this email address to verify your login. *We value your privacy. We will not rent or sell your email address.

Download Free Demo of VCE Exam Simulator

Experience Avanset VCE Exam Simulator for yourself.

Simply submit your e-mail address below to get started with our interactive software demo of your free trial.

Free Demo Limits: In the demo version you will be able to access only first 5 questions from exam.