100% Latest & Updated PMI CAPM Practice Test Questions, Exam Dumps & Verified Answers!
30 Days Free Updates, Instant Download!
Question 30
After a corrective decision on Issues-versus-risks classification, which independent evidence most directly verifies the result ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A conveyor has already failed in system testing but a status report lists the failure as a future possibility with only a probability score. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Check the issue log for actual date, impact, owner and resolution, and separately inspect future-risk descriptions. Reconcile the result with the current approved decision baseline.
- Compare approved benefit measures with baseline and after-release processing times. Reconcile the result with the current approved decision baseline.
- Treating every observed failure as an untriggered risk postpones immediate defect resolution.
- Review assumption-validation dates and the approved cost limit in the planning baseline. Reconcile the result with the current approved decision baseline.
Explanation
Correct Answer
A:This checks the actual mechanism rather than merely declaring success: Check the issue log for actual date, impact, owner and resolution, and separately inspect future-risk descriptions. Reconcile the result with the current approved decision baseline. The desired observed result is Current defects are actively resolved while uncertain exposures retain risk responses. The decision can be traced to the review evidence. [R158 R158-Q0030; case R158-C008; CAPM domain 1, task 1.1; source ECO.]
Incorrect Answers
B:The proposed verify (Compare approved benefit measures with baseline and after-release processing times. Reconcile the result with the current approved decision baseline.) comes from a different Project life cycles and processes situation: A sponsor measures the upgrade only by the number of screens delivered even though the business case concerns reduced claims processing time. It does not resolve or independently test the stated issue: A conveyor has already failed in system testing but a status report lists the failure as a future possibility with only a probability score. Here, the relevant check is Check the issue log for actual date, impact, owner and resolution, and separately inspect future-risk descriptions. Reconcile the result with the current approved decision baseline. [R158 R158-Q0030; case R158-C008; CAPM domain 1, task 1.1; source ECO.]
C:This is a tempting but unsupported shortcut in this case: Treating every observed failure as an untriggered risk postpones immediate defect resolution. It does not show that Current defects are actively resolved while uncertain exposures retain risk responses. The decision can be traced to the review evidence. [R158 R158-Q0030; case R158-C008; CAPM domain 1, task 1.1; source ECO.]
D:This option concerns a different Project life cycles and processes situation: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. For the reported case, use this verification: Check the issue log for actual date, impact, owner and resolution, and separately inspect future-risk descriptions. Reconcile the result with the current approved decision baseline.
Question 31
Which statement most accurately flags a misleading shortcut to avoid in this Issues-versus-risks classification case? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A conveyor has already failed in system testing but a status report lists the failure as a future possibility with only a probability score. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Treating every observed failure as an untriggered risk postpones immediate defect resolution.
- Check the issue log for actual date, impact, owner and resolution, and separately inspect future-risk descriptions. Reconcile the result with the current approved decision baseline.
- Current defects are actively resolved while uncertain exposures retain risk responses. The decision can be traced to the review evidence.
- Log the actual failure as an issue with owner and corrective action; reserve risk entries for uncertain future events. Document impacted stakeholders and the decision owner at the review.
Explanation
Correct Answer
A:The shortcut is mistaken: Treating every observed failure as an untriggered risk postpones immediate defect resolution. The appropriate response is to log the actual failure as an issue with owner and corrective action; reserve risk entries for uncertain future events. Document impacted stakeholders and the decision owner at the review.
Incorrect Answers
B:This is an appropriate independent test of the proposed decision: Check the issue log for actual date, impact, owner and resolution, and separately inspect future-risk descriptions. Reconcile the result with the current approved decision baseline. It is not the invalid shortcut.
C:This is a relevant outcome to seek after the decision: Current defects are actively resolved while uncertain exposures retain risk responses. The decision can be traced to the review evidence. It is not an unsupported assumption.
D:This is a supported decision, not the unsupported claim: Log the actual failure as an issue with owner and corrective action; reserve risk entries for uncertain future events. Document impacted stakeholders and the decision owner at the review. It responds to the actual project issue: A conveyor has already failed in system testing but a status report lists the failure as a future possibility with only a probability score.
Question 32
Select THREE consistent elements of the Issues-versus-risks classification case: appropriate decision, verification, and observable success condition. At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A conveyor has already failed in system testing but a status report lists the failure as a future possibility with only a probability score. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Check the issue log for actual date, impact, owner and resolution, and separately inspect future-risk descriptions. Reconcile the result with the current approved decision baseline.
- Log the actual failure as an issue with owner and corrective action; reserve risk entries for uncertain future events. Document impacted stakeholders and the decision owner at the review.
- Treating every observed failure as an untriggered risk postpones immediate defect resolution.
- Vendor selection is traceable to fair criteria rather than an undisclosed personal interest. The decision can be traced to the review evidence.
- Current defects are actively resolved while uncertain exposures retain risk responses. The decision can be traced to the review evidence.
- Report the actual milestone variance with evidence, root cause and a credible recovery proposal. Document impacted stakeholders and the decision owner at the review.
Explanation
Correct Answer
A:This checks the actual mechanism rather than merely declaring success: Check the issue log for actual date, impact, owner and resolution, and separately inspect future-risk descriptions. Reconcile the result with the current approved decision baseline. The desired observed result is Current defects are actively resolved while uncertain exposures retain risk responses. The decision can be traced to the review evidence. [R158 R158-Q0032; case R158-C008; CAPM domain 1, task 1.1; source ECO.]
B:The case evidence identifies A conveyor has already failed in system testing but a status report lists the failure as a future possibility with only a probability score. The specified decision directly addresses it: Log the actual failure as an issue with owner and corrective action; reserve risk entries for uncertain future events. Document impacted stakeholders and the decision owner at the review. This can be checked using Check the issue log for actual date, impact, owner and resolution, and separately inspect future-risk descriptions. Reconcile the result with the current approved decision baseline. [R158 R158-Q0032; case R158-C008; CAPM domain 1, task 1.1; source ECO.]
E:The stated result demonstrates the case acceptance condition: Current defects are actively resolved while uncertain exposures retain risk responses. The decision can be traced to the review evidence. It depends on the decision Log the actual failure as an issue with owner and corrective action; reserve risk entries for uncertain future events. Document impacted stakeholders and the decision owner at the review.
Incorrect Answers
C:This is a tempting but unsupported shortcut in this case: Treating every observed failure as an untriggered risk postpones immediate defect resolution. It does not show that Current defects are actively resolved while uncertain exposures retain risk responses. The decision can be traced to the review evidence. [R158 R158-Q0032; case R158-C008; CAPM domain 1, task 1.1; source ECO.]
D:This option concerns a different Project life cycles and processes situation: A project evaluator has a close financial interest in a vendor under consideration but plans to score proposals without telling the review panel. For the reported case, use this verification: Check the issue log for actual date, impact, owner and resolution, and separately inspect future-risk descriptions. Reconcile the result with the current approved decision baseline.
F:This option concerns a different Project life cycles and processes situation: An integration milestone is late, but a lead asks for a green status to prevent executive scrutiny. For the reported case, use this verification: Check the issue log for actual date, impact, owner and resolution, and separately inspect future-risk descriptions. Reconcile the result with the current approved decision baseline.
Question 33
Which project-management decision best addresses the Assumptions-versus-constraints situation ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Define the temporary redesign effort as a project with a unique outcome, and separate the ongoing fulfillment process as operations. Record the rationale before the next commitment.
- Document permit approval as an assumption to validate and the funding ceiling as a constraint to plan within. Record the rationale before the next commitment.
- Clarify the documented product boundary and route the proposed payroll addition through the agreed change evaluation. Record the rationale before the next commitment.
- Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed.
Explanation
Correct Answer
B:The case evidence identifies An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. The specified decision directly addresses it: Document permit approval as an assumption to validate and the funding ceiling as a constraint to plan within. Record the rationale before the next commitment. This can be checked using Review assumption-validation dates and the approved cost limit in the planning baseline. Retain the initiating evidence for audit. [R158 R158-Q0033; case R158-C009; CAPM domain 1, task 1.1; source ECO.]
Incorrect Answers
A:This option concerns a different Project life cycles and processes situation: A retail chain is commissioning a one-time warehouse routing redesign but the team wants to fund it as routine monthly order processing. For the reported case, use this verification: Review assumption-validation dates and the approved cost limit in the planning baseline. Retain the initiating evidence for audit.
C:This option concerns a different Project life cycles and processes situation: A school scheduling rollout includes student enrollment but excludes payroll integration; a manager requests payroll features without a change decision. For the reported case, use this verification: Review assumption-validation dates and the approved cost limit in the planning baseline. Retain the initiating evidence for audit.
D:This is a tempting but unsupported shortcut in this case: Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed. It does not show that Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The result is recorded in the project controls. [R158 R158-Q0033; case R158-C009; CAPM domain 1, task 1.1; source ECO.]
Question 34
After a corrective decision on Assumptions-versus-constraints, which independent evidence most directly verifies the result ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Review assumption-validation dates and the approved cost limit in the planning baseline. Retain the initiating evidence for audit.
- Check transition ownership, staff readiness criteria and post-rollout benefit measurements. Reconcile the result with the current approved decision baseline.
- Reconcile reported progress with accepted deliverables and dated milestone records. Reconcile the result with the current approved decision baseline.
- Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed.
Explanation
Correct Answer
A:This checks the actual mechanism rather than merely declaring success: Review assumption-validation dates and the approved cost limit in the planning baseline. Retain the initiating evidence for audit. The desired observed result is Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The result is recorded in the project controls. [R158 R158-Q0034; case R158-C009; CAPM domain 1, task 1.1; source ECO.]
Incorrect Answers
B:This option concerns a different Project life cycles and processes situation: A health system installs a new triage tool but does not assign anyone to transition daily workflows or support staff adoption. For the reported case, use this verification: Review assumption-validation dates and the approved cost limit in the planning baseline. Retain the initiating evidence for audit.
C:The proposed verify (Reconcile reported progress with accepted deliverables and dated milestone records. Reconcile the result with the current approved decision baseline.) comes from a different Project life cycles and processes situation: An integration milestone is late, but a lead asks for a green status to prevent executive scrutiny. It does not resolve or independently test the stated issue: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Here, the relevant check is Review assumption-validation dates and the approved cost limit in the planning baseline. Retain the initiating evidence for audit. [R158 R158-Q0034; case R158-C009; CAPM domain 1, task 1.1; source ECO.]
D:This is a tempting but unsupported shortcut in this case: Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed. It does not show that Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The result is recorded in the project controls. [R158 R158-Q0034; case R158-C009; CAPM domain 1, task 1.1; source ECO.]
Question 35
Which statement most accurately flags a misleading shortcut to avoid in this Assumptions-versus-constraints case? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Review assumption-validation dates and the approved cost limit in the planning baseline. Retain the initiating evidence for audit.
- Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The result is recorded in the project controls.
- Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed.
- Document permit approval as an assumption to validate and the funding ceiling as a constraint to plan within. Record the rationale before the next commitment.
Explanation
Correct Answer
C:The shortcut is mistaken: Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed. The appropriate response is to document permit approval as an assumption to validate and the funding ceiling as a constraint to plan within. Record the rationale before the next commitment.
Incorrect Answers
A:This is an appropriate independent test of the proposed decision: Review assumption-validation dates and the approved cost limit in the planning baseline. Retain the initiating evidence for audit. It is not the invalid shortcut.
B:This is a relevant outcome to seek after the decision: Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The result is recorded in the project controls. It is not an unsupported assumption.
D:This is a supported decision, not the unsupported claim: Document permit approval as an assumption to validate and the funding ceiling as a constraint to plan within. Record the rationale before the next commitment. It responds to the actual project issue: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit.
Question 36
Select THREE consistent elements of the Assumptions-versus-constraints case: appropriate decision, verification, and observable success condition. During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Review assumption-validation dates and the approved cost limit in the planning baseline. Retain the initiating evidence for audit.
- Document permit approval as an assumption to validate and the funding ceiling as a constraint to plan within. Record the rationale before the next commitment.
- Report the actual milestone variance with evidence, root cause and a credible recovery proposal. Document impacted stakeholders and the decision owner at the review.
- Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The result is recorded in the project controls.
- Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed.
- Shared benefits and dependencies are tracked at program level while investment priorities remain visible at portfolio level. The decision can be traced to the review evidence.
Explanation
Correct Answer
A:This checks the actual mechanism rather than merely declaring success: Review assumption-validation dates and the approved cost limit in the planning baseline. Retain the initiating evidence for audit. The desired observed result is Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The result is recorded in the project controls. [R158 R158-Q0036; case R158-C009; CAPM domain 1, task 1.1; source ECO.]
B:The case evidence identifies An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. The specified decision directly addresses it: Document permit approval as an assumption to validate and the funding ceiling as a constraint to plan within. Record the rationale before the next commitment. This can be checked using Review assumption-validation dates and the approved cost limit in the planning baseline. Retain the initiating evidence for audit. [R158 R158-Q0036; case R158-C009; CAPM domain 1, task 1.1; source ECO.]
D:The stated result demonstrates the case acceptance condition: Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The result is recorded in the project controls. It depends on the decision Document permit approval as an assumption to validate and the funding ceiling as a constraint to plan within. Record the rationale before the next commitment.
Incorrect Answers
C:The proposed action (Report the actual milestone variance with evidence, root cause and a credible recovery proposal. Document impacted stakeholders and the decision owner at the review.) comes from a different Project life cycles and processes situation: An integration milestone is late, but a lead asks for a green status to prevent executive scrutiny. It does not resolve or independently test the stated issue: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Here, the relevant check is Review assumption-validation dates and the approved cost limit in the planning baseline. Retain the initiating evidence for audit. [R158 R158-Q0036; case R158-C009; CAPM domain 1, task 1.1; source ECO.]
E:This is a tempting but unsupported shortcut in this case: Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed. It does not show that Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The result is recorded in the project controls. [R158 R158-Q0036; case R158-C009; CAPM domain 1, task 1.1; source ECO.]
F:This option concerns a different Project life cycles and processes situation: A hospital groups linked clinical record, identity, and data-migration projects under one coordinated benefit but reports them as unrelated portfolio investments. For the reported case, use this verification: Review assumption-validation dates and the approved cost limit in the planning baseline. Retain the initiating evidence for audit.
Question 37
Which project-management decision best addresses the Assumptions-versus-constraints situation ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Disclose the conflict promptly, follow the organization's procurement safeguards and recuse where independence is required. Document impacted stakeholders and the decision owner at the review.
- Document permit approval as an assumption to validate and the funding ceiling as a constraint to plan within. Document impacted stakeholders and the decision owner at the review.
- Clarify the documented product boundary and route the proposed payroll addition through the agreed change evaluation. Record the rationale before the next commitment.
- Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed.
Explanation
Correct Answer
B:Document permit approval as an assumption to validate and the funding ceiling as a constraint to plan within. Document impacted stakeholders and the decision owner at the review. To verify the specified result, review assumption-validation dates and the approved cost limit in the planning baseline. Reconcile the result with the current approved decision baseline.
Incorrect Answers
A:The proposed action (Disclose the conflict promptly, follow the organization's procurement safeguards and recuse where independence is required. Document impacted stakeholders and the decision owner at the review.) comes from a different Project life cycles and processes situation: A project evaluator has a close financial interest in a vendor under consideration but plans to score proposals without telling the review panel. It does not resolve or independently test the stated issue: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Here, the relevant check is Review assumption-validation dates and the approved cost limit in the planning baseline. Reconcile the result with the current approved decision baseline. [R158 R158-Q0037; case R158-C010; CAPM domain 1, task 1.1; source ECO.]
C:The proposed action (Clarify the documented product boundary and route the proposed payroll addition through the agreed change evaluation. Record the rationale before the next commitment.) comes from a different Project life cycles and processes situation: A school scheduling rollout includes student enrollment but excludes payroll integration; a manager requests payroll features without a change decision. It does not resolve or independently test the stated issue: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Here, the relevant check is Review assumption-validation dates and the approved cost limit in the planning baseline. Reconcile the result with the current approved decision baseline. [R158 R158-Q0037; case R158-C010; CAPM domain 1, task 1.1; source ECO.]
D:This is a tempting but unsupported shortcut in this case: Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed. It does not show that Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The decision can be traced to the review evidence. [R158 R158-Q0037; case R158-C010; CAPM domain 1, task 1.1; source ECO.]
Question 38
After a corrective decision on Assumptions-versus-constraints, which independent evidence most directly verifies the result ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Inspect conflict declarations and the documented impartial scoring or substitution process. Retain the initiating evidence for audit.
- Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed.
- Review assumption-validation dates and the approved cost limit in the planning baseline. Reconcile the result with the current approved decision baseline.
- Check transition ownership, staff readiness criteria and post-rollout benefit measurements. Retain the initiating evidence for audit.
Explanation
Correct Answer
C:Review assumption-validation dates and the approved cost limit in the planning baseline. Reconcile the result with the current approved decision baseline. The expected result is uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The decision can be traced to the review evidence.
Incorrect Answers
A:The proposed verify (Inspect conflict declarations and the documented impartial scoring or substitution process. Retain the initiating evidence for audit.) comes from a different Project life cycles and processes situation: A project evaluator has a close financial interest in a vendor under consideration but plans to score proposals without telling the review panel. It does not resolve or independently test the stated issue: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Here, the relevant check is Review assumption-validation dates and the approved cost limit in the planning baseline. Reconcile the result with the current approved decision baseline. [R158 R158-Q0038; case R158-C010; CAPM domain 1, task 1.1; source ECO.]
B:This is a tempting but unsupported shortcut in this case: Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed. It does not show that Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The decision can be traced to the review evidence. [R158 R158-Q0038; case R158-C010; CAPM domain 1, task 1.1; source ECO.]
D:The proposed verify (Check transition ownership, staff readiness criteria and post-rollout benefit measurements. Retain the initiating evidence for audit.) comes from a different Project life cycles and processes situation: A health system installs a new triage tool but does not assign anyone to transition daily workflows or support staff adoption. It does not resolve or independently test the stated issue: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Here, the relevant check is Review assumption-validation dates and the approved cost limit in the planning baseline. Reconcile the result with the current approved decision baseline. [R158 R158-Q0038; case R158-C010; CAPM domain 1, task 1.1; source ECO.]
Question 39
Which statement most accurately flags a misleading shortcut to avoid in this Assumptions-versus-constraints case? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed.
- Document permit approval as an assumption to validate and the funding ceiling as a constraint to plan within. Document impacted stakeholders and the decision owner at the review.
- Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The decision can be traced to the review evidence.
- Review assumption-validation dates and the approved cost limit in the planning baseline. Reconcile the result with the current approved decision baseline.
Explanation
Correct Answer
A:The shortcut is mistaken: Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed. The appropriate response is to document permit approval as an assumption to validate and the funding ceiling as a constraint to plan within. Document impacted stakeholders and the decision owner at the review.
Incorrect Answers
B:This is a supported decision, not the unsupported claim: Document permit approval as an assumption to validate and the funding ceiling as a constraint to plan within. Document impacted stakeholders and the decision owner at the review. It responds to the actual project issue: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit.
C:This is a relevant outcome to seek after the decision: Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The decision can be traced to the review evidence. It is not an unsupported assumption.
D:This is an appropriate independent test of the proposed decision: Review assumption-validation dates and the approved cost limit in the planning baseline. Reconcile the result with the current approved decision baseline. It is not the invalid shortcut.
Question 40
Which observed result supports acceptance of the Assumptions-versus-constraints corrective decision ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- The scope statement and authorized work remain aligned instead of growing through informal requests. The result is recorded in the project controls.
- Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The decision can be traced to the review evidence.
- The new tool changes operational practice and can realize the intended benefit after launch. The decision can be traced to the review evidence.
- Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed.
Explanation
Correct Answer
B:The stated result demonstrates the case acceptance condition: Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The decision can be traced to the review evidence. It depends on the decision Document permit approval as an assumption to validate and the funding ceiling as a constraint to plan within. Document impacted stakeholders and the decision owner at the review.
Incorrect Answers
A:The proposed outcome (The scope statement and authorized work remain aligned instead of growing through informal requests. The result is recorded in the project controls.) comes from a different Project life cycles and processes situation: A school scheduling rollout includes student enrollment but excludes payroll integration; a manager requests payroll features without a change decision. It does not resolve or independently test the stated issue: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Here, the relevant check is Review assumption-validation dates and the approved cost limit in the planning baseline. Reconcile the result with the current approved decision baseline. [R158 R158-Q0040; case R158-C010; CAPM domain 1, task 1.1; source ECO.]
C:The proposed outcome (The new tool changes operational practice and can realize the intended benefit after launch. The decision can be traced to the review evidence.) comes from a different Project life cycles and processes situation: A health system installs a new triage tool but does not assign anyone to transition daily workflows or support staff adoption. It does not resolve or independently test the stated issue: An energy retrofit plan assumes a regulator will approve a permit, while the funding ceiling is a fixed contractual limit. Here, the relevant check is Review assumption-validation dates and the approved cost limit in the planning baseline. Reconcile the result with the current approved decision baseline. [R158 R158-Q0040; case R158-C010; CAPM domain 1, task 1.1; source ECO.]
D:This is a tempting but unsupported shortcut in this case: Treating the unconfirmed permit as a binding constraint makes unknown external approval appear guaranteed. It does not show that Uncertain approval is monitored and the firm funding restriction remains visible in scope and schedule decisions. The decision can be traced to the review evidence. [R158 R158-Q0040; case R158-C010; CAPM domain 1, task 1.1; source ECO.]
Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests