PMI CAPM Exam Dumps, Practice Test Questions

100% Latest & Updated PMI CAPM Practice Test Questions, Exam Dumps & Verified Answers!
30 Days Free Updates, Instant Download!

PMI CAPM Premium Bundle
$79.97
$59.98

CAPM Premium Bundle

  • Premium File: 688 Questions & Answers. Last update: Nov 2, 2026
  • Training Course: 123 Video Lectures
  • Study Guide: 719 Pages
  • Latest Questions
  • 100% Accurate Answers
  • Fast Exam Updates

CAPM Premium Bundle

PMI CAPM Premium Bundle
  • Premium File: 688 Questions & Answers. Last update: Nov 2, 2026
  • Training Course: 123 Video Lectures
  • Study Guide: 719 Pages
  • Latest Questions
  • 100% Accurate Answers
  • Fast Exam Updates
$79.97
$59.98

PMI CAPM Practice Test 35

Question 340

Which observed result supports acceptance of the Total-float-computation corrective decision ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: An activity can start no earlier than project day 5 but can start as late as day 9 without delaying the current network completion. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. The WBS covers authorized outputs without mistaking recurring meetings for the deliverables themselves. The result is recorded in the project controls.
  2. Calling any nonzero float a four-day increase in the overall project duration confuses scheduling flexibility with extension approval.
  3. The activity has four days of total float before it threatens the controlling finish date. The result is recorded in the project controls.
  4. The approved plan reflects coherent cross-functional impacts instead of isolated equipment changes. The result is recorded in the project controls.

Explanation

Correct Answer

C:

The stated result demonstrates the case acceptance condition: The activity has four days of total float before it threatens the controlling finish date. The result is recorded in the project controls. It depends on the decision Compute total float as late start minus early start, giving four days under the stated unconstrained network. Record the rationale before the next commitment.

Incorrect Answers

A:

The proposed outcome (The WBS covers authorized outputs without mistaking recurring meetings for the deliverables themselves. The result is recorded in the project controls.) comes from a different Predictive project schedule and methods situation: A project WBS has vague headings such as weekly calls and team morale but lacks identifiable deliverables for the security audit. It does not resolve or independently test the stated issue: An activity can start no earlier than project day 5 but can start as late as day 9 without delaying the current network completion. Here, the relevant check is Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Retain the initiating evidence for audit. [R158 R158-Q0340; case R158-C085; CAPM domain 2, task 2.2; source CPM.]

B:

This is a tempting but unsupported shortcut in this case: Calling any nonzero float a four-day increase in the overall project duration confuses scheduling flexibility with extension approval. It does not show that The activity has four days of total float before it threatens the controlling finish date. The result is recorded in the project controls. [R158 R158-Q0340; case R158-C085; CAPM domain 2, task 2.2; source CPM.]

D:

This option concerns a different Predictive project schedule and methods situation: A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost. For the reported case, use this verification: Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Retain the initiating evidence for audit.

Question 341

Which project-management decision best addresses the Total-float-computation situation ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: An activity can start no earlier than project day 5 but can start as late as day 9 without delaying the current network completion. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Document impacted stakeholders and the decision owner at the review.
  2. Calling any nonzero float a four-day increase in the overall project duration confuses scheduling flexibility with extension approval.
  3. Decompose the approved project scope into deliverable-oriented components and work packages that can be planned and controlled. Document impacted stakeholders and the decision owner at the review.
  4. Compute total float as late start minus early start, giving four days under the stated unconstrained network. Document impacted stakeholders and the decision owner at the review.

Explanation

Correct Answer

D:

The case evidence identifies An activity can start no earlier than project day 5 but can start as late as day 9 without delaying the current network completion. The specified decision directly addresses it: Compute total float as late start minus early start, giving four days under the stated unconstrained network. Document impacted stakeholders and the decision owner at the review. This can be checked using Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Reconcile the result with the current approved decision baseline. [R158 R158-Q0341; case R158-C086; CAPM domain 2, task 2.2; source CPM.]

Incorrect Answers

A:

This option concerns a different Predictive project schedule and methods situation: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. For the reported case, use this verification: Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Reconcile the result with the current approved decision baseline.

B:

This is a tempting but unsupported shortcut in this case: Calling any nonzero float a four-day increase in the overall project duration confuses scheduling flexibility with extension approval. It does not show that The activity has four days of total float before it threatens the controlling finish date. The decision can be traced to the review evidence. [R158 R158-Q0341; case R158-C086; CAPM domain 2, task 2.2; source CPM.]

C:

The proposed action (Decompose the approved project scope into deliverable-oriented components and work packages that can be planned and controlled. Document impacted stakeholders and the decision owner at the review.) comes from a different Predictive project schedule and methods situation: A project WBS has vague headings such as weekly calls and team morale but lacks identifiable deliverables for the security audit. It does not resolve or independently test the stated issue: An activity can start no earlier than project day 5 but can start as late as day 9 without delaying the current network completion. Here, the relevant check is Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Reconcile the result with the current approved decision baseline. [R158 R158-Q0341; case R158-C086; CAPM domain 2, task 2.2; source CPM.]

Question 342

After a corrective decision on Total-float-computation, which independent evidence most directly verifies the result ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: An activity can start no earlier than project day 5 but can start as late as day 9 without delaying the current network completion. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Trace work packages to scoped audit deliverables and identify the accountable control or acceptance point. Reconcile the result with the current approved decision baseline.
  2. Calculate both path lengths as 8+4=12 and 13+4=17 days and inspect the dependency network. Reconcile the result with the current approved decision baseline.
  3. Calling any nonzero float a four-day increase in the overall project duration confuses scheduling flexibility with extension approval.
  4. Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Reconcile the result with the current approved decision baseline.

Explanation

Correct Answer

D:

This checks the actual mechanism rather than merely declaring success: Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Reconcile the result with the current approved decision baseline. The desired observed result is The activity has four days of total float before it threatens the controlling finish date. The decision can be traced to the review evidence. [R158 R158-Q0342; case R158-C086; CAPM domain 2, task 2.2; source CPM.]

Incorrect Answers

A:

The proposed verify (Trace work packages to scoped audit deliverables and identify the accountable control or acceptance point. Reconcile the result with the current approved decision baseline.) comes from a different Predictive project schedule and methods situation: A project WBS has vague headings such as weekly calls and team morale but lacks identifiable deliverables for the security audit. It does not resolve or independently test the stated issue: An activity can start no earlier than project day 5 but can start as late as day 9 without delaying the current network completion. Here, the relevant check is Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Reconcile the result with the current approved decision baseline. [R158 R158-Q0342; case R158-C086; CAPM domain 2, task 2.2; source CPM.]

B:

This option concerns a different Predictive project schedule and methods situation: Two parallel activities lead to the same milestone: engineering takes 8 days, procurement 13 days, followed by a common 4-day commissioning task. For the reported case, use this verification: Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Reconcile the result with the current approved decision baseline.

C:

This is a tempting but unsupported shortcut in this case: Calling any nonzero float a four-day increase in the overall project duration confuses scheduling flexibility with extension approval. It does not show that The activity has four days of total float before it threatens the controlling finish date. The decision can be traced to the review evidence. [R158 R158-Q0342; case R158-C086; CAPM domain 2, task 2.2; source CPM.]

Question 343

Which statement most accurately flags a misleading shortcut to avoid in this Total-float-computation case? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: An activity can start no earlier than project day 5 but can start as late as day 9 without delaying the current network completion. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Reconcile the result with the current approved decision baseline.
  2. Calling any nonzero float a four-day increase in the overall project duration confuses scheduling flexibility with extension approval.
  3. Compute total float as late start minus early start, giving four days under the stated unconstrained network. Document impacted stakeholders and the decision owner at the review.
  4. The activity has four days of total float before it threatens the controlling finish date. The decision can be traced to the review evidence.

Explanation

Correct Answer

B:

The shortcut is mistaken: Calling any nonzero float a four-day increase in the overall project duration confuses scheduling flexibility with extension approval. The appropriate response is to compute total float as late start minus early start, giving four days under the stated unconstrained network. Document impacted stakeholders and the decision owner at the review.

Incorrect Answers

A:

This is an appropriate independent test of the proposed decision: Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Reconcile the result with the current approved decision baseline. It is not the invalid shortcut.

C:

This is a supported decision, not the unsupported claim: Compute total float as late start minus early start, giving four days under the stated unconstrained network. Document impacted stakeholders and the decision owner at the review. It responds to the actual project issue: An activity can start no earlier than project day 5 but can start as late as day 9 without delaying the current network completion.

D:

This is a relevant outcome to seek after the decision: The activity has four days of total float before it threatens the controlling finish date. The decision can be traced to the review evidence. It is not an unsupported assumption.

Question 344

Select TWO case-specific elements of a justified Total-float-computation resolution : the decision and its direct evidence. At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: An activity can start no earlier than project day 5 but can start as late as day 9 without delaying the current network completion. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Trace work packages to scoped audit deliverables and identify the accountable control or acceptance point. Retain the initiating evidence for audit.
  2. Calling any nonzero float a four-day increase in the overall project duration confuses scheduling flexibility with extension approval.
  3. Compute total float as late start minus early start, giving four days under the stated unconstrained network. Document impacted stakeholders and the decision owner at the review.
  4. Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Reconcile the result with the current approved decision baseline.
  5. Apply the approved quality plan's sampling and defect criteria and escalate nonconforming test results. Record the rationale before the next commitment.

Explanation

Correct Answer

C:

The case evidence identifies An activity can start no earlier than project day 5 but can start as late as day 9 without delaying the current network completion. The specified decision directly addresses it: Compute total float as late start minus early start, giving four days under the stated unconstrained network. Document impacted stakeholders and the decision owner at the review. This can be checked using Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Reconcile the result with the current approved decision baseline. [R158 R158-Q0344; case R158-C086; CAPM domain 2, task 2.2; source CPM.]

D:

This checks the actual mechanism rather than merely declaring success: Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Reconcile the result with the current approved decision baseline. The desired observed result is The activity has four days of total float before it threatens the controlling finish date. The decision can be traced to the review evidence. [R158 R158-Q0344; case R158-C086; CAPM domain 2, task 2.2; source CPM.]

Incorrect Answers

A:

The proposed verify (Trace work packages to scoped audit deliverables and identify the accountable control or acceptance point. Retain the initiating evidence for audit.) comes from a different Predictive project schedule and methods situation: A project WBS has vague headings such as weekly calls and team morale but lacks identifiable deliverables for the security audit. It does not resolve or independently test the stated issue: An activity can start no earlier than project day 5 but can start as late as day 9 without delaying the current network completion. Here, the relevant check is Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Reconcile the result with the current approved decision baseline. [R158 R158-Q0344; case R158-C086; CAPM domain 2, task 2.2; source CPM.]

B:

This is a tempting but unsupported shortcut in this case: Calling any nonzero float a four-day increase in the overall project duration confuses scheduling flexibility with extension approval. It does not show that The activity has four days of total float before it threatens the controlling finish date. The decision can be traced to the review evidence. [R158 R158-Q0344; case R158-C086; CAPM domain 2, task 2.2; source CPM.]

E:

This option concerns a different Predictive project schedule and methods situation: A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. For the reported case, use this verification: Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Reconcile the result with the current approved decision baseline.

Question 345

Which project-management decision best addresses the Schedule-variance-sign situation ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A predictive project has PV=$90,000 and EV=$75,000 at the review date. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Subtracting AC from EV gives cost variance, not the schedule variance requested by the case.
  2. Apply the approved quality plan's sampling and defect criteria and escalate nonconforming test results. Document impacted stakeholders and the decision owner at the review.
  3. Evaluate the integrated impact on scope, schedule, cost, interfaces and approvals before altering baselines. Document impacted stakeholders and the decision owner at the review.
  4. Calculate schedule variance as EV minus PV, yielding negative $15,000 of budget-valued schedule variance. Record the rationale before the next commitment.

Explanation

Correct Answer

D:

The case evidence identifies A predictive project has PV=$90,000 and EV=$75,000 at the review date. The specified decision directly addresses it: Calculate schedule variance as EV minus PV, yielding negative $15,000 of budget-valued schedule variance. Record the rationale before the next commitment. This can be checked using Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Retain the initiating evidence for audit. [R158 R158-Q0345; case R158-C087; CAPM domain 2, task 2.2; source EVM.]

Incorrect Answers

A:

This is a tempting but unsupported shortcut in this case: Subtracting AC from EV gives cost variance, not the schedule variance requested by the case. It does not show that The report correctly flags less budgeted work earned than planned rather than asserting a literal 15-day delay. The result is recorded in the project controls. [R158 R158-Q0345; case R158-C087; CAPM domain 2, task 2.2; source EVM.]

B:

The proposed action (Apply the approved quality plan's sampling and defect criteria and escalate nonconforming test results. Document impacted stakeholders and the decision owner at the review.) comes from a different Predictive project schedule and methods situation: A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. It does not resolve or independently test the stated issue: A predictive project has PV=$90,000 and EV=$75,000 at the review date. Here, the relevant check is Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Retain the initiating evidence for audit. [R158 R158-Q0345; case R158-C087; CAPM domain 2, task 2.2; source EVM.]

C:

This option concerns a different Predictive project schedule and methods situation: A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost. For the reported case, use this verification: Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Retain the initiating evidence for audit.

Question 346

After a corrective decision on Schedule-variance-sign, which independent evidence most directly verifies the result ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A predictive project has PV=$90,000 and EV=$75,000 at the review date. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Calculate both path lengths as 8+4=12 and 13+4=17 days and inspect the dependency network. Reconcile the result with the current approved decision baseline.
  2. Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Retain the initiating evidence for audit.
  3. Verify ES=5, LS=9 and the equivalent LF−EF calculation for the same activity. Reconcile the result with the current approved decision baseline.
  4. Subtracting AC from EV gives cost variance, not the schedule variance requested by the case.

Explanation

Correct Answer

B:

This checks the actual mechanism rather than merely declaring success: Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Retain the initiating evidence for audit. The desired observed result is The report correctly flags less budgeted work earned than planned rather than asserting a literal 15-day delay. The result is recorded in the project controls. [R158 R158-Q0346; case R158-C087; CAPM domain 2, task 2.2; source EVM.]

Incorrect Answers

A:

This option concerns a different Predictive project schedule and methods situation: Two parallel activities lead to the same milestone: engineering takes 8 days, procurement 13 days, followed by a common 4-day commissioning task. For the reported case, use this verification: Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Retain the initiating evidence for audit.

C:

This option concerns a different Predictive project schedule and methods situation: An activity can start no earlier than project day 5 but can start as late as day 9 without delaying the current network completion. For the reported case, use this verification: Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Retain the initiating evidence for audit.

D:

This is a tempting but unsupported shortcut in this case: Subtracting AC from EV gives cost variance, not the schedule variance requested by the case. It does not show that The report correctly flags less budgeted work earned than planned rather than asserting a literal 15-day delay. The result is recorded in the project controls. [R158 R158-Q0346; case R158-C087; CAPM domain 2, task 2.2; source EVM.]

Question 347

Which statement most accurately flags a misleading shortcut to avoid in this Schedule-variance-sign case? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A predictive project has PV=$90,000 and EV=$75,000 at the review date. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Subtracting AC from EV gives cost variance, not the schedule variance requested by the case.
  2. Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Retain the initiating evidence for audit.
  3. Calculate schedule variance as EV minus PV, yielding negative $15,000 of budget-valued schedule variance. Record the rationale before the next commitment.
  4. The report correctly flags less budgeted work earned than planned rather than asserting a literal 15-day delay. The result is recorded in the project controls.

Explanation

Correct Answer

A:

The shortcut is mistaken: Subtracting AC from EV gives cost variance, not the schedule variance requested by the case. The appropriate response is to calculate schedule variance as EV minus PV, yielding negative $15,000 of budget-valued schedule variance. Record the rationale before the next commitment.

Incorrect Answers

B:

This is an appropriate independent test of the proposed decision: Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Retain the initiating evidence for audit. It is not the invalid shortcut.

C:

This is a supported decision, not the unsupported claim: Calculate schedule variance as EV minus PV, yielding negative $15,000 of budget-valued schedule variance. Record the rationale before the next commitment. It responds to the actual project issue: A predictive project has PV=$90,000 and EV=$75,000 at the review date.

D:

This is a relevant outcome to seek after the decision: The report correctly flags less budgeted work earned than planned rather than asserting a literal 15-day delay. The result is recorded in the project controls. It is not an unsupported assumption.

Question 348

Select TWO case-specific elements of a justified Schedule-variance-sign resolution : the decision and its direct evidence. During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A predictive project has PV=$90,000 and EV=$75,000 at the review date. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Subtracting AC from EV gives cost variance, not the schedule variance requested by the case.
  2. Apply the approved quality plan's sampling and defect criteria and escalate nonconforming test results. Record the rationale before the next commitment.
  3. Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline.
  4. Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Retain the initiating evidence for audit.
  5. Calculate schedule variance as EV minus PV, yielding negative $15,000 of budget-valued schedule variance. Record the rationale before the next commitment.

Explanation

Correct Answer

D:

This checks the actual mechanism rather than merely declaring success: Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Retain the initiating evidence for audit. The desired observed result is The report correctly flags less budgeted work earned than planned rather than asserting a literal 15-day delay. The result is recorded in the project controls. [R158 R158-Q0348; case R158-C087; CAPM domain 2, task 2.2; source EVM.]

E:

The case evidence identifies A predictive project has PV=$90,000 and EV=$75,000 at the review date. The specified decision directly addresses it: Calculate schedule variance as EV minus PV, yielding negative $15,000 of budget-valued schedule variance. Record the rationale before the next commitment. This can be checked using Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Retain the initiating evidence for audit. [R158 R158-Q0348; case R158-C087; CAPM domain 2, task 2.2; source EVM.]

Incorrect Answers

A:

This is a tempting but unsupported shortcut in this case: Subtracting AC from EV gives cost variance, not the schedule variance requested by the case. It does not show that The report correctly flags less budgeted work earned than planned rather than asserting a literal 15-day delay. The result is recorded in the project controls. [R158 R158-Q0348; case R158-C087; CAPM domain 2, task 2.2; source EVM.]

B:

The proposed action (Apply the approved quality plan's sampling and defect criteria and escalate nonconforming test results. Record the rationale before the next commitment.) comes from a different Predictive project schedule and methods situation: A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. It does not resolve or independently test the stated issue: A predictive project has PV=$90,000 and EV=$75,000 at the review date. Here, the relevant check is Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Retain the initiating evidence for audit. [R158 R158-Q0348; case R158-C087; CAPM domain 2, task 2.2; source EVM.]

C:

This option concerns a different Predictive project schedule and methods situation: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. For the reported case, use this verification: Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Retain the initiating evidence for audit.

Question 349

Which project-management decision best addresses the Schedule-variance-sign situation ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A predictive project has PV=$90,000 and EV=$75,000 at the review date. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Document impacted stakeholders and the decision owner at the review.
  2. Calculate schedule variance as EV minus PV, yielding negative $15,000 of budget-valued schedule variance. Document impacted stakeholders and the decision owner at the review.
  3. Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Record the rationale before the next commitment.
  4. Subtracting AC from EV gives cost variance, not the schedule variance requested by the case.

Explanation

Correct Answer

B:

The case evidence identifies A predictive project has PV=$90,000 and EV=$75,000 at the review date. The specified decision directly addresses it: Calculate schedule variance as EV minus PV, yielding negative $15,000 of budget-valued schedule variance. Document impacted stakeholders and the decision owner at the review. This can be checked using Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Reconcile the result with the current approved decision baseline. [R158 R158-Q0349; case R158-C088; CAPM domain 2, task 2.2; source EVM.]

Incorrect Answers

A:

The proposed action (Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Document impacted stakeholders and the decision owner at the review.) comes from a different Predictive project schedule and methods situation: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. It does not resolve or independently test the stated issue: A predictive project has PV=$90,000 and EV=$75,000 at the review date. Here, the relevant check is Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Reconcile the result with the current approved decision baseline. [R158 R158-Q0349; case R158-C088; CAPM domain 2, task 2.2; source EVM.]

C:

The proposed action (Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Record the rationale before the next commitment.) comes from a different Predictive project schedule and methods situation: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. It does not resolve or independently test the stated issue: A predictive project has PV=$90,000 and EV=$75,000 at the review date. Here, the relevant check is Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Reconcile the result with the current approved decision baseline. [R158 R158-Q0349; case R158-C088; CAPM domain 2, task 2.2; source EVM.]

D:

This is a tempting but unsupported shortcut in this case: Subtracting AC from EV gives cost variance, not the schedule variance requested by the case. It does not show that The report correctly flags less budgeted work earned than planned rather than asserting a literal 15-day delay. The decision can be traced to the review evidence. [R158 R158-Q0349; case R158-C088; CAPM domain 2, task 2.2; source EVM.]

Question 350

After a corrective decision on Schedule-variance-sign, which independent evidence most directly verifies the result ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A predictive project has PV=$90,000 and EV=$75,000 at the review date. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Reconcile the result with the current approved decision baseline.
  2. Subtracting AC from EV gives cost variance, not the schedule variance requested by the case.
  3. Review sample size, critical defect count and the agreed acceptance limit. Reconcile the result with the current approved decision baseline.
  4. Calculate both path lengths as 8+4=12 and 13+4=17 days and inspect the dependency network. Retain the initiating evidence for audit.

Explanation

Correct Answer

A:

This checks the actual mechanism rather than merely declaring success: Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Reconcile the result with the current approved decision baseline. The desired observed result is The report correctly flags less budgeted work earned than planned rather than asserting a literal 15-day delay. The decision can be traced to the review evidence. [R158 R158-Q0350; case R158-C088; CAPM domain 2, task 2.2; source EVM.]

Incorrect Answers

B:

This is a tempting but unsupported shortcut in this case: Subtracting AC from EV gives cost variance, not the schedule variance requested by the case. It does not show that The report correctly flags less budgeted work earned than planned rather than asserting a literal 15-day delay. The decision can be traced to the review evidence. [R158 R158-Q0350; case R158-C088; CAPM domain 2, task 2.2; source EVM.]

C:

This option concerns a different Predictive project schedule and methods situation: A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. For the reported case, use this verification: Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Reconcile the result with the current approved decision baseline.

D:

This option concerns a different Predictive project schedule and methods situation: Two parallel activities lead to the same milestone: engineering takes 8 days, procurement 13 days, followed by a common 4-day commissioning task. For the reported case, use this verification: Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Reconcile the result with the current approved decision baseline.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

UP

SPECIAL OFFER: GET 10% OFF

This is ONE TIME OFFER

ExamSnap Discount Offer
Enter Your Email Address to Receive Your 10% Off Discount Code

A confirmation link will be sent to this email address to verify your login. *We value your privacy. We will not rent or sell your email address.

Download Free Demo of VCE Exam Simulator

Experience Avanset VCE Exam Simulator for yourself.

Simply submit your e-mail address below to get started with our interactive software demo of your free trial.

Free Demo Limits: In the demo version you will be able to access only first 5 questions from exam.