Question 360
Which observed result supports acceptance of the WBS-deliverable-decomposition corrective decision ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A project WBS has vague headings such as weekly calls and team morale but lacks identifiable deliverables for the security audit. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- The WBS covers authorized outputs without mistaking recurring meetings for the deliverables themselves. The decision can be traced to the review evidence.
- The milestone is based on the 17-day longest network path and the shorter branch has five days of path-length margin. The result is recorded in the project controls.
- A calendar of recurring activities does not replace deliverable-oriented scope decomposition.
- The activity has four days of total float before it threatens the controlling finish date. The decision can be traced to the review evidence.
Explanation
Correct Answer
A:The stated result demonstrates the case acceptance condition: The WBS covers authorized outputs without mistaking recurring meetings for the deliverables themselves. The decision can be traced to the review evidence. It depends on the decision Decompose the approved project scope into deliverable-oriented components and work packages that can be planned and controlled. Document impacted stakeholders and the decision owner at the review.
Incorrect Answers
B:The proposed outcome (The milestone is based on the 17-day longest network path and the shorter branch has five days of path-length margin. The result is recorded in the project controls.) comes from a different Predictive project schedule and methods situation: Two parallel activities lead to the same milestone: engineering takes 8 days, procurement 13 days, followed by a common 4-day commissioning task. It does not resolve or independently test the stated issue: A project WBS has vague headings such as weekly calls and team morale but lacks identifiable deliverables for the security audit. Here, the relevant check is Trace work packages to scoped audit deliverables and identify the accountable control or acceptance point. Reconcile the result with the current approved decision baseline. [R158 R158-Q0360; case R158-C090; CAPM domain 2, task 2.2; source ECO.]
C:This is a tempting but unsupported shortcut in this case: A calendar of recurring activities does not replace deliverable-oriented scope decomposition. It does not show that The WBS covers authorized outputs without mistaking recurring meetings for the deliverables themselves. The decision can be traced to the review evidence. [R158 R158-Q0360; case R158-C090; CAPM domain 2, task 2.2; source ECO.]
D:This option concerns a different Predictive project schedule and methods situation: An activity can start no earlier than project day 5 but can start as late as day 9 without delaying the current network completion. For the reported case, use this verification: Trace work packages to scoped audit deliverables and identify the accountable control or acceptance point. Reconcile the result with the current approved decision baseline.
Question 361
Which project-management decision best addresses the Work-package-versus-activity situation ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Identify the procurement branch as the controlling longer path and plan the milestone at 17 days, assuming no other constraints. Document impacted stakeholders and the decision owner at the review.
- Evaluate the integrated impact on scope, schedule, cost, interfaces and approvals before altering baselines. Record the rationale before the next commitment.
- Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Record the rationale before the next commitment.
- Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty.
Explanation
Correct Answer
C:The case evidence identifies A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. The specified decision directly addresses it: Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Record the rationale before the next commitment. This can be checked using Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Retain the initiating evidence for audit. [R158 R158-Q0361; case R158-C091; CAPM domain 2, task 2.2; source ECO.]
Incorrect Answers
A:This option concerns a different Predictive project schedule and methods situation: Two parallel activities lead to the same milestone: engineering takes 8 days, procurement 13 days, followed by a common 4-day commissioning task. For the reported case, use this verification: Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Retain the initiating evidence for audit.
B:The proposed action (Evaluate the integrated impact on scope, schedule, cost, interfaces and approvals before altering baselines. Record the rationale before the next commitment.) comes from a different Predictive project schedule and methods situation: A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost. It does not resolve or independently test the stated issue: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. Here, the relevant check is Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Retain the initiating evidence for audit. [R158 R158-Q0361; case R158-C091; CAPM domain 2, task 2.2; source ECO.]
D:This is a tempting but unsupported shortcut in this case: Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty. It does not show that Scope control and schedule execution operate at appropriate levels of detail. The result is recorded in the project controls. [R158 R158-Q0361; case R158-C091; CAPM domain 2, task 2.2; source ECO.]
Question 362
After a corrective decision on Work-package-versus-activity, which independent evidence most directly verifies the result ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Retain the initiating evidence for audit.
- Check 75,000−90,000=−15,000 and distinguish this cost-denominated metric from calendar days. Reconcile the result with the current approved decision baseline.
- Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty.
- Trace work packages to scoped audit deliverables and identify the accountable control or acceptance point. Retain the initiating evidence for audit.
Explanation
Correct Answer
A:This checks the actual mechanism rather than merely declaring success: Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Retain the initiating evidence for audit. The desired observed result is Scope control and schedule execution operate at appropriate levels of detail. The result is recorded in the project controls. [R158 R158-Q0362; case R158-C091; CAPM domain 2, task 2.2; source ECO.]
Incorrect Answers
B:This option concerns a different Predictive project schedule and methods situation: A predictive project has PV=$90,000 and EV=$75,000 at the review date. For the reported case, use this verification: Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Retain the initiating evidence for audit.
C:This is a tempting but unsupported shortcut in this case: Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty. It does not show that Scope control and schedule execution operate at appropriate levels of detail. The result is recorded in the project controls. [R158 R158-Q0362; case R158-C091; CAPM domain 2, task 2.2; source ECO.]
D:This option concerns a different Predictive project schedule and methods situation: A project WBS has vague headings such as weekly calls and team morale but lacks identifiable deliverables for the security audit. For the reported case, use this verification: Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Retain the initiating evidence for audit.
Question 363
Which statement most accurately flags a misleading shortcut to avoid in this Work-package-versus-activity case? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty.
- Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Record the rationale before the next commitment.
- Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Retain the initiating evidence for audit.
- Scope control and schedule execution operate at appropriate levels of detail. The result is recorded in the project controls.
Explanation
Correct Answer
A:The shortcut is mistaken: Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty. The appropriate response is to define manageable work packages and then identify, sequence and estimate the activities required to produce them. Record the rationale before the next commitment.
Incorrect Answers
B:This is a supported decision, not the unsupported claim: Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Record the rationale before the next commitment. It responds to the actual project issue: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks.
C:This is an appropriate independent test of the proposed decision: Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Retain the initiating evidence for audit. It is not the invalid shortcut.
D:This is a relevant outcome to seek after the decision: Scope control and schedule execution operate at appropriate levels of detail. The result is recorded in the project controls. It is not an unsupported assumption.
Question 364
Select TWO case-specific elements of a justified Work-package-versus-activity resolution : the decision and its direct evidence. During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Review sample size, critical defect count and the agreed acceptance limit. Reconcile the result with the current approved decision baseline.
- Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Record the rationale before the next commitment.
- Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty.
- Evaluate the integrated impact on scope, schedule, cost, interfaces and approvals before altering baselines. Record the rationale before the next commitment.
- Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Retain the initiating evidence for audit.
Explanation
Correct Answer
B:The case evidence identifies A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. The specified decision directly addresses it: Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Record the rationale before the next commitment. This can be checked using Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Retain the initiating evidence for audit. [R158 R158-Q0364; case R158-C091; CAPM domain 2, task 2.2; source ECO.]
E:This checks the actual mechanism rather than merely declaring success: Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Retain the initiating evidence for audit. The desired observed result is Scope control and schedule execution operate at appropriate levels of detail. The result is recorded in the project controls. [R158 R158-Q0364; case R158-C091; CAPM domain 2, task 2.2; source ECO.]
Incorrect Answers
A:This option concerns a different Predictive project schedule and methods situation: A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. For the reported case, use this verification: Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Retain the initiating evidence for audit.
C:This is a tempting but unsupported shortcut in this case: Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty. It does not show that Scope control and schedule execution operate at appropriate levels of detail. The result is recorded in the project controls. [R158 R158-Q0364; case R158-C091; CAPM domain 2, task 2.2; source ECO.]
D:The proposed action (Evaluate the integrated impact on scope, schedule, cost, interfaces and approvals before altering baselines. Record the rationale before the next commitment.) comes from a different Predictive project schedule and methods situation: A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost. It does not resolve or independently test the stated issue: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. Here, the relevant check is Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Retain the initiating evidence for audit. [R158 R158-Q0364; case R158-C091; CAPM domain 2, task 2.2; source ECO.]
Question 365
Which project-management decision best addresses the Work-package-versus-activity situation ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty.
- Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Document impacted stakeholders and the decision owner at the review.
- Decompose the approved project scope into deliverable-oriented components and work packages that can be planned and controlled. Document impacted stakeholders and the decision owner at the review.
- Evaluate the integrated impact on scope, schedule, cost, interfaces and approvals before altering baselines. Document impacted stakeholders and the decision owner at the review.
Explanation
Correct Answer
B:The case evidence identifies A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. The specified decision directly addresses it: Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Document impacted stakeholders and the decision owner at the review. This can be checked using Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline. [R158 R158-Q0365; case R158-C092; CAPM domain 2, task 2.2; source ECO.]
Incorrect Answers
A:This is a tempting but unsupported shortcut in this case: Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty. It does not show that Scope control and schedule execution operate at appropriate levels of detail. The decision can be traced to the review evidence. [R158 R158-Q0365; case R158-C092; CAPM domain 2, task 2.2; source ECO.]
C:This option concerns a different Predictive project schedule and methods situation: A project WBS has vague headings such as weekly calls and team morale but lacks identifiable deliverables for the security audit. For the reported case, use this verification: Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline.
D:This option concerns a different Predictive project schedule and methods situation: A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost. For the reported case, use this verification: Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline.
Question 366
After a corrective decision on Work-package-versus-activity, which independent evidence most directly verifies the result ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline.
- Calculate both path lengths as 8+4=12 and 13+4=17 days and inspect the dependency network. Reconcile the result with the current approved decision baseline.
- Review sample size, critical defect count and the agreed acceptance limit. Reconcile the result with the current approved decision baseline.
- Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty.
Explanation
Correct Answer
A:This checks the actual mechanism rather than merely declaring success: Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline. The desired observed result is Scope control and schedule execution operate at appropriate levels of detail. The decision can be traced to the review evidence. [R158 R158-Q0366; case R158-C092; CAPM domain 2, task 2.2; source ECO.]
Incorrect Answers
B:The proposed verify (Calculate both path lengths as 8+4=12 and 13+4=17 days and inspect the dependency network. Reconcile the result with the current approved decision baseline.) comes from a different Predictive project schedule and methods situation: Two parallel activities lead to the same milestone: engineering takes 8 days, procurement 13 days, followed by a common 4-day commissioning task. It does not resolve or independently test the stated issue: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. Here, the relevant check is Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline. [R158 R158-Q0366; case R158-C092; CAPM domain 2, task 2.2; source ECO.]
C:The proposed verify (Review sample size, critical defect count and the agreed acceptance limit. Reconcile the result with the current approved decision baseline.) comes from a different Predictive project schedule and methods situation: A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. It does not resolve or independently test the stated issue: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. Here, the relevant check is Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline. [R158 R158-Q0366; case R158-C092; CAPM domain 2, task 2.2; source ECO.]
D:This is a tempting but unsupported shortcut in this case: Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty. It does not show that Scope control and schedule execution operate at appropriate levels of detail. The decision can be traced to the review evidence. [R158 R158-Q0366; case R158-C092; CAPM domain 2, task 2.2; source ECO.]
Question 367
Which statement most accurately flags a misleading shortcut to avoid in this Work-package-versus-activity case? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Scope control and schedule execution operate at appropriate levels of detail. The decision can be traced to the review evidence.
- Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Document impacted stakeholders and the decision owner at the review.
- Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline.
- Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty.
Explanation
Correct Answer
D:The shortcut is mistaken: Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty. The appropriate response is to define manageable work packages and then identify, sequence and estimate the activities required to produce them. Document impacted stakeholders and the decision owner at the review.
Incorrect Answers
A:This is a relevant outcome to seek after the decision: Scope control and schedule execution operate at appropriate levels of detail. The decision can be traced to the review evidence. It is not an unsupported assumption.
B:This is a supported decision, not the unsupported claim: Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Document impacted stakeholders and the decision owner at the review. It responds to the actual project issue: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks.
C:This is an appropriate independent test of the proposed decision: Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline. It is not the invalid shortcut.
Question 368
Select TWO case-specific elements of a justified Work-package-versus-activity resolution : the decision and its direct evidence. At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Identify the procurement branch as the controlling longer path and plan the milestone at 17 days, assuming no other constraints. Record the rationale before the next commitment.
- Review sample size, critical defect count and the agreed acceptance limit. Reconcile the result with the current approved decision baseline.
- Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty.
- Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Document impacted stakeholders and the decision owner at the review.
- Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline.
Explanation
Correct Answer
D:The case evidence identifies A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. The specified decision directly addresses it: Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Document impacted stakeholders and the decision owner at the review. This can be checked using Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline. [R158 R158-Q0368; case R158-C092; CAPM domain 2, task 2.2; source ECO.]
E:This checks the actual mechanism rather than merely declaring success: Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline. The desired observed result is Scope control and schedule execution operate at appropriate levels of detail. The decision can be traced to the review evidence. [R158 R158-Q0368; case R158-C092; CAPM domain 2, task 2.2; source ECO.]
Incorrect Answers
A:The proposed action (Identify the procurement branch as the controlling longer path and plan the milestone at 17 days, assuming no other constraints. Record the rationale before the next commitment.) comes from a different Predictive project schedule and methods situation: Two parallel activities lead to the same milestone: engineering takes 8 days, procurement 13 days, followed by a common 4-day commissioning task. It does not resolve or independently test the stated issue: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. Here, the relevant check is Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline. [R158 R158-Q0368; case R158-C092; CAPM domain 2, task 2.2; source ECO.]
B:The proposed verify (Review sample size, critical defect count and the agreed acceptance limit. Reconcile the result with the current approved decision baseline.) comes from a different Predictive project schedule and methods situation: A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. It does not resolve or independently test the stated issue: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. Here, the relevant check is Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline. [R158 R158-Q0368; case R158-C092; CAPM domain 2, task 2.2; source ECO.]
C:This is a tempting but unsupported shortcut in this case: Treating the total work package label as a fully analyzed activity conceals dependencies and estimating uncertainty. It does not show that Scope control and schedule execution operate at appropriate levels of detail. The decision can be traced to the review evidence. [R158 R158-Q0368; case R158-C092; CAPM domain 2, task 2.2; source ECO.]
Question 369
Which project-management decision best addresses the Quality-control-threshold situation ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Apply the approved quality plan's sampling and defect criteria and escalate nonconforming test results. Record the rationale before the next commitment.
- Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Document impacted stakeholders and the decision owner at the review.
- Compute total float as late start minus early start, giving four days under the stated unconstrained network. Document impacted stakeholders and the decision owner at the review.
- A signed inspection checklist without measured defect results cannot establish compliance with the numerical tolerance.
Explanation
Correct Answer
A:The case evidence identifies A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. The specified decision directly addresses it: Apply the approved quality plan's sampling and defect criteria and escalate nonconforming test results. Record the rationale before the next commitment. This can be checked using Review sample size, critical defect count and the agreed acceptance limit. Retain the initiating evidence for audit. [R158 R158-Q0369; case R158-C093; CAPM domain 2, task 2.2; source ECO.]
Incorrect Answers
B:The proposed action (Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Document impacted stakeholders and the decision owner at the review.) comes from a different Predictive project schedule and methods situation: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. It does not resolve or independently test the stated issue: A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. Here, the relevant check is Review sample size, critical defect count and the agreed acceptance limit. Retain the initiating evidence for audit. [R158 R158-Q0369; case R158-C093; CAPM domain 2, task 2.2; source ECO.]
C:The proposed action (Compute total float as late start minus early start, giving four days under the stated unconstrained network. Document impacted stakeholders and the decision owner at the review.) comes from a different Predictive project schedule and methods situation: An activity can start no earlier than project day 5 but can start as late as day 9 without delaying the current network completion. It does not resolve or independently test the stated issue: A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. Here, the relevant check is Review sample size, critical defect count and the agreed acceptance limit. Retain the initiating evidence for audit. [R158 R158-Q0369; case R158-C093; CAPM domain 2, task 2.2; source ECO.]
D:This is a tempting but unsupported shortcut in this case: A signed inspection checklist without measured defect results cannot establish compliance with the numerical tolerance. It does not show that Quality evidence demonstrates whether delivered units meet the defined requirement. The result is recorded in the project controls. [R158 R158-Q0369; case R158-C093; CAPM domain 2, task 2.2; source ECO.]
Question 370
After a corrective decision on Quality-control-threshold, which independent evidence most directly verifies the result ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- A signed inspection checklist without measured defect results cannot establish compliance with the numerical tolerance.
- Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline.
- Review sample size, critical defect count and the agreed acceptance limit. Retain the initiating evidence for audit.
- Trace work packages to scoped audit deliverables and identify the accountable control or acceptance point. Retain the initiating evidence for audit.
Explanation
Correct Answer
C:This checks the actual mechanism rather than merely declaring success: Review sample size, critical defect count and the agreed acceptance limit. Retain the initiating evidence for audit. The desired observed result is Quality evidence demonstrates whether delivered units meet the defined requirement. The result is recorded in the project controls. [R158 R158-Q0370; case R158-C093; CAPM domain 2, task 2.2; source ECO.]
Incorrect Answers
A:This is a tempting but unsupported shortcut in this case: A signed inspection checklist without measured defect results cannot establish compliance with the numerical tolerance. It does not show that Quality evidence demonstrates whether delivered units meet the defined requirement. The result is recorded in the project controls. [R158 R158-Q0370; case R158-C093; CAPM domain 2, task 2.2; source ECO.]
B:The proposed verify (Inspect the WBS for bounded packages and the network for appropriately sized activities tied to them. Reconcile the result with the current approved decision baseline.) comes from a different Predictive project schedule and methods situation: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. It does not resolve or independently test the stated issue: A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. Here, the relevant check is Review sample size, critical defect count and the agreed acceptance limit. Retain the initiating evidence for audit. [R158 R158-Q0370; case R158-C093; CAPM domain 2, task 2.2; source ECO.]
D:The proposed verify (Trace work packages to scoped audit deliverables and identify the accountable control or acceptance point. Retain the initiating evidence for audit.) comes from a different Predictive project schedule and methods situation: A project WBS has vague headings such as weekly calls and team morale but lacks identifiable deliverables for the security audit. It does not resolve or independently test the stated issue: A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. Here, the relevant check is Review sample size, critical defect count and the agreed acceptance limit. Retain the initiating evidence for audit. [R158 R158-Q0370; case R158-C093; CAPM domain 2, task 2.2; source ECO.]