PMI PMP External Change and Strategic Adaptation Practice Test
Topic 27 covers external change and strategic adaptation for the PMI Project Management Professional (PMP) certification. These original scenarios apply the July 2026 exam objectives across predictive, agile and hybrid projects. Use the stated constraints to select one answer unless the question specifies otherwise. For broader preparation, visit the PMP Exam Dumps page. Each option has an explanation of its role in the decision.
Question 1
A project’s market-entry assumption depends on a proposed import rule taking effect next year. The proposal is under consultation, and the responsible authority has not issued a final decision. What should the project manager recommend now?
Correct Answer: E
Correct Answer
Answer E is correct because the proposal is relevant but not yet a settled constraint. Scenarios preserve preparation, while a verification route and trigger connect future evidence to an authorized decision.
Incorrect Answers
Answer A is incorrect because the authority has not finalized the rule. Treating the proposal as enacted would convert uncertainty into a false planning fact rather than assess alternative outcomes.
Answer B is incorrect because the proposal could affect a material market-entry assumption. Recording and analyzing it now supports timely response without claiming that it will become law.
Answer C is incorrect because the consultation deadline governs feedback, not when a final rule becomes applicable. Conflating these dates creates a false project constraint rather than a verified decision trigger.
Answer D is incorrect because some commitments may need to wait, but the stem does not establish that every activity creates unacceptable exposure. Scenario analysis can identify proportionate preparatory work and decision points without an indiscriminate freeze.
Question 2
A project owes EUR 200,000 at delivery. A written forward agreement fixes the dollar cost of 70% of that payment at USD 1.10 per EUR; only the remaining 30% is converted at the planning rate. That rate rises from USD 1.10 to USD 1.20 per EUR. The supplier price is unchanged, and fees are excluded. How much does the estimated total dollar payment increase?
Correct Answer: D
Correct Answer
Answer D is correct because the exposed amount is 200,000 × 30% = EUR 60,000. Applying the USD 0.10 rate increase to that portion gives USD 6,000. The fixed portion remains USD 154,000; the total changes from USD 220,000 to USD 226,000.
Incorrect Answers
Answer A is incorrect because the agreement fixes only 70% of the payment, not all of it. The remaining 30% still changes with the planning rate, so the partial hedge reduces the exposure but does not eliminate it.
Answer B is incorrect because this applies the USD 0.10 movement to the entire EUR 200,000. It would describe an unhedged payment, but the written agreement fixes the dollar cost of 70% and leaves only 30% exposed.
Answer C is incorrect because this applies the rate movement to the EUR 140,000 covered by the agreement. That portion is precisely the part whose dollar cost is fixed; the EUR 60,000 uncovered portion creates the increase.
Answer E is incorrect because this is the revised total payment: EUR 140,000 at 1.10 plus EUR 60,000 at 1.20. The question asks for the increase from the USD 220,000 original total, which is USD 6,000.
Question 3
A competitor announces a product feature similar to one planned for a Scrum Team’s product. No customer research has yet tested whether this changes demand. Which TWO actions best inform the next product decision? Choose TWO.
Correct Answers: B, D
Correct Answers
Answer B is correct because the announcement may change expectations, but the actual effect on this product’s users is unverified. Targeted evidence can inform whether and how the product should respond.
Answer D is correct because competitive information affects product choices through its implications for value. The Product Owner can evaluate those implications alongside the existing goal and alternatives.
Incorrect Answers
Answer A is incorrect because stating that the goal is unchanged does not establish capacity or protect it from unexamined scope additions. The announcement first needs value assessment, followed by appropriate collaboration on any Sprint scope adjustment.
Answer C is incorrect because a feature announcement identifies a market signal, not the intended segment’s willingness to use or pay for it. Targeted customer evidence is needed before treating the feature as a demand requirement.
Answer E is incorrect because long-term evidence could improve the comparison, but the team can investigate customer relevance and differentiation now. Waiting for a fixed year sacrifices a timely product decision without a stated need.
Answer F is incorrect because being second does not establish that the feature lacks value. Customer needs, differentiation and delivery economics remain relevant.
Question 4
A vendor announces the end of support for a platform six months before the project’s planned operating period ends. The contract does not include extended support. What analysis is most useful for the steering committee?
Correct Answer: E
Correct Answer
Answer E is correct because the announcement affects the intended operating period, not just installation. Decision makers need the consequences and alternatives, including continuity, compatibility and transition effort.
Incorrect Answers
Answer A is incorrect because purchase prices are only one part of responding to the support gap. Compatibility, transition effort and continuity through the intended operating period can change which option is feasible and valuable.
Answer B is incorrect because extended support may be worth investigating, but it is not in the contract and its price is unconfirmed. The committee should distinguish a possible option from an established supported operating plan.
Answer C is incorrect because finishing may still be an option, but deferral without analysis moves a known lifecycle exposure into operations. The steering committee needs to evaluate it before further commitments constrain alternatives.
Answer D is incorrect because completion helps describe status but does not establish a viable supported operating period. The committee needs forward-looking options for the newly exposed lifecycle gap.
Question 5
A demand forecast used in a business case predates a major regional economic slowdown. Analysts provide credible high, central and low demand estimates, but no defensible probabilities. What is the most appropriate analysis?
Correct Answer: C
Correct Answer
Answer C is correct because the estimates support examining how outcomes change under different demand levels. They do not support a probability-weighted expected value unless credible probabilities are established.
Incorrect Answers
Answer A is incorrect because a central scenario can organize discussion, but using it alone hides the stated range and its viability consequences. No probabilities establish that it is an adequate substitute for evaluating the downside and upside.
Answer B is incorrect because three scenarios do not imply equal likelihood. That assumption would create a numerical expected value without an evidential basis for its weights.
Answer D is incorrect because an arithmetic average assigns equal weight whether or not that weighting is justified. Without defensible probabilities, it should not be represented as a probability-based forecast.
Answer E is incorrect because the credible slowdown evidence already challenges the forecast. Waiting for realized sales would postpone reassessment until after additional resources may have been committed on an outdated assumption.
Question 6
A change in public transport reduces access to a proposed service center for the project’s main user population. The building design still meets its approved specifications. What should the project manager do next?
Correct Answer: A
Correct Answer
Answer A is correct because the external change may undermine the reason for the center despite compliant construction. Evaluating user access connects the new condition to the project’s outcome rather than only its physical specifications.
Incorrect Answers
Answer B is incorrect because operations will be affected, but the access change can alter the project’s current benefits case. Deferring the issue without analysis may lock in a service center that cannot achieve its intended reach.
Answer C is incorrect because relocation may be an option, but it has not been shown superior to transport or service changes. The first analysis should establish the outcome impact and feasible responses before a costly redesign.
Answer D is incorrect because that may describe one scenario, but adopting it as the new target without evaluation changes the intended service coverage. The sponsor needs the impact and alternatives before accepting a reduced outcome.
Answer E is incorrect because real utilization could refine the estimate, but the known transport change is decision-relevant now. Early assessment preserves options that may become expensive or unavailable after construction finishes.
Question 7
A drought creates a credible risk that a manufacturing pilot will receive less cooling water. The project can trial a recirculation design but needs facilities approval to modify equipment. Which TWO actions are justified now? Choose TWO.
Correct Answers: D, E
Correct Answers
Answer D is correct because the external condition matters through the amount and timing of water the pilot needs. That comparison establishes the practical exposure before choosing a response.
Answer E is correct because a trial can reduce uncertainty about an available adaptation. Obtaining facilities approval preserves the stated equipment-change authority.
Incorrect Answers
Answer A is incorrect because a general estimate may inform a hypothesis but does not validate this installation’s performance. The available trial can test the adaptation under relevant conditions before relying on it.
Answer B is incorrect because a time allowance cannot show whether the pilot can operate under reduced supply or whether recirculation helps. The response needs a link between the external constraint and specific operating requirements.
Answer C is incorrect because historic consumption may not reflect the reduced availability or current pilot conditions. The project should assess the new constraint and options rather than assume a reservation alone resolves the exposure.
Answer F is incorrect because the option may be useful, but committing to full equipment before a bounded test assumes its suitability. The stated opportunity is to reduce uncertainty through an authorized trial first.
Question 8
A sponsor proposes continuing a product because USD 2 million has already been spent. A verified market shift means the remaining USD 500,000 investment is expected to yield only USD 300,000 in additional cash benefit, with no other required obligations or material benefits. What should the project manager recommend?
Correct Answer: A
Correct Answer
Answer A is correct because the stated future cash benefit is below the remaining investment, and no other obligation or material benefit is identified. Prior expenditure does not make the incremental case favorable.
Incorrect Answers
Answer B is incorrect because a positive benefit does not by itself justify the USD 500,000 needed to obtain it. The comparison must include the remaining cost.
Answer C is incorrect because the past expenditure has already occurred and cannot be recovered by labeling the project complete. The continuation decision should assess what additional commitment can achieve.
Answer D is incorrect because available funding addresses affordability, not whether the future investment is justified. It does not change the stated $300,000 incremental benefit or eliminate the $200,000 shortfall.
Answer E is incorrect because the verified shift affects the value of committing another $500,000 now. Waiting for an old milestone can consume funds without resolving the unfavorable incremental case.
Question 9
A new trade restriction may affect a critical component sourced through two distributors. Both distributors obtain it from the same factory in the affected country. What is the key implication for the project’s response analysis?
Correct Answer: C
Correct Answer
Answer C is correct because two commercial channels do not provide independent supply when the same restricted factory supplies both. The response analysis must examine the underlying source dependency.
Incorrect Answers
Answer A is incorrect because financial strength may affect resilience, but it does not change the shared factory in the restricted country. Origin-related fulfillment exposure remains in both commercial channels.
Answer B is incorrect because logistics paths may differ after production, but the component still comes from one factory. Route diversity does not establish independence from a restriction affecting that origin.
Answer D is incorrect because the number of orders does not remove a shared upstream factory exposure. Both channels may be disrupted by the same restriction.
Answer E is incorrect because splitting orders can reduce distributor-specific exposure, but both still depend on the same affected source. It cannot be treated as a complete response to the stated upstream restriction.
Question 10
A project’s value depends on a government grant that will be decided in three months. A limited design study can be completed now and reused under either outcome. Full construction would create a large unrecoverable commitment. What is the most useful proposal for the sponsor?
Correct Answer: C
Correct Answer
Answer C is correct because the bounded work can add useful information or readiness under either grant outcome. It preserves flexibility before the uncertain funding decision rather than forcing an immediate full commitment.
Incorrect Answers
Answer A is incorrect because this avoids spending but also defers work explicitly useful under either outcome. The sponsor can evaluate the bounded study separately from the large irreversible construction commitment.
Answer B is incorrect because knowing when a decision is expected does not establish its outcome. Construction should remain contingent on the authorized funding and viability decision rather than an assumed favorable result.
Answer D is incorrect because the phased label does not show that the construction commitment is recoverable or useful without the grant. The reusable study offers progress while preserving a later funding-dependent decision.
Answer E is incorrect because deferring payment does not necessarily defer the contractual commitment or cancellation exposure. The proposal must be evaluated by recoverability and obligations, not just cash timing.
Question 11
A new external privacy requirement will apply to one region before launch. The organization’s legal specialist confirms that the other regions are outside its scope. Which THREE inputs should the project manager bring to the release decision? Choose THREE.
Correct Answers: A, D, F
Correct Answers
Answer A is correct because the response needs a clear boundary based on the confirmed interpretation. This prevents both omission of affected work and unsupported assumptions about unaffected regions.
Answer D is correct because decision makers must know what compliant readiness requires and how it interacts with the release plan. Applicability alone does not establish feasibility.
Answer F is correct because the project can compare coordinated or regional sequencing while preserving the stated requirement. The appropriate authority needs the implications before selecting an option.
Incorrect Answers
Answer B is incorrect because exemption removes one constraint but does not establish operational independence. Shared components, support and business consequences still need evaluation before a regional sequence is selected.
Answer C is incorrect because the statement identifies where the obligation applies, not whether the design changes are implemented or feasible in time. Delivery impact and authorized options remain necessary decision inputs.
Answer E is incorrect because the verified applicability is regional. A global delay might be justified by coupled architecture or business needs, but it cannot be inferred solely from the rule’s existence.
Question 12
A supplier offers a new technology that could reduce operating cost. Its demonstration used a workload unlike the project’s, and switching would require retraining. What should the project evaluate before recommending adoption?
Correct Answer: A
Correct Answer
Answer A is correct because the demonstration does not establish fit for this project’s workload. A meaningful comparison includes validated operating effects together with retraining and other transition costs.
Incorrect Answers
Answer B is incorrect because that percentage was demonstrated under different conditions and excludes stated retraining. It is insufficient for the project’s actual decision.
Answer C is incorrect because retraining is a consequence of switching regardless of which department pays for it. Excluding it can overstate the net advantage and distort the timing and feasibility of adoption.
Answer D is incorrect because a reference can strengthen a hypothesis, but similarity alone does not establish performance on this project’s work. The known demonstration mismatch and retraining burden still require relevant evaluation.
Answer E is incorrect because the proposed benefit and retraining burden both occur beyond purchase. Excluding them would omit the main reasons to consider or reject the switch.
Question 13
A strategic review changes the organization’s priority from rapid geographic expansion to retention of current customers. The project charter still emphasizes entering three new markets. What should the project manager arrange?
Correct Answer: E
Correct Answer
Answer E is correct because the project objective may no longer support the current strategy. The sponsor and relevant decision owners should assess whether to adapt, continue with justification or stop the remaining investment.
Incorrect Answers
Answer A is incorrect because the new strategy creates a reason to propose changes, but it does not automatically authorize the team to repurpose the project budget. The sponsor needs an explicit comparison of remaining options and obligations.
Answer B is incorrect because a pause may be one response, but indiscriminate suspension can create avoidable cost or breach current commitments. An authorized options review should consider these consequences alongside alignment.
Answer C is incorrect because completion of the approved scope may still be justified, but the verified strategic change must inform that decision now. Sequencing review after completion risks spending remaining funds on an outdated purpose.
Answer D is incorrect because milestones show progress against scope, not whether that scope still supports the revised strategy. A direct change in organizational priority warrants a timely sponsor review.
Question 14
A market indicator is being monitored as an early warning for a project. Reports record its value every month, but nobody is responsible for acting when it crosses the agreed threshold. Which TWO additions make the monitoring actionable? Choose TWO.
Correct Answers: D, F
Correct Answers
Answer D is correct because a trigger needs an accountable response role. Without one, recording the indicator can continue while the condition that should prompt a decision goes unattended.
Answer F is correct because the indicator must connect to a timely action or authorized review. A route and timeframe turn the signal into a usable governance mechanism.
Incorrect Answers
Answer A is incorrect because a register entry preserves visibility but does not define who must act on a threshold crossing or how quickly. Waiting for a routine review may miss the intended early-warning response window.
Answer B is incorrect because an unconfirmed assumption is not a defined response arrangement. The monitoring needs explicit ownership and a known decision path.
Answer C is incorrect because more frequent observations may detect the condition earlier, but detection is not the missing capability. Without an owner and decision route, the signal can still go unanswered.
Answer E is incorrect because automation can deliver the signal, but the substantive assessment still needs an accountable role. An alert alone does not create a response obligation or authorized decision path.
Question 15
A project compares two locations. A credible energy-price change increases Site A’s annual operating estimate from USD 120,000 to USD 180,000. Site B remains USD 150,000 annually. All other relevant costs and benefits are equal for the comparison. What does the revised evidence support?
Correct Answer: A
Correct Answer
Answer A is correct because the revised comparison is 180,000 minus 150,000, giving USD 30,000 annually in favor of Site B. The original advantage for Site A no longer holds.
Incorrect Answers
Answer B is incorrect because the original comparison used 120,000 against 150,000. The external price change invalidates that operating-cost advantage under the stated equal-other-factors assumption.
Answer C is incorrect because the $60,000 amount is an increase in Site A’s own estimate, not a saving against Site B. The comparison must use the revised $180,000 and $150,000 annual figures.
Answer D is incorrect because the USD 60,000 figure is Site A’s increase relative to its own previous estimate. The current annual difference between the two sites is USD 30,000, favoring Site B.
Answer E is incorrect because that amount halves the current $30,000 difference without a stated sharing or half-year assumption. Both estimates are annual, so they should be compared on that same full-year basis.
Question 16
A new industry standard has been published. The project’s contract requires a named older edition, and the customer has not requested a change. What should the project manager do first?
Correct Answer: A
Correct Answer
Answer A is correct because publication alone does not establish that the new edition replaces the explicitly contracted one. The project should determine obligations and evaluate any proposed update through the agreed mechanism.
Incorrect Answers
Answer B is incorrect because implementing before an agreed change can create unapproved work and a commercial dispute. Publication alone does not replace the contract’s named edition or authorize the additional cost.
Answer C is incorrect because the publication may affect future operation or other applicable obligations. A project-specific assessment is appropriate now even though the contract does not automatically change.
Answer D is incorrect because that can create acceptance criteria different from the agreed requirement. Technical preference cannot silently amend the edition against which the deliverable is judged.
Answer E is incorrect because noncompliance depends on the applicable requirement, not simply publication order. The contract currently names the older edition, subject to any separately verified obligation.
Question 17
An external labor-market shortage increases the expected cost of a scarce skill. A proposed design alternative uses an available skill but adds a maintenance dependency. What comparison should inform the design decision?
Correct Answer: E
Correct Answer
Answer E is correct because the labor change affects more than the immediate staffing rate. The alternative’s maintenance dependency must be compared with delivery feasibility and ongoing costs before selecting a design.
Incorrect Answers
Answer A is incorrect because contingency can cover an exposure, but availability of funds does not establish that the original design is now the better choice. The feasible alternative and its maintenance effects still need comparison.
Answer B is incorrect because hourly rates omit productivity, skill suitability and the stated maintenance dependency. A lower rate alone may not yield a better lifecycle outcome.
Answer C is incorrect because the build-phase advantage may be offset by the new maintenance dependency. The decision affects the operating lifecycle, so the comparison should not stop at initial staffing.
Answer D is incorrect because current availability matters to delivery, but it does not resolve long-term support or total effort. The design decision spans a longer operating horizon.
Question 18
A project manager receives two conflicting market reports. One covers the intended region and current year; the other is older and describes a different customer segment. Which TWO responses are appropriate? Choose TWO.
Correct Answers: C, F
Correct Answers
Answer C is correct because the conflict may not be fully resolved by choosing one report. Focused evidence can address the assumption that materially affects the pending decision.
Answer F is correct because different populations and periods can explain apparently conflicting conclusions. Assessing relevance helps determine what each report can support for this project.
Incorrect Answers
Answer A is incorrect because sample size can improve precision for the population studied, but cannot make a different customer segment directly relevant. Scope and collection method still determine what the evidence supports.
Answer B is incorrect because independent forecasts may reasonably differ even when useful. The project needs targeted evidence and explicit uncertainty for its material assumption, not an exact agreement condition that may never occur.
Answer D is incorrect because rates from different regions, segments or periods may not describe a meaningful common quantity. Averaging them can conceal rather than resolve the mismatch.
Answer E is incorrect because recency helps relevance but does not guarantee accuracy. Method and scope still need examination.
Question 19
A supplier disruption delays a critical component by eight weeks. The project can substitute a component, resequence nondependent work, or defer launch. What should the project manager prepare for the change authority?
Correct Answer: B
Correct Answer
Answer B is correct because each option changes different aspects of the project. A structured comparison gives the authorized decision maker the tradeoffs needed to select a response.
Incorrect Answers
Answer A is incorrect because price and availability matter only if the substitute can meet the required function and interfaces. Compatibility evidence is needed before recommending it as a feasible response.
Answer C is incorrect because the available alternatives may affect the actual delay. Simple date addition skips analysis of substitution and resequencing.
Answer D is incorrect because the change authority needs a decision, not only awareness of the event. The identified alternatives should be evaluated sufficiently to support that decision.
Answer E is incorrect because productive nondependent work can reduce idle time but may not remove the critical component’s effect on launch. The remaining dependency path must be evaluated before retaining the date.
Question 20
A pilot’s business case assumes that customers can use a smartphone application. New research in the target community shows limited smartphone access but reliable basic-phone access. What is the best next step?
Correct Answer: D
Correct Answer
Answer D is correct because the research challenges the chosen channel, not necessarily the underlying customer need. Comparing accessible alternatives can preserve the intended outcome while updating the delivery approach.
Incorrect Answers
Answer A is incorrect because basic-phone access is promising evidence, but availability alone does not establish that the channel can meet the intended service outcome. Alternatives need evaluation against the actual task.
Answer B is incorrect because a narrower audience may be an option, but it changes the intended outcome and potential benefits. That tradeoff requires explicit evaluation rather than treating the access gap as a sampling adjustment.
Answer C is incorrect because that may refine usability for a subset, but it leaves the verified access barrier for the intended community unresolved. Channel evaluation should account for those unable to participate at all.
Answer E is incorrect because device provision may be feasible, but it creates cost and support obligations not yet assessed. The evidence supports comparing access options before committing to one remedy.
Question 21
A favorable external policy creates a six-month market opportunity. The project could deliver a smaller compliant product in four months or the original complete product in nine months. Scope changes require sponsor approval. What should the project manager recommend?
Correct Answer: B
Correct Answer
Answer B is correct because the opportunity may justify a different delivery boundary, but the smaller product must still provide worthwhile compliant value. The sponsor should decide using that comparison.
Incorrect Answers
Answer A is incorrect because recording the opportunity preserves awareness but does not present the feasible scope-time option for a value decision. The sponsor should compare whether adaptation is worthwhile.
Answer C is incorrect because preparing an analysis is appropriate, but implementing the changed scope commits capacity before the stated sponsor approval. Opportunity urgency does not remove that boundary.
Answer D is incorrect because feature count does not establish proportional value. Some capabilities may be essential to a usable compliant offer, so the smaller product’s benefits need direct evaluation.
Answer E is incorrect because the estimate applies to reduced scope. Transferring it to the complete product assumes capacity or productivity that the stated nine-month estimate does not support.
Question 22
The project’s strategy review identifies several external trends, but their effects on its objectives and assumptions have not yet been mapped. What is the most useful next analytical step?
Correct Answer: A
Correct Answer
Answer A is correct because a list of trends becomes useful when connected to how the project could be affected. That mapping distinguishes relevant signals from background information and identifies decisions needing attention.
Incorrect Answers
Answer B is incorrect because prominence can help identify signals but does not establish this project’s exposure or consequences. Ratings should follow the link to specific assumptions and outcomes, not media attention alone.
Answer C is incorrect because actual effects would be stronger evidence, but prospective mapping can identify decision points while options remain available. The review need not wait for a realized loss to examine relevance.
Answer D is incorrect because detailed response planning consumes effort and may target background trends with no material effect. Mapping implications first identifies which issues merit that investment.
Answer E is incorrect because speed can influence urgency, but a fast change may be immaterial to this project. Priority requires both a credible effect pathway and timing, not velocity alone.
Question 23
A project’s launch decision will be reviewed if a market index stays below 80 for three consecutive monthly observations. The latest values are 79, 82 and 78. What is the correct interpretation?
Correct Answer: E
Correct Answer
Answer E is correct because the condition requires three consecutive observations below 80. The middle value, 82, breaks the sequence, so the three reported months do not satisfy that rule.
Incorrect Answers
Answer A is incorrect because one low observation is not the stated condition. The rule requires three consecutive monthly values below the threshold.
Answer B is incorrect because a majority of low values differs from three consecutive low values. The stated rule does not use a two-out-of-three test.
Answer C is incorrect because the higher observation breaks the current sequence but does not retire the trigger. Future consecutive observations may still meet it.
Answer D is incorrect because the average is about 79.67, but the rule is based on consecutive individual observations. Substituting an average would change the agreed trigger.
Question 24
A new data-hosting restriction has been confirmed by the organization’s legal team. Two architecture options appear compliant, but one creates a long-term dependency on a single vendor. Which TWO considerations should enter the recommendation? Choose TWO.
Correct Answers: A, E
Correct Answers
Answer A is correct because the recommendation needs a verified basis for its required compliance claim. An initial appearance of compliance should be checked against the legal interpretation and actual design.
Answer E is correct because both options may meet the immediate requirement while differing in future flexibility and cost. The long-term dependency is a material tradeoff for the authorized decision.
Incorrect Answers
Answer B is incorrect because time matters for meeting the requirement, but both alternatives still need evaluation beyond initial readiness. A faster change can create a costly or inflexible long-term dependency.
Answer C is incorrect because a generic statement may not cover the project’s data flows, locations or operating design. Evidence must connect the architecture to the confirmed restriction rather than rely solely on a marketing or contract label.
Answer D is incorrect because initial price excludes later operating, transition and exit costs. The stated dependency is one reason the lifecycle comparison may differ.
Answer F is incorrect because a fixed price can reduce one cost uncertainty during the term. It does not establish exit feasibility, future change capacity or service continuity if the single vendor becomes unavailable.
Question 25
After several external changes, the sponsor approves a revised market strategy and benefits forecast. Team members continue using the original assumptions in their detailed plans. What should the project manager coordinate?
Correct Answer: D
Correct Answer
Answer D is correct because the authorized strategic decision must be reflected where delivery choices are made. Tracing dependencies prevents the team from executing plans based on a justification that has been replaced.
Incorrect Answers
Answer A is incorrect because the immediate issue is propagation of an approved change, not evidence that the decision needs reversal. The plans should be updated through their controlled process.
Answer B is incorrect because leads can identify impacts, but uncoordinated interpretations may produce conflicting assumptions. The project needs a common approved basis and explicit resolution of cross-workstream dependencies.
Answer C is incorrect because some work may remain valid, but a blanket rule can preserve dependencies on a superseded benefits case. The approved changes should be traced now to determine which ongoing packages are actually affected.
Answer E is incorrect because the updated forecast alone does not identify how soon dependent work needs to change. A traceability review is needed to avoid commitments made under assumptions already superseded by the approved decision.
Popular posts
Recent Posts
