PMI PMP Change Control and Approved Changes Practice Test

 

Topic 22 covers change control and approved changes for the PMI Project Management Professional (PMP) certification. These original scenarios apply the July 2026 exam objectives across predictive, agile and hybrid projects. Use the stated constraints to select one answer unless the question specifies otherwise. For broader preparation, visit the PMP Exam Dumps page. Each option has an explanation of its role in the decision.

Question 1

A predictive project’s design is baselined. A customer requests an additional inspection station and wants the team to reserve fabrication capacity today. The change procedure requires an impact assessment and approval before any new commitment. What should the manager do first?

  1. Reserve the capacity while estimating the station’s total cost.
  2. Ask the fabricator to begin detailed production planning under the original order.
  3. Replace an existing station with the new one to keep the total quantity constant.
  4. Register the request and assess its effect before committing fabrication capacity.
  5. Ask the customer to approve the estimated cost before recording the request.

Correct Answer: D

 

Correct Answer

Answer D is correct because reserving capacity would be a new commitment under the stated procedure. Recording and assessing the station request supplies the basis for approval without treating customer interest as implementation authority.

Incorrect Answers

Answer A is incorrect because early reservation could protect the schedule, but it crosses the explicit commitment boundary before approval. The assessment can identify the cost of waiting as part of the decision.

Answer B is incorrect because the original order covers the baseline, not the additional station. Using it for new committed work could create cost and contractual consequences before the change decision.

Answer C is incorrect because equal quantity does not establish equivalent scope, function or acceptance. The substitute could affect the original requirements and also needs impact assessment.

Answer E is incorrect because customer support is useful input, but the documented assessment and approval process still applies. An early cost agreement alone does not evaluate all baseline effects.

 

Question 2

A Scrum product’s governance allows the Product Owner to reorder unstarted backlog items within the approved funding and service boundaries. New customer evidence makes an existing item more valuable. The current Sprint is unaffected. What is the appropriate next step?

  1. Hold the ordering change until the next Sprint Review even though no active Sprint work is affected.
  2. Submit a funding-change request before changing any backlog order.
  3. Have the Product Owner reorder the item within the delegated boundaries.
  4. Ask each customer representative to assign a separate priority to the item.
  5. Ask Developers to replace current Sprint work with the newly favored item.

Correct Answer: C

 

Correct Answer

Answer C is correct because the decision concerns unstarted work and remains inside the expressly allowed scope. The existing backlog authority can respond to evidence without inventing a separate approval requirement for this case.

Incorrect Answers

Answer A is incorrect because a review can supply evidence for adaptation, but it is not a required approval gate for this already delegated Product Backlog decision. The Product Owner can use the new evidence within the stated boundaries now.

Answer B is incorrect because no funding or service boundary is changing. The governance rule already delegates this type of ordering decision, so a funding request would address a change that is not being proposed.

Answer D is incorrect because additional opinions may inform value, but multiple independent priority lists would not produce the single Product Owner ordering decision described by governance.

Answer E is incorrect because the scenario says the current Sprint is unaffected. Changing active work would introduce a different decision and bypass the intended backlog-ordering action.

 

Question 3

A hybrid change request proposes replacing a data interface. The review board asks for a decision-ready submission, and its procedure requires both integrated impact analysis and an executable change plan. Which two additions meet that request? Choose TWO.

  1. Use the unchanged original schedule without examining interface dependencies.
  2. Describe implementation sequencing, verification, fallback and responsible owners.
  3. Use receiving-team technical signoffs as the complete basis for approving the replacement.
  4. Obtain approval of the cost case first and develop fallback and verification plans afterward.
  5. Attach the replacement estimate and retain the downstream teams’ original commitments as fixed assumptions.
  6. Assess effects on linked services, schedule, cost, benefits and operating risk.

Correct Answers: B, F

 

Correct Answers

Answer B is correct because a justified change also needs a feasible route into service. Sequencing and fallback make the proposal executable, while owners and verification show how completion would be established.

Answer F is correct because an interface can change behavior beyond the component being replaced. Integrated analysis lets the board judge the overall consequence rather than approving an attractive local change that damages another commitment.

Incorrect Answers

Answer A is incorrect because retaining a baseline date can be an objective, but assuming it remains achievable omits the dependency analysis needed to justify that conclusion.

Answer C is incorrect because technical support is useful evidence but does not supply the integrated business impacts or execution plan the board requires. Agreement about the interface is only part of the change decision.

Answer D is incorrect because the procedure requires an executable plan in the submission. Deferring those elements would leave the board unable to assess how implementation could be verified or safely reversed when it authorizes the change.

Answer E is incorrect because a local estimate does not establish that the replacement preserves linked services, dates or operating risks. Those effects must be examined rather than assumed away in a decision-ready submission.

 

Question 4

A predictive project’s board approves a design change on condition that an additional test engineer is secured before implementation. The engineer is still unavailable, but the change appears as approved in the tracker. What should the project manager do?

  1. Start the design work and recruit the engineer before the testing phase.
  2. Keep implementation on hold until the staffing condition is met or formally revised.
  3. Update the implementation baseline now and leave the staffing condition as a later issue.
  4. Close the change request because the board has already voted on it.
  5. Ask the existing engineer to cover both assignments without changing the plan.

Correct Answer: B

 

Correct Answer

Answer B is correct because conditional approval grants permission only within its stated condition. The tracker label does not establish that the engineer exists, so implementation must wait for fulfillment or an authorized revision.

Incorrect Answers

Answer A is incorrect because that may be a reasonable alternative proposal, but it does not satisfy the board’s explicit before-implementation condition. The manager cannot silently move the required timing.

Answer C is incorrect because the unresolved condition governs whether implementation may begin. Moving it into a separate issue entry does not remove the authorization constraint.

Answer D is incorrect because a decision is not the same as implemented and verified work, and the condition remains open. Closing the record would lose visibility of the remaining prerequisite.

Answer E is incorrect because this assumes capacity that has not been secured and could weaken both test efforts. Evidence of a feasible staffing arrangement is needed before claiming the condition is met.

 

Question 5

A hybrid project’s emergency procedure authorizes the incident lead to deploy a tested rollback when a release blocks all customer transactions. It requires a change record and retrospective review within one business day. The trigger has occurred and the rollback is tested. What is the best response?

  1. Deploy the rollback and close the incident without a change review because it was preauthorized.
  2. Submit a new permanent design baseline for approval before restoring transactions.
  3. Use the emergency authorization, record the action and complete the required review.
  4. Obtain a second approval from the release manager before the incident lead acts.
  5. Wait for the normal weekly change board before using the rollback.

Correct Answer: C

 

Correct Answer

Answer C is correct because this is a predefined control route for the observed emergency, not an absence of control. Timely rollback restores service while the record and review preserve oversight of the actual change.

Incorrect Answers

Answer A is incorrect because preauthorization permits the action but does not waive the separate record and review requirements. Those steps confirm what happened and identify any consequences requiring follow-up.

Answer B is incorrect because a permanent redesign may be considered after stabilization. It is not a prerequisite to the tested emergency rollback already authorized for the immediate condition.

Answer D is incorrect because the procedure already gives the incident lead authority when this trigger is met. Requiring another approval would delay the tested rollback without addressing any stated condition of the emergency route.

Answer E is incorrect because the emergency procedure already assigns authority for this condition. Waiting for the routine meeting would prolong a total service block without adding a required approval.

 

Question 6

Two hybrid workstreams propose changes to a shared message format. Each request is affordable and individually useful, but one assumes field X is numeric while the other assumes it is text. Both are scheduled for the same release. What should the manager recommend?

  1. Move one request to the next release without examining the compatibility requirement.
  2. Let each workstream retain its preferred format and document the difference.
  3. Approve both on their individual cost cases and reconcile the interface in testing.
  4. Approve the cheaper request first and automatically reject the second.
  5. Assess the requests together and resolve the shared interface before approval.

Correct Answer: E

 

Correct Answer

Answer E is correct because isolated approval would permit incompatible assumptions to enter the same release. Joint assessment exposes the interface conflict and allows a compatible combined design or an explicit choice between alternatives.

Incorrect Answers

Answer A is incorrect because sequencing may eventually be part of a solution, but different dates do not automatically make incompatible formats coexist. The dependency still needs analysis.

Answer B is incorrect because documenting incompatibility does not make the shared interface work. An agreed contract between the components is necessary before the release can be assessed as coherent.

Answer C is incorrect because affordability does not establish compatibility. Waiting until testing defers a known design conflict until work has been committed and may need substantial rework.

Answer D is incorrect because cost alone does not resolve which interface best supports the combined outcomes. The cheaper proposal may not be the more valuable or feasible integrated choice.

 

Question 7

A supplier on a predictive project installed an unapproved substitute component. It may meet the original performance criteria, but its maintenance needs differ. The project procedure requires an assessed disposition of unauthorized changes. What should the manager do first?

  1. Order immediate removal without evaluating the effect on safety or schedule.
  2. Record the deviation and assess impacts before seeking an authorized disposition.
  3. Treat the supplier’s installation record as retrospective approval.
  4. Issue a new maintenance manual and close the substitution as documentation work.
  5. Accept the substitute immediately if the supplier’s performance test passes.

Correct Answer: B

 

Correct Answer

Answer B is correct because the project needs to establish both compliance with existing requirements and the consequences of different maintenance needs. That evidence supports a valid decision to retain, modify or reverse the substitution.

Incorrect Answers

Answer A is incorrect because reversal may be the eventual decision, but it can itself introduce cost, disruption or risk. The required assessed disposition should determine the appropriate correction.

Answer C is incorrect because a record of what occurred establishes configuration, not authorization. The procedure still requires a decision on the deviation’s acceptability.

Answer D is incorrect because a manual may be needed if the component is accepted, but it does not decide whether the changed operating burden is acceptable. The disposition must come first.

Answer E is incorrect because performance is one part of the impact, while maintenance has already changed. A successful test does not authorize the unassessed deviation under the stated procedure.

 

Question 8

A predictive project’s board rejected a change because its expected benefit did not justify its cost. The requester now has verified evidence of a substantially lower implementation cost. What is the appropriate action?

  1. Implement the change because the original reason for rejection appears resolved.
  2. Submit a revised request linking the new evidence to the earlier decision.
  3. Create a new unlinked request so the lower estimate is evaluated without the previous rejection history.
  4. Leave the rejected request closed and wait for the next periodic benefits review to reconsider it.
  5. Seek an informal sponsor endorsement without updating the change record.

Correct Answer: B

 

Correct Answer

Answer B is correct because the original rejection was based on an economic assessment that may now differ. A traceable resubmission lets the board reconsider the changed case without pretending that the prior request was already approved.

Incorrect Answers

Answer A is incorrect because new evidence supports reconsideration, not automatic authorization. The board may still need to review other impacts and decide whether the revised proposal is justified.

Answer C is incorrect because the changed cost supports a revised decision, but the earlier reasoning remains relevant context. A linked resubmission shows what changed and allows reviewers to distinguish new evidence from an unchanged rejected case.

Answer D is incorrect because the verified implementation-cost change is relevant to the original rejection now. Routing a revised request provides the authorized decision process with that evidence without an unsupported wait for another review cycle.

Answer E is incorrect because endorsement may help route the proposal but leaves the new evidence and decision history incomplete. The revised request should use the established control process.

 

Question 9

A hybrid project has approved and implemented a schema change affecting three systems. Its control procedure requires an identifiable current baseline and traceability from authorization to implementation. Which two records complete those requirements? Choose TWO.

  1. A versioned baseline identifying the compatible schema in all three systems.
  2. Archive the three local test reports and defer mapping them to versions until the next audit.
  3. Use the most recently edited schema draft as the common reference for all three systems.
  4. A link from the approved request to the deployed versions and verification results.
  5. Retain the approval date and general release name as the complete configuration reference.
  6. Three separate completion emails without version identifiers.

Correct Answers: A, D

 

Correct Answers

Answer A is correct because the current configuration must be reproducible across the linked components. A single local update would not establish which combination is the approved integrated state.

Answer D is correct because this connects permission with what was actually delivered and tested. Reviewers can then distinguish an approved idea from its completed implementation.

Incorrect Answers

Answer B is incorrect because the procedure requires present traceability from authorization through implementation. Unmapped reports cannot establish which tested versions constitute the current integrated baseline.

Answer C is incorrect because recency does not establish that a draft matches the approved, deployed combination. The current reference must identify the controlled versions actually implemented and verified.

Answer E is incorrect because these identify a decision and a package but not the compatible schema versions operating across the three systems. The current baseline and its implementation evidence require version-level traceability.

Answer F is incorrect because local claims of completion cannot prove compatibility or link the releases to the authorized request. Version-level traceability is the missing evidence.

 

Question 10

A predictive project’s approved change adds 40,000 of scope to a 500,000 cost baseline. Before the change, completed work had already exceeded its budget by 15,000. Policy requires the new baseline to include authorized scope changes while preserving historical variance. How should the manager report?

  1. Use a 540,000 revised baseline and retain the 15,000 historical overrun.
  2. Set the baseline to 525,000 by offsetting the new scope against the historical overrun.
  3. Report only the revised baseline until enough new work is complete to recalculate all history.
  4. Set the baseline to 555,000 so it includes both added scope and the earlier overrun.
  5. Keep the baseline at 500,000 and treat the full added scope as adverse variance.

Correct Answer: A

 

Correct Answer

Answer A is correct because the authorized addition changes the planned cost of scope, while the earlier overrun describes performance against the prior plan. Adding scope does not authorize absorbing that variance into a larger baseline.

Incorrect Answers

Answer B is incorrect because an overrun is not a credit that reduces the authorized addition. Subtracting it would understate the planned cost of the changed scope.

Answer C is incorrect because the historical variance remains known and decision-relevant. The policy requires preserving it rather than temporarily withholding the earlier performance result.

Answer D is incorrect because the extra 15,000 is a performance variance, not an authorized scope addition. Including it would rebaseline past inefficiency contrary to the explicit reporting policy.

Answer E is incorrect because that would ignore an approved change to the work being measured. The revised baseline should include the authorized 40,000 while distinguishing earlier performance.

 

Question 11

A hybrid change will introduce a new data format. The team can reinstall the old application, but it cannot read records created in the new format. Policy requires an approved recovery method that preserves transactions submitted after cutover. Only application reinstallation has been tested. What is needed before release authorization?

  1. Pause writes during deployment and resume them immediately afterward using the existing recovery plan.
  2. Retain a pre-cutover snapshot and approve release before testing reconciliation of later transactions.
  3. Schedule recovery testing after the first production day, when representative new records are available.
  4. Approve release using the successful application-reinstallation test as the complete recovery evidence.
  5. Validate a recovery method covering both application behavior and post-cutover transactions.

Correct Answer: E

 

Correct Answer

Answer E is correct because reinstalling software does not restore a usable service if the resulting application cannot read the current records. The recovery method must demonstrate how transactions created after cutover remain usable under the stated policy.

Incorrect Answers

Answer A is incorrect because pausing writes during installation reduces one exposure window but does not address new-format records created after service resumes. The stated recovery gap remains once users begin submitting transactions.

Answer B is incorrect because the snapshot can restore the earlier state, but it does not contain transactions submitted afterward. Reconciliation or another supported recovery route must be validated to meet the preservation requirement.

Answer C is incorrect because representative evidence is useful, but the policy makes a supported recovery method a condition of release authorization. A controlled test can create relevant records before production exposure rather than leave the first day without validated recovery.

Answer D is incorrect because that test proves only that the old software can be installed. It does not address the explicitly identified incompatibility with records that users will create after cutover.

 

Question 12

A hybrid project’s approved change has been deployed, and the implementer asks to close its record. The change plan requires proof of the expected behavior and confirmation that affected users and support staff received the updated instructions. Which two actions should precede closure? Choose TWO.

  1. Use the original acceptance record without checking the changed behavior.
  2. Close the request as soon as the deployment tool returns a success code.
  3. Confirm delivery of the revised instructions to the affected operating groups.
  4. Verify the deployed behavior against the change’s acceptance checks.
  5. Keep the request open until the next annual operations audit confirms routine compliance.
  6. Publish general release notes and treat publication alone as confirmation that affected staff received their instructions.

Correct Answers: C, D

 

Correct Answers

Answer C is correct because these groups need the new procedure to use and support the changed service. The plan explicitly makes that communication part of completion rather than an optional activity after closure.

Answer D is correct because deployment establishes that something changed, not that the intended result occurred. The planned checks provide evidence that the implemented change meets its approved purpose.

Incorrect Answers

Answer A is incorrect because original acceptance concerns the earlier baseline and cannot prove the new behavior. The approved change has its own checks that need execution.

Answer B is incorrect because a tool’s success status may show installation completed but not the business behavior or instruction transfer required by the change plan.

Answer E is incorrect because the defined completion conditions concern this change’s behavior and instruction delivery. A later annual audit may provide additional assurance, but it is not a stated prerequisite to closing this change record.

Answer F is incorrect because publication can support communication but does not establish the delivery confirmation required by this change plan. The affected user and support groups need the revised instructions through the agreed completion process.

 

Question 13

Two separately approved hybrid changes are ready to deploy. One modifies authentication, and the other modifies session expiry. Both passed isolated tests, but combined behavior has not been tested. The release policy requires integrated verification for interacting changes. What should happen next?

  1. Move both approvals to a single tracking record and proceed.
  2. Deploy whichever change is smaller and add the other immediately afterward.
  3. Deploy both because their individual approvals already establish release readiness.
  4. Ask the two implementers to confirm that they expect no conflict.
  5. Verify the combined configuration before authorizing the joint release.

Correct Answer: E

 

Correct Answer

Answer E is correct because separate approvals and tests do not establish how the changes interact. The policy specifically requires integrated evidence, which can reveal failures invisible when each change is tested alone.

Incorrect Answers

Answer A is incorrect because combining paperwork may improve traceability but does not test the technical interaction. The release condition concerns behavior, not the number of records.

Answer B is incorrect because deploying in quick succession still produces the untested combined state. Sequencing alone does not satisfy the integrated-verification requirement.

Answer C is incorrect because change approval and combined release readiness are different decisions here. The known interaction remains outside the isolated evidence.

Answer D is incorrect because expert judgment can guide tests but cannot replace the verification required by policy. Expectations are not evidence of the combined configuration’s behavior.

 

Question 14

A predictive project’s proposed component change saves 30,000 in installation cost but adds 12,000 per year in maintenance for three years. Policy evaluates incremental cost across installation and those three operating years, with no discounting and all other costs equal. What cost impact should be submitted?

  1. A 30,000 saving because the maintenance budget belongs to operations.
  2. A 6,000 net increase over the policy’s evaluation period.
  3. An 18,000 saving because only the first year’s maintenance is relevant.
  4. A 66,000 increase by adding the installation saving to the maintenance total.
  5. A 36,000 increase because installation costs are already part of the baseline.

Correct Answer: B

 

Correct Answer

Answer B is correct because the added maintenance totals 36,000, which exceeds the 30,000 installation saving by 6,000. The change’s local capital saving therefore does not establish a lower total cost under the stated model.

Incorrect Answers

Answer A is incorrect because the policy explicitly includes the three operating years. Moving ownership of the expense does not remove it from the required change assessment.

Answer C is incorrect because subtracting one 12,000 payment from the saving ignores two additional years required by the model. The comparison must use the full specified horizon.

Answer D is incorrect because the 30,000 is a reduction in cost, so it offsets rather than adds to the operating increase. The signs of the incremental effects matter.

Answer E is incorrect because the proposed change reduces a future installation cost by 30,000. That incremental reduction remains relevant even though installation exists in the current plan.

 

Question 15

A predictive project’s procedure delegates correction of defects to the test lead when the correction restores approved behavior without changing scope, budget or milestones. A defect meets those conditions. What control route should the manager use?

  1. Submit the defect as an enhancement because the software will change.
  2. Use the delegated defect-correction route and retain the test evidence.
  3. Wait for the monthly scope board even though no controlled limit changes.
  4. Record the correction under the delegated route but reuse the original passing test as closure evidence.
  5. Ask the customer to accept the failed behavior as the new requirement.

Correct Answer: B

 

Correct Answer

Answer B is correct because the procedure already authorizes this bounded correction. Restoring approved behavior under the stated limits does not require inventing a new scope approval, while evidence still confirms the correction worked.

Incorrect Answers

Answer A is incorrect because a technical alteration does not necessarily change the approved requirements. This correction restores the baseline behavior and fits the explicitly delegated route.

Answer C is incorrect because the procedure provides a more direct authority for this exact case. An unnecessary delay would not add a required scope decision.

Answer D is incorrect because the route is appropriate, but a result obtained before the defect correction does not demonstrate that the corrected implementation works. Verification must address the actual changed behavior.

Answer E is incorrect because that would change the acceptance basis rather than correct the defect. No evidence suggests the customer needs a different requirement.

 

Question 16

A compliance specialist confirms that a new requirement applies to a predictive project’s deliverable. It must be met before use, but two compliant designs have different cost and schedule effects. The change procedure requires an impact-based choice by the board. What should the manager do?

  1. Submit the compliant alternatives and their integrated impacts for the required decision.
  2. Treat the obligation as accepted risk and keep the baseline unchanged.
  3. Select the first compliant design immediately because compliance removes the need for change review.
  4. Ask the compliance specialist to commit the project to the cheapest design.
  5. Retain the original design until the next routine scope refresh because it was previously approved.

Correct Answer: A

 

Correct Answer

Answer A is correct because the obligation makes a response necessary but does not determine which compliant design should be chosen. The board still needs the stated impact comparison to authorize the implementation approach.

Incorrect Answers

Answer B is incorrect because the scenario requires compliance before use and offers compliant alternatives. Risk acceptance is not provided as a route for waiving this requirement.

Answer C is incorrect because necessity does not eliminate meaningful alternatives or their consequences. The procedure explicitly retains an impact-based choice even when a response is mandatory.

Answer D is incorrect because the specialist establishes applicability and can assess compliance, but no authority to choose the project’s cost and schedule tradeoff is stated.

Answer E is incorrect because prior approval does not resolve a confirmed new applicability condition before use. The manager should bring the necessary change forward in time to meet that condition.

 

Question 17

A hybrid project’s change request says only ‘make the dashboard faster.’ The review board needs measurable acceptance criteria to compare alternatives, but the requester has not identified the affected workflow or acceptable response time. What should the manager do first?

  1. Estimate a server upgrade because it is the team’s usual performance remedy.
  2. Ask the board to approve a fixed budget and let the team infer the desired result.
  3. Set the acceptance target to the fastest response the current system can achieve.
  4. Return the request to the backlog for the next planning cycle without clarifying the acceptance need.
  5. Clarify the workflow and measurable performance need with the requester.

Correct Answer: E

 

Correct Answer

Answer E is correct because the request does not yet define what outcome would count as an acceptable change. Clarification makes estimation and option comparison meaningful before the team commits to a particular technical solution.

Incorrect Answers

Answer A is incorrect because an upgrade may be one option, but the actual bottleneck and required response are undefined. Starting with a familiar remedy risks assessing the wrong change.

Answer B is incorrect because funding does not define acceptance. The board would lack the measurable outcome needed to judge whether the change delivered its purpose.

Answer C is incorrect because current capability is not necessarily the customer’s need. Choosing the target from the existing result could make the requirement convenient but ineffective.

Answer D is incorrect because deferral leaves the same missing workflow and measurable target unresolved. Clarification is the next useful action before the board can compare alternatives or decide whether the request deserves investment.

 

Question 18

Two departments submit hybrid change requests for the same export capability under different names. Their requested fields largely overlap, and both business cases claim the same staff-time saving. Which two actions should the manager take before board review? Choose TWO.

  1. Reject the later request solely because it arrived second.
  2. Reconcile the requirements and identify one common capability with any real differences.
  3. Retain both benefit claims until a shared solution has been implemented.
  4. Ask the supplier to choose which department’s fields to support after approval.
  5. Approve both independently because each department controls its own request.
  6. Reconcile the benefit attribution so the shared saving is counted once.

Correct Answers: B, F

 

Correct Answers

Answer B is correct because similar labels can hide either duplication or distinct needs. Comparing the actual fields and usage makes it possible to assess a shared implementation without losing legitimate department-specific requirements.

Answer F is correct because two request records do not create two realizations of the same staff-time reduction. A consolidated case should preserve a defensible benefit total while recognizing the departments involved.

Incorrect Answers

Answer A is incorrect because order of arrival does not establish that every requirement is identical. The second request may contain legitimate differences that need reconciliation.

Answer C is incorrect because the board is evaluating the business case now. Counting the same forecast saving twice can distort that decision even if the discrepancy is intended to be corrected after delivery.

Answer D is incorrect because that defers a business-scope decision to an implementer without the necessary authority. The requesters’ requirements should be reconciled before the board evaluates the proposal.

Answer E is incorrect because separate sponsorship does not remove overlapping requirements or duplicated benefits. Independent approval could fund the same capability twice.

 

Question 19

A hybrid project’s release freeze permits only fixes for verified severity-one defects; all other changes move to the next release. A valuable usability improvement is ready, and a separate severity-one defect has been verified. What should the manager recommend?

  1. Defer both changes because a freeze means no modifications are allowed.
  2. Ask the team to lower the freeze threshold for this release because the improvement is valuable.
  3. Bundle the usability improvement with the defect so both share the exception.
  4. Process the defect through the freeze exception and defer the usability change.
  5. Release the usability improvement first because it has already completed testing.

Correct Answer: D

 

Correct Answer

Answer D is correct because the freeze rule differentiates the two requests by verified severity, not readiness or perceived value. Applying it selectively allows the necessary correction while preserving the controlled release boundary.

Incorrect Answers

Answer A is incorrect because the policy expressly provides a severity-one exception. Treating the freeze as absolute would prevent a correction the process is designed to permit.

Answer B is incorrect because the team has no stated authority to revise the freeze rule. Value can support a future request, but it does not itself change the current eligibility condition.

Answer C is incorrect because the exception applies to the qualifying defect, not every change packaged beside it. Bundling would expand the permitted scope without a new authorized decision.

Answer E is incorrect because test completion does not make the improvement eligible for the stated exception. Readiness and authorization are separate conditions.

 

Question 20

A predictive project’s board approves a supplier-related design change. The contract states that only a signed amendment from the procurement authority authorizes changed supplier work. The board decision is not itself an amendment. Which two actions are needed before the supplier starts? Choose TWO.

  1. Issue only an updated internal drawing without changing the supplier agreement.
  2. Pay an advance for the revised work and treat the payment as implied approval.
  3. Tell the supplier to proceed using the board minutes as the contractual instruction.
  4. Have the site engineer sign the amendment because they understand the technical details.
  5. Obtain the procurement authority’s signed amendment defining the revised work.
  6. Align the supplier’s implementation schedule and acceptance terms with that amendment.

Correct Answers: E, F

 

Correct Answers

Answer E is correct because internal project approval establishes the organization’s decision but does not satisfy the contractual authorization mechanism. The amendment translates it into the supplier’s authorized obligations.

Answer F is correct because the changed obligation must be executable and verifiable under its agreed terms. Consistent schedule and acceptance details prevent the internal plan and supplier commitment from describing different work.

Incorrect Answers

Answer A is incorrect because the drawing may describe the desired design but does not establish the contractual terms governing its performance. The supplier needs the authorized amendment.

Answer B is incorrect because payment does not replace the stated signed-amendment mechanism. It can create exposure before scope and acceptance are properly agreed.

Answer C is incorrect because the contract expressly distinguishes the board decision from an amendment. Minutes can support preparation but are not the required authorization to start changed work.

Answer D is incorrect because technical understanding does not confer the procurement authority specified by the contract. The engineer can contribute detail while the authorized role executes the amendment.

 

Question 21

An approved hybrid change is half implemented when the business sponsor requests its cancellation. Reversing the installed portion would interrupt a dependent service. The procedure requires assessment of changes to approved implementation plans. What should the manager do?

  1. Restore the original design immediately because it was the earliest baseline.
  2. Finish the funded implementation before assessing cancellation so the project reaches a stable configuration first.
  3. Assess cancellation and rollback impacts and obtain a controlled revised decision.
  4. Stop every implementation task and leave the installed components indefinitely.
  5. Remove the request from the implementation schedule and let operations decide the configuration.

Correct Answer: C

 

Correct Answer

Answer C is correct because stopping an approved change can itself alter the current configuration and disrupt dependencies. The revised decision needs evidence about what is installed and how to reach a safe, agreed end state.

Incorrect Answers

Answer A is incorrect because the system now includes a partially implemented state with live dependencies. Returning to an earlier baseline is a new action whose disruption must be assessed.

Answer B is incorrect because finishing may be one alternative, but it also consumes remaining effort after the sponsor requests cancellation. The stated process calls for assessing the current partial configuration and consequences before choosing continuation, rollback or another controlled end state.

Answer D is incorrect because a pause may be a temporary safeguard, but it does not define a coherent final state or resolve the dependent service. The cancellation needs an assessed disposition.

Answer E is incorrect because changing the schedule does not transfer decision authority or assess the effects. Operations should contribute to the revised plan, not inherit an undefined partial state.

 

Question 22

An adaptive team’s governance delegates technical work sequencing when scope, quality, funding and release commitments remain unchanged. The team wants to reverse the order of two independent internal tasks, with no effect on those boundaries. What should the manager do?

  1. Wait for a combined dependency review with unrelated workstreams before changing the order.
  2. Update the internal schedule only after both tasks are finished in the new order.
  3. Allow the team to adapt its work plan within the documented delegation.
  4. Ask the sponsor to select the detailed task order at the next steering meeting.
  5. Submit a scope-change request because any task-order change alters the baseline.

Correct Answer: C

 

Correct Answer

Answer C is correct because the adjustment changes an internal method rather than a controlled commitment. Applying the existing delegation preserves useful adaptability while the team remains accountable for the unchanged boundaries.

Incorrect Answers

Answer A is incorrect because a shared review would matter if the proposed sequence affected other work. The facts establish independent tasks and unchanged commitments, so the existing team delegation is sufficient.

Answer B is incorrect because the team may choose the sequence, but its current plan should reflect intended execution. Deferring the update until completion leaves coordination information inconsistent with the work being performed.

Answer D is incorrect because the decision is already delegated to the team and involves no crossed boundary. Moving it upward would add delay without supplying a needed authorization.

Answer E is incorrect because the governance rule explicitly permits this kind of internal sequencing. No scope or release commitment is changing under the facts given.

 

Question 23

A predictive construction crew is using drawing version 4. The approved change record identifies version 5 as effective today, but the controlled distribution list did not reach this crew. Work on the affected section has not started. What should the manager do?

  1. Provide the approved drawing and confirm the affected crew uses the effective version.
  2. Allow the crew to complete the section under version 4 and revise it later.
  3. Send a general email saying that some drawings have changed.
  4. Ask the board to approve version 5 again before informing the crew.
  5. Send both drawing versions to the crew and let the foreman select the one that best fits the construction sequence.

Correct Answer: A

 

Correct Answer

Answer A is correct because the change is authorized but has not reached the point of use. Correcting controlled distribution before work starts prevents construction against a superseded configuration without reopening the substantive design decision.

Incorrect Answers

Answer B is incorrect because affected work has not begun, so foreseeable rework can be avoided now. Continuing with the superseded drawing would create an unnecessary configuration deviation.

Answer C is incorrect because a nonspecific notice does not identify the applicable version or confirm receipt at the point of work. The distribution gap needs targeted correction and confirmation.

Answer D is incorrect because the approval already exists and is effective. Repeating the decision does not address the actual failure in distribution and use of controlled information.

Answer E is incorrect because the effective version is already authorized. Sequence preferences cannot determine which design governs the work, and distributing both without a clear active version perpetuates the configuration gap.

 

Question 24

A hybrid project’s approved change improves transaction throughput. The implementation team has met the new throughput target but has not rerun the unchanged error-rate and recovery checks. The change plan requires regression checks for those existing constraints. Which two actions support completion? Choose TWO.

  1. Accept the throughput gain as compensation for any deterioration in the existing error-rate result.
  2. Close the request once throughput passes and place regression work in a future backlog.
  3. Use the pre-change recovery result because recovery was not the requested improvement.
  4. Link the new-target and regression results to the request’s completion decision.
  5. Verify the unchanged error-rate and recovery constraints on the changed system.
  6. Ask the throughput requester alone to waive the remaining checks.

Correct Answers: D, E

 

Correct Answers

Answer D is correct because the complete evidence set should support closure of this specific change. Connecting both types of results prevents throughput success from being mistaken for satisfaction of all acceptance conditions.

Answer E is correct because a change can meet its new target while damaging existing behavior. Regression evidence is needed because the approved plan retains these constraints as part of the acceptable overall result.

Incorrect Answers

Answer A is incorrect because the approved plan retains the error-rate constraint rather than authorizing a throughput-for-quality tradeoff. A local improvement does not establish acceptance of a changed existing limit.

Answer B is incorrect because the plan makes regression checks part of this change, not optional future work. Deferral would declare completion before its defined conditions are known.

Answer C is incorrect because unchanged requirements can still be affected by changed implementation. The stated regression requirement exists to test that assumption on the new system.

Answer F is incorrect because interest in the improvement does not establish authority to waive other retained acceptance conditions. Any proposed relaxation would require its own controlled decision.

 

Question 25

A hybrid program plans to package several approved project changes into one coordinated release. Its policy requires cumulative-impact review, an agreed execution sequence across teams and confirmation that the combined result meets retained acceptance conditions. Which three arrangements satisfy the policy? Choose THREE.

  1. Review aggregate demand on shared capacity and the combined operating exposure.
  2. Agree the cross-team sequence and accountable handoffs before the release starts.
  3. Allocate the full shared test environment to whichever team is ready first.
  4. Use each team’s original release date without examining shared dependencies.
  5. Verify the combined release against new and retained acceptance conditions.
  6. Close each change record when its component deploys and perform combined acceptance as a later release activity.

Correct Answers: A, B, E

 

Correct Answers

Answer A is correct because individually acceptable changes may consume the same resources or interact in operation. A cumulative review assesses the release as a whole rather than assuming local approvals sum to a feasible outcome.

Answer B is correct because shared execution depends on the right work reaching the right team at the right time. Explicit handoffs turn separate plans into a coordinated release path.

Answer E is correct because the final state must deliver the intended additions while preserving existing constraints. Combined verification tests the actual release rather than relying only on isolated implementation evidence.

Incorrect Answers

Answer C is incorrect because readiness order alone does not resolve aggregate capacity demand or critical dependencies. The shared resource needs to support the agreed integrated plan.

Answer D is incorrect because independent dates can conflict when changes are packaged together. The policy requires a coordinated sequence, which may need adjusted timing.

Answer F is incorrect because local deployment does not prove that interacting changes meet the retained conditions. The policy makes verification of the combined result part of completion, so closing records first would separate closure from required evidence.