PMI CAPM Exam Dumps, Practice Test Questions

100% Latest & Updated PMI CAPM Practice Test Questions, Exam Dumps & Verified Answers!
30 Days Free Updates, Instant Download!

PMI CAPM Premium Bundle
$79.97
$59.98

CAPM Premium Bundle

  • Premium File: 688 Questions & Answers. Last update: Nov 2, 2026
  • Training Course: 123 Video Lectures
  • Study Guide: 719 Pages
  • Latest Questions
  • 100% Accurate Answers
  • Fast Exam Updates

CAPM Premium Bundle

PMI CAPM Premium Bundle
  • Premium File: 688 Questions & Answers. Last update: Nov 2, 2026
  • Training Course: 123 Video Lectures
  • Study Guide: 719 Pages
  • Latest Questions
  • 100% Accurate Answers
  • Fast Exam Updates
$79.97
$59.98

PMI CAPM Practice Test 12

Question 110

After a corrective decision on Milestone-versus-duration, which independent evidence most directly verifies the result ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A sponsor requests a four-week duration for a regulatory sign-off milestone that represents a single approval event. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Inspect the schedule network for a milestone event after its review and remediation activities. Reconcile the result with the current approved decision baseline.
  2. Compare resource histograms and actual capacity with the revised activity timing. Reconcile the result with the current approved decision baseline.
  3. Compare the integrated baseline's spending profile with the scheduled procurement packages. Retain the initiating evidence for audit.
  4. Assigning the entire review duration to the sign-off event obscures the tasks that drive the date.

Explanation

Correct Answer

A:

This checks the actual mechanism rather than merely declaring success: Inspect the schedule network for a milestone event after its review and remediation activities. Reconcile the result with the current approved decision baseline. The desired observed result is The schedule distinguishes work effort from the decision point marking its completion. The decision can be traced to the review evidence. [R158 R158-Q0110; case R158-C028; CAPM domain 1, task 1.2; source ECO.]

Incorrect Answers

B:

The proposed verify (Compare resource histograms and actual capacity with the revised activity timing. Reconcile the result with the current approved decision baseline.) comes from a different Project management planning situation: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. It does not resolve or independently test the stated issue: A sponsor requests a four-week duration for a regulatory sign-off milestone that represents a single approval event. Here, the relevant check is Inspect the schedule network for a milestone event after its review and remediation activities. Reconcile the result with the current approved decision baseline. [R158 R158-Q0110; case R158-C028; CAPM domain 1, task 1.2; source ECO.]

C:

This option concerns a different Project management planning situation: A regional construction plan has a cost forecast but no connection between procurement milestones and when spending occurs. For the reported case, use this verification: Inspect the schedule network for a milestone event after its review and remediation activities. Reconcile the result with the current approved decision baseline.

D:

This is a tempting but unsupported shortcut in this case: Assigning the entire review duration to the sign-off event obscures the tasks that drive the date. It does not show that The schedule distinguishes work effort from the decision point marking its completion. The decision can be traced to the review evidence. [R158 R158-Q0110; case R158-C028; CAPM domain 1, task 1.2; source ECO.]

Question 111

Which statement most accurately flags a misleading shortcut to avoid in this Milestone-versus-duration case? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A sponsor requests a four-week duration for a regulatory sign-off milestone that represents a single approval event. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Inspect the schedule network for a milestone event after its review and remediation activities. Reconcile the result with the current approved decision baseline.
  2. Represent the approval as a zero-duration milestone and model the review work as predecessor activities with realistic durations. Document impacted stakeholders and the decision owner at the review.
  3. Assigning the entire review duration to the sign-off event obscures the tasks that drive the date.
  4. The schedule distinguishes work effort from the decision point marking its completion. The decision can be traced to the review evidence.

Explanation

Correct Answer

C:

The shortcut is mistaken: Assigning the entire review duration to the sign-off event obscures the tasks that drive the date. The appropriate response is to represent the approval as a zero-duration milestone and model the review work as predecessor activities with realistic durations. Document impacted stakeholders and the decision owner at the review.

Incorrect Answers

A:

This is an appropriate independent test of the proposed decision: Inspect the schedule network for a milestone event after its review and remediation activities. Reconcile the result with the current approved decision baseline. It is not the invalid shortcut.

B:

This is a supported decision, not the unsupported claim: Represent the approval as a zero-duration milestone and model the review work as predecessor activities with realistic durations. Document impacted stakeholders and the decision owner at the review. It responds to the actual project issue: A sponsor requests a four-week duration for a regulatory sign-off milestone that represents a single approval event.

D:

This is a relevant outcome to seek after the decision: The schedule distinguishes work effort from the decision point marking its completion. The decision can be traced to the review evidence. It is not an unsupported assumption.

Question 112

Select THREE consistent elements of the Milestone-versus-duration case: appropriate decision, verification, and observable success condition. At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A sponsor requests a four-week duration for a regulatory sign-off milestone that represents a single approval event. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Decisions occur within required response windows and routine information remains appropriately batched. The result is recorded in the project controls.
  2. Assigning the entire review duration to the sign-off event obscures the tasks that drive the date.
  3. The schedule distinguishes work effort from the decision point marking its completion. The decision can be traced to the review evidence.
  4. Represent the approval as a zero-duration milestone and model the review work as predecessor activities with realistic durations. Document impacted stakeholders and the decision owner at the review.
  5. Inspect the schedule network for a milestone event after its review and remediation activities. Reconcile the result with the current approved decision baseline.
  6. Plan measurable quality criteria and associated assurance and control activities before final acceptance. Document impacted stakeholders and the decision owner at the review.

Explanation

Correct Answer

C:

The stated result demonstrates the case acceptance condition: The schedule distinguishes work effort from the decision point marking its completion. The decision can be traced to the review evidence. It depends on the decision Represent the approval as a zero-duration milestone and model the review work as predecessor activities with realistic durations. Document impacted stakeholders and the decision owner at the review.

D:

The case evidence identifies A sponsor requests a four-week duration for a regulatory sign-off milestone that represents a single approval event. The specified decision directly addresses it: Represent the approval as a zero-duration milestone and model the review work as predecessor activities with realistic durations. Document impacted stakeholders and the decision owner at the review. This can be checked using Inspect the schedule network for a milestone event after its review and remediation activities. Reconcile the result with the current approved decision baseline. [R158 R158-Q0112; case R158-C028; CAPM domain 1, task 1.2; source ECO.]

E:

This checks the actual mechanism rather than merely declaring success: Inspect the schedule network for a milestone event after its review and remediation activities. Reconcile the result with the current approved decision baseline. The desired observed result is The schedule distinguishes work effort from the decision point marking its completion. The decision can be traced to the review evidence. [R158 R158-Q0112; case R158-C028; CAPM domain 1, task 1.2; source ECO.]

Incorrect Answers

A:

This option concerns a different Project management planning situation: A remote project team sends status slides weekly but keeps missing decisions that require urgent escalation. For the reported case, use this verification: Inspect the schedule network for a milestone event after its review and remediation activities. Reconcile the result with the current approved decision baseline.

B:

This is a tempting but unsupported shortcut in this case: Assigning the entire review duration to the sign-off event obscures the tasks that drive the date. It does not show that The schedule distinguishes work effort from the decision point marking its completion. The decision can be traced to the review evidence. [R158 R158-Q0112; case R158-C028; CAPM domain 1, task 1.2; source ECO.]

F:

The proposed action (Plan measurable quality criteria and associated assurance and control activities before final acceptance. Document impacted stakeholders and the decision owner at the review.) comes from a different Project management planning situation: A new supplier onboarding flow has an acceptance deadline but no defined accuracy, reliability or performance thresholds. It does not resolve or independently test the stated issue: A sponsor requests a four-week duration for a regulatory sign-off milestone that represents a single approval event. Here, the relevant check is Inspect the schedule network for a milestone event after its review and remediation activities. Reconcile the result with the current approved decision baseline. [R158 R158-Q0112; case R158-C028; CAPM domain 1, task 1.2; source ECO.]

Question 113

Which project-management decision best addresses the Resource-capacity-analysis situation ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Assess resource availability and level or resequence the conflicting assignments before committing schedule dates. Record the rationale before the next commitment.
  2. Plan measurable quality criteria and associated assurance and control activities before final acceptance. Document impacted stakeholders and the decision owner at the review.
  3. Distinguish evolving product direction from the project management plan's execution, governance and control components. Document impacted stakeholders and the decision owner at the review.
  4. Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule.

Explanation

Correct Answer

A:

The case evidence identifies A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. The specified decision directly addresses it: Assess resource availability and level or resequence the conflicting assignments before committing schedule dates. Record the rationale before the next commitment. This can be checked using Compare resource histograms and actual capacity with the revised activity timing. Retain the initiating evidence for audit. [R158 R158-Q0113; case R158-C029; CAPM domain 1, task 1.2; source ECO.]

Incorrect Answers

B:

This option concerns a different Project management planning situation: A new supplier onboarding flow has an acceptance deadline but no defined accuracy, reliability or performance thresholds. For the reported case, use this verification: Compare resource histograms and actual capacity with the revised activity timing. Retain the initiating evidence for audit.

C:

The proposed action (Distinguish evolving product direction from the project management plan's execution, governance and control components. Document impacted stakeholders and the decision owner at the review.) comes from a different Project management planning situation: An application team treats the long-term feature roadmap as if it specified the project's staffing, risks, procurement and change controls. It does not resolve or independently test the stated issue: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. Here, the relevant check is Compare resource histograms and actual capacity with the revised activity timing. Retain the initiating evidence for audit. [R158 R158-Q0113; case R158-C029; CAPM domain 1, task 1.2; source ECO.]

D:

This is a tempting but unsupported shortcut in this case: Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule. It does not show that The assigned expert's work is feasible without an unacknowledged over-allocation. The result is recorded in the project controls. [R158 R158-Q0113; case R158-C029; CAPM domain 1, task 1.2; source ECO.]

Question 114

After a corrective decision on Resource-capacity-analysis, which independent evidence most directly verifies the result ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule.
  2. Compare agreed baseline and post-rollout metrics using consistent population and measurement periods. Reconcile the result with the current approved decision baseline.
  3. Compare resource histograms and actual capacity with the revised activity timing. Retain the initiating evidence for audit.
  4. Inspect the stakeholder register and communication mapping for the regulator's approvals and users' feedback channels. Retain the initiating evidence for audit.

Explanation

Correct Answer

C:

This checks the actual mechanism rather than merely declaring success: Compare resource histograms and actual capacity with the revised activity timing. Retain the initiating evidence for audit. The desired observed result is The assigned expert's work is feasible without an unacknowledged over-allocation. The result is recorded in the project controls. [R158 R158-Q0114; case R158-C029; CAPM domain 1, task 1.2; source ECO.]

Incorrect Answers

A:

This is a tempting but unsupported shortcut in this case: Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule. It does not show that The assigned expert's work is feasible without an unacknowledged over-allocation. The result is recorded in the project controls. [R158 R158-Q0114; case R158-C029; CAPM domain 1, task 1.2; source ECO.]

B:

The proposed verify (Compare agreed baseline and post-rollout metrics using consistent population and measurement periods. Reconcile the result with the current approved decision baseline.) comes from a different Project management planning situation: A sponsor claims productivity increased after rollout but no pre-rollout baseline exists to compare. It does not resolve or independently test the stated issue: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. Here, the relevant check is Compare resource histograms and actual capacity with the revised activity timing. Retain the initiating evidence for audit. [R158 R158-Q0114; case R158-C029; CAPM domain 1, task 1.2; source ECO.]

D:

This option concerns a different Project management planning situation: A regulator and end users receive the same generic project updates despite having different decisions and information needs. For the reported case, use this verification: Compare resource histograms and actual capacity with the revised activity timing. Retain the initiating evidence for audit.

Question 115

Which statement most accurately flags a misleading shortcut to avoid in this Resource-capacity-analysis case? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. The assigned expert's work is feasible without an unacknowledged over-allocation. The result is recorded in the project controls.
  2. Compare resource histograms and actual capacity with the revised activity timing. Retain the initiating evidence for audit.
  3. Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule.
  4. Assess resource availability and level or resequence the conflicting assignments before committing schedule dates. Record the rationale before the next commitment.

Explanation

Correct Answer

C:

The shortcut is mistaken: Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule. The appropriate response is to assess resource availability and level or resequence the conflicting assignments before committing schedule dates. Record the rationale before the next commitment.

Incorrect Answers

A:

This is a relevant outcome to seek after the decision: The assigned expert's work is feasible without an unacknowledged over-allocation. The result is recorded in the project controls. It is not an unsupported assumption.

B:

This is an appropriate independent test of the proposed decision: Compare resource histograms and actual capacity with the revised activity timing. Retain the initiating evidence for audit. It is not the invalid shortcut.

D:

This is a supported decision, not the unsupported claim: Assess resource availability and level or resequence the conflicting assignments before committing schedule dates. Record the rationale before the next commitment. It responds to the actual project issue: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck.

Question 116

Select THREE consistent elements of the Resource-capacity-analysis case: appropriate decision, verification, and observable success condition. During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Distinguish evolving product direction from the project management plan's execution, governance and control components. Document impacted stakeholders and the decision owner at the review.
  2. Compare resource histograms and actual capacity with the revised activity timing. Retain the initiating evidence for audit.
  3. Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule.
  4. Assess resource availability and level or resequence the conflicting assignments before committing schedule dates. Record the rationale before the next commitment.
  5. Benefit realization can be credibly evaluated instead of inferred from activity or opinions. The result is recorded in the project controls.
  6. The assigned expert's work is feasible without an unacknowledged over-allocation. The result is recorded in the project controls.

Explanation

Correct Answer

B:

This checks the actual mechanism rather than merely declaring success: Compare resource histograms and actual capacity with the revised activity timing. Retain the initiating evidence for audit. The desired observed result is The assigned expert's work is feasible without an unacknowledged over-allocation. The result is recorded in the project controls. [R158 R158-Q0116; case R158-C029; CAPM domain 1, task 1.2; source ECO.]

D:

The case evidence identifies A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. The specified decision directly addresses it: Assess resource availability and level or resequence the conflicting assignments before committing schedule dates. Record the rationale before the next commitment. This can be checked using Compare resource histograms and actual capacity with the revised activity timing. Retain the initiating evidence for audit. [R158 R158-Q0116; case R158-C029; CAPM domain 1, task 1.2; source ECO.]

F:

The stated result demonstrates the case acceptance condition: The assigned expert's work is feasible without an unacknowledged over-allocation. The result is recorded in the project controls. It depends on the decision Assess resource availability and level or resequence the conflicting assignments before committing schedule dates. Record the rationale before the next commitment.

Incorrect Answers

A:

The proposed action (Distinguish evolving product direction from the project management plan's execution, governance and control components. Document impacted stakeholders and the decision owner at the review.) comes from a different Project management planning situation: An application team treats the long-term feature roadmap as if it specified the project's staffing, risks, procurement and change controls. It does not resolve or independently test the stated issue: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. Here, the relevant check is Compare resource histograms and actual capacity with the revised activity timing. Retain the initiating evidence for audit. [R158 R158-Q0116; case R158-C029; CAPM domain 1, task 1.2; source ECO.]

C:

This is a tempting but unsupported shortcut in this case: Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule. It does not show that The assigned expert's work is feasible without an unacknowledged over-allocation. The result is recorded in the project controls. [R158 R158-Q0116; case R158-C029; CAPM domain 1, task 1.2; source ECO.]

E:

The proposed outcome (Benefit realization can be credibly evaluated instead of inferred from activity or opinions. The result is recorded in the project controls.) comes from a different Project management planning situation: A sponsor claims productivity increased after rollout but no pre-rollout baseline exists to compare. It does not resolve or independently test the stated issue: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. Here, the relevant check is Compare resource histograms and actual capacity with the revised activity timing. Retain the initiating evidence for audit. [R158 R158-Q0116; case R158-C029; CAPM domain 1, task 1.2; source ECO.]

Question 117

Which project-management decision best addresses the Resource-capacity-analysis situation ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Distinguish evolving product direction from the project management plan's execution, governance and control components. Document impacted stakeholders and the decision owner at the review.
  2. Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule.
  3. Assess resource availability and level or resequence the conflicting assignments before committing schedule dates. Document impacted stakeholders and the decision owner at the review.
  4. Record cause, potential event, impact, qualitative assessment, owner and planned response in the risk register. Document impacted stakeholders and the decision owner at the review.

Explanation

Correct Answer

C:

Assess resource availability and level or resequence the conflicting assignments before committing schedule dates. Document impacted stakeholders and the decision owner at the review. To verify the specified result, compare resource histograms and actual capacity with the revised activity timing. Reconcile the result with the current approved decision baseline.

Incorrect Answers

A:

This option concerns a different Project management planning situation: An application team treats the long-term feature roadmap as if it specified the project's staffing, risks, procurement and change controls. For the reported case, use this verification: Compare resource histograms and actual capacity with the revised activity timing. Reconcile the result with the current approved decision baseline.

B:

This is a tempting but unsupported shortcut in this case: Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule. It does not show that The assigned expert's work is feasible without an unacknowledged over-allocation. The decision can be traced to the review evidence. [R158 R158-Q0117; case R158-C030; CAPM domain 1, task 1.2; source ECO.]

D:

This option concerns a different Project management planning situation: A flood exposure is listed only as high risk, with no specific event description, owner or response. For the reported case, use this verification: Compare resource histograms and actual capacity with the revised activity timing. Reconcile the result with the current approved decision baseline.

Question 118

After a corrective decision on Resource-capacity-analysis, which independent evidence most directly verifies the result ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Inspect the schedule network for a milestone event after its review and remediation activities. Retain the initiating evidence for audit.
  2. Inspect the schedule network for a milestone event after its review and remediation activities. Reconcile the result with the current approved decision baseline.
  3. Compare resource histograms and actual capacity with the revised activity timing. Reconcile the result with the current approved decision baseline.
  4. Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule.

Explanation

Correct Answer

C:

Compare resource histograms and actual capacity with the revised activity timing. Reconcile the result with the current approved decision baseline. The expected result is the assigned expert's work is feasible without an unacknowledged over-allocation. The decision can be traced to the review evidence.

Incorrect Answers

A:

The proposed verify (Inspect the schedule network for a milestone event after its review and remediation activities. Retain the initiating evidence for audit.) comes from a different Project management planning situation: A sponsor requests a four-week duration for a regulatory sign-off milestone that represents a single approval event. It does not resolve or independently test the stated issue: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. Here, the relevant check is Compare resource histograms and actual capacity with the revised activity timing. Reconcile the result with the current approved decision baseline. [R158 R158-Q0118; case R158-C030; CAPM domain 1, task 1.2; source ECO.]

B:

The proposed verify (Inspect the schedule network for a milestone event after its review and remediation activities. Reconcile the result with the current approved decision baseline.) comes from a different Project management planning situation: A sponsor requests a four-week duration for a regulatory sign-off milestone that represents a single approval event. It does not resolve or independently test the stated issue: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. Here, the relevant check is Compare resource histograms and actual capacity with the revised activity timing. Reconcile the result with the current approved decision baseline. [R158 R158-Q0118; case R158-C030; CAPM domain 1, task 1.2; source ECO.]

D:

This is a tempting but unsupported shortcut in this case: Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule. It does not show that The assigned expert's work is feasible without an unacknowledged over-allocation. The decision can be traced to the review evidence. [R158 R158-Q0118; case R158-C030; CAPM domain 1, task 1.2; source ECO.]

Question 119

Which statement most accurately flags a misleading shortcut to avoid in this Resource-capacity-analysis case? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule.
  2. Compare resource histograms and actual capacity with the revised activity timing. Reconcile the result with the current approved decision baseline.
  3. Assess resource availability and level or resequence the conflicting assignments before committing schedule dates. Document impacted stakeholders and the decision owner at the review.
  4. The assigned expert's work is feasible without an unacknowledged over-allocation. The decision can be traced to the review evidence.

Explanation

Correct Answer

A:

The shortcut is mistaken: Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule. The appropriate response is to assess resource availability and level or resequence the conflicting assignments before committing schedule dates. Document impacted stakeholders and the decision owner at the review.

Incorrect Answers

B:

This is an appropriate independent test of the proposed decision: Compare resource histograms and actual capacity with the revised activity timing. Reconcile the result with the current approved decision baseline. It is not the invalid shortcut.

C:

This is a supported decision, not the unsupported claim: Assess resource availability and level or resequence the conflicting assignments before committing schedule dates. Document impacted stakeholders and the decision owner at the review. It responds to the actual project issue: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck.

D:

This is a relevant outcome to seek after the decision: The assigned expert's work is feasible without an unacknowledged over-allocation. The decision can be traced to the review evidence. It is not an unsupported assumption.

Question 120

Which observed result supports acceptance of the Resource-capacity-analysis corrective decision ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A rollout assigns the same specialist simultaneously to two full-time integrations although the plan assumes no resource bottleneck. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. The assigned expert's work is feasible without an unacknowledged over-allocation. The decision can be traced to the review evidence.
  2. Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule.
  3. The team can evaluate product fitness using objective tests instead of aesthetic impressions. The result is recorded in the project controls.
  4. Stakeholders receive relevant information and decisions reach the appropriate accountable parties. The result is recorded in the project controls.

Explanation

Correct Answer

A:

The stated result demonstrates the case acceptance condition: The assigned expert's work is feasible without an unacknowledged over-allocation. The decision can be traced to the review evidence. It depends on the decision Assess resource availability and level or resequence the conflicting assignments before committing schedule dates. Document impacted stakeholders and the decision owner at the review.

Incorrect Answers

B:

This is a tempting but unsupported shortcut in this case: Assuming one person can provide two full-time weeks in the same calendar week creates a false schedule. It does not show that The assigned expert's work is feasible without an unacknowledged over-allocation. The decision can be traced to the review evidence. [R158 R158-Q0120; case R158-C030; CAPM domain 1, task 1.2; source ECO.]

C:

This option concerns a different Project management planning situation: A new supplier onboarding flow has an acceptance deadline but no defined accuracy, reliability or performance thresholds. For the reported case, use this verification: Compare resource histograms and actual capacity with the revised activity timing. Reconcile the result with the current approved decision baseline.

D:

This option concerns a different Project management planning situation: A regulator and end users receive the same generic project updates despite having different decisions and information needs. For the reported case, use this verification: Compare resource histograms and actual capacity with the revised activity timing. Reconcile the result with the current approved decision baseline.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

UP

SPECIAL OFFER: GET 10% OFF

This is ONE TIME OFFER

ExamSnap Discount Offer
Enter Your Email Address to Receive Your 10% Off Discount Code

A confirmation link will be sent to this email address to verify your login. *We value your privacy. We will not rent or sell your email address.

Download Free Demo of VCE Exam Simulator

Experience Avanset VCE Exam Simulator for yourself.

Simply submit your e-mail address below to get started with our interactive software demo of your free trial.

Free Demo Limits: In the demo version you will be able to access only first 5 questions from exam.