Question 380
Which observed result supports acceptance of the Integration-change-impact corrective decision ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- The approved plan reflects coherent cross-functional impacts instead of isolated equipment changes. The result is recorded in the project controls.
- Scope control and schedule execution operate at appropriate levels of detail. The result is recorded in the project controls.
- Approving the new unit by engineering preference alone ignores budget, safety and interface effects.
- The WBS covers authorized outputs without mistaking recurring meetings for the deliverables themselves. The decision can be traced to the review evidence.
Explanation
Correct Answer
A:The stated result demonstrates the case acceptance condition: The approved plan reflects coherent cross-functional impacts instead of isolated equipment changes. The result is recorded in the project controls. It depends on the decision Evaluate the integrated impact on scope, schedule, cost, interfaces and approvals before altering baselines. Record the rationale before the next commitment.
Incorrect Answers
B:This option concerns a different Predictive project schedule and methods situation: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. For the reported case, use this verification: Inspect change analysis across affected engineering disciplines and the final governance decision. Retain the initiating evidence for audit.
C:This is a tempting but unsupported shortcut in this case: Approving the new unit by engineering preference alone ignores budget, safety and interface effects. It does not show that The approved plan reflects coherent cross-functional impacts instead of isolated equipment changes. The result is recorded in the project controls. [R158 R158-Q0380; case R158-C095; CAPM domain 2, task 2.2; source ECO.]
D:The proposed outcome (The WBS covers authorized outputs without mistaking recurring meetings for the deliverables themselves. The decision can be traced to the review evidence.) comes from a different Predictive project schedule and methods situation: A project WBS has vague headings such as weekly calls and team morale but lacks identifiable deliverables for the security audit. It does not resolve or independently test the stated issue: A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost. Here, the relevant check is Inspect change analysis across affected engineering disciplines and the final governance decision. Retain the initiating evidence for audit. [R158 R158-Q0380; case R158-C095; CAPM domain 2, task 2.2; source ECO.]
Question 381
Which project-management decision best addresses the Integration-change-impact situation ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Define manageable work packages and then identify, sequence and estimate the activities required to produce them. Document impacted stakeholders and the decision owner at the review.
- Evaluate the integrated impact on scope, schedule, cost, interfaces and approvals before altering baselines. Document impacted stakeholders and the decision owner at the review.
- Identify the procurement branch as the controlling longer path and plan the milestone at 17 days, assuming no other constraints. Record the rationale before the next commitment.
- Approving the new unit by engineering preference alone ignores budget, safety and interface effects.
Explanation
Correct Answer
B:The case evidence identifies A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost. The specified decision directly addresses it: Evaluate the integrated impact on scope, schedule, cost, interfaces and approvals before altering baselines. Document impacted stakeholders and the decision owner at the review. This can be checked using Inspect change analysis across affected engineering disciplines and the final governance decision. Reconcile the result with the current approved decision baseline. [R158 R158-Q0381; case R158-C096; CAPM domain 2, task 2.2; source ECO.]
Incorrect Answers
A:This option concerns a different Predictive project schedule and methods situation: A project team schedules the whole data-center migration as one eight-month activity without decomposing its scoped work package into executable tasks. For the reported case, use this verification: Inspect change analysis across affected engineering disciplines and the final governance decision. Reconcile the result with the current approved decision baseline.
C:This option concerns a different Predictive project schedule and methods situation: Two parallel activities lead to the same milestone: engineering takes 8 days, procurement 13 days, followed by a common 4-day commissioning task. For the reported case, use this verification: Inspect change analysis across affected engineering disciplines and the final governance decision. Reconcile the result with the current approved decision baseline.
D:This is a tempting but unsupported shortcut in this case: Approving the new unit by engineering preference alone ignores budget, safety and interface effects. It does not show that The approved plan reflects coherent cross-functional impacts instead of isolated equipment changes. The decision can be traced to the review evidence. [R158 R158-Q0381; case R158-C096; CAPM domain 2, task 2.2; source ECO.]
Question 382
After a corrective decision on Integration-change-impact, which independent evidence most directly verifies the result ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Approving the new unit by engineering preference alone ignores budget, safety and interface effects.
- Review sample size, critical defect count and the agreed acceptance limit. Retain the initiating evidence for audit.
- Trace work packages to scoped audit deliverables and identify the accountable control or acceptance point. Reconcile the result with the current approved decision baseline.
- Inspect change analysis across affected engineering disciplines and the final governance decision. Reconcile the result with the current approved decision baseline.
Explanation
Correct Answer
D:This checks the actual mechanism rather than merely declaring success: Inspect change analysis across affected engineering disciplines and the final governance decision. Reconcile the result with the current approved decision baseline. The desired observed result is The approved plan reflects coherent cross-functional impacts instead of isolated equipment changes. The decision can be traced to the review evidence. [R158 R158-Q0382; case R158-C096; CAPM domain 2, task 2.2; source ECO.]
Incorrect Answers
A:This is a tempting but unsupported shortcut in this case: Approving the new unit by engineering preference alone ignores budget, safety and interface effects. It does not show that The approved plan reflects coherent cross-functional impacts instead of isolated equipment changes. The decision can be traced to the review evidence. [R158 R158-Q0382; case R158-C096; CAPM domain 2, task 2.2; source ECO.]
B:The proposed verify (Review sample size, critical defect count and the agreed acceptance limit. Retain the initiating evidence for audit.) comes from a different Predictive project schedule and methods situation: A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. It does not resolve or independently test the stated issue: A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost. Here, the relevant check is Inspect change analysis across affected engineering disciplines and the final governance decision. Reconcile the result with the current approved decision baseline. [R158 R158-Q0382; case R158-C096; CAPM domain 2, task 2.2; source ECO.]
C:This option concerns a different Predictive project schedule and methods situation: A project WBS has vague headings such as weekly calls and team morale but lacks identifiable deliverables for the security audit. For the reported case, use this verification: Inspect change analysis across affected engineering disciplines and the final governance decision. Reconcile the result with the current approved decision baseline.
Question 383
Which statement most accurately flags a misleading shortcut to avoid in this Integration-change-impact case? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Approving the new unit by engineering preference alone ignores budget, safety and interface effects.
- Inspect change analysis across affected engineering disciplines and the final governance decision. Reconcile the result with the current approved decision baseline.
- The approved plan reflects coherent cross-functional impacts instead of isolated equipment changes. The decision can be traced to the review evidence.
- Evaluate the integrated impact on scope, schedule, cost, interfaces and approvals before altering baselines. Document impacted stakeholders and the decision owner at the review.
Explanation
Correct Answer
A:The shortcut is mistaken: Approving the new unit by engineering preference alone ignores budget, safety and interface effects. The appropriate response is to evaluate the integrated impact on scope, schedule, cost, interfaces and approvals before altering baselines. Document impacted stakeholders and the decision owner at the review.
Incorrect Answers
B:This is an appropriate independent test of the proposed decision: Inspect change analysis across affected engineering disciplines and the final governance decision. Reconcile the result with the current approved decision baseline. It is not the invalid shortcut.
C:This is a relevant outcome to seek after the decision: The approved plan reflects coherent cross-functional impacts instead of isolated equipment changes. The decision can be traced to the review evidence. It is not an unsupported assumption.
D:This is a supported decision, not the unsupported claim: Evaluate the integrated impact on scope, schedule, cost, interfaces and approvals before altering baselines. Document impacted stakeholders and the decision owner at the review. It responds to the actual project issue: A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost.
Question 384
Select TWO case-specific elements of a justified Integration-change-impact resolution : the decision and its direct evidence. At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Evaluate the integrated impact on scope, schedule, cost, interfaces and approvals before altering baselines. Document impacted stakeholders and the decision owner at the review.
- Review sample size, critical defect count and the agreed acceptance limit. Reconcile the result with the current approved decision baseline.
- Calculate schedule variance as EV minus PV, yielding negative $15,000 of budget-valued schedule variance. Record the rationale before the next commitment.
- Approving the new unit by engineering preference alone ignores budget, safety and interface effects.
- Inspect change analysis across affected engineering disciplines and the final governance decision. Reconcile the result with the current approved decision baseline.
Explanation
Correct Answer
A:The case evidence identifies A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost. The specified decision directly addresses it: Evaluate the integrated impact on scope, schedule, cost, interfaces and approvals before altering baselines. Document impacted stakeholders and the decision owner at the review. This can be checked using Inspect change analysis across affected engineering disciplines and the final governance decision. Reconcile the result with the current approved decision baseline. [R158 R158-Q0384; case R158-C096; CAPM domain 2, task 2.2; source ECO.]
E:This checks the actual mechanism rather than merely declaring success: Inspect change analysis across affected engineering disciplines and the final governance decision. Reconcile the result with the current approved decision baseline. The desired observed result is The approved plan reflects coherent cross-functional impacts instead of isolated equipment changes. The decision can be traced to the review evidence. [R158 R158-Q0384; case R158-C096; CAPM domain 2, task 2.2; source ECO.]
Incorrect Answers
B:The proposed verify (Review sample size, critical defect count and the agreed acceptance limit. Reconcile the result with the current approved decision baseline.) comes from a different Predictive project schedule and methods situation: A manufacturing project must verify at most two critical defects per 1,000 units, but the team reports only completion of inspection paperwork. It does not resolve or independently test the stated issue: A client requests a larger refrigeration unit that affects power demand, structural loads and installation cost. Here, the relevant check is Inspect change analysis across affected engineering disciplines and the final governance decision. Reconcile the result with the current approved decision baseline. [R158 R158-Q0384; case R158-C096; CAPM domain 2, task 2.2; source ECO.]
C:This option concerns a different Predictive project schedule and methods situation: A predictive project has PV=$90,000 and EV=$75,000 at the review date. For the reported case, use this verification: Inspect change analysis across affected engineering disciplines and the final governance decision. Reconcile the result with the current approved decision baseline.
D:This is a tempting but unsupported shortcut in this case: Approving the new unit by engineering preference alone ignores budget, safety and interface effects. It does not show that The approved plan reflects coherent cross-functional impacts instead of isolated equipment changes. The decision can be traced to the review evidence. [R158 R158-Q0384; case R158-C096; CAPM domain 2, task 2.2; source ECO.]
Question 385
Which project-management decision best addresses the Cost-variance-calculation situation ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A construction update reports EV=$64,000 and AC=$72,000. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Record the rationale before the next commitment.
- Calculating PV−EV would measure schedule variance, not the cost variance in this case.
- Report favorable CV=+$15k and unfavorable SV=−$20k as separate facts requiring different explanations. Document impacted stakeholders and the decision owner at the review.
- Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Record the rationale before the next commitment.
Explanation
Correct Answer
A:The case evidence identifies A construction update reports EV=$64,000 and AC=$72,000. The specified decision directly addresses it: Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Record the rationale before the next commitment. This can be checked using Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit. [R158 R158-Q0385; case R158-C097; CAPM domain 2, task 2.3; source EVM.]
Incorrect Answers
B:This is a tempting but unsupported shortcut in this case: Calculating PV−EV would measure schedule variance, not the cost variance in this case. It does not show that The team reports an $8,000 cost overrun relative to the value of work earned. The result is recorded in the project controls. [R158 R158-Q0385; case R158-C097; CAPM domain 2, task 2.3; source EVM.]
C:The proposed action (Report favorable CV=+$15k and unfavorable SV=−$20k as separate facts requiring different explanations. Document impacted stakeholders and the decision owner at the review.) comes from a different Predictive project controls situation: A team records EV=$180k, AC=$165k and PV=$200k but announces the project is simply ahead because spending is favorable. It does not resolve or independently test the stated issue: A construction update reports EV=$64,000 and AC=$72,000. Here, the relevant check is Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit. [R158 R158-Q0385; case R158-C097; CAPM domain 2, task 2.3; source EVM.]
D:The proposed action (Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Record the rationale before the next commitment.) comes from a different Predictive project controls situation: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. It does not resolve or independently test the stated issue: A construction update reports EV=$64,000 and AC=$72,000. Here, the relevant check is Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit. [R158 R158-Q0385; case R158-C097; CAPM domain 2, task 2.3; source EVM.]
Question 386
After a corrective decision on Cost-variance-calculation, which independent evidence most directly verifies the result ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A construction update reports EV=$64,000 and AC=$72,000. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Calculating PV−EV would measure schedule variance, not the cost variance in this case.
- Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit.
- Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit.
- Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit.
Explanation
Correct Answer
C:This checks the actual mechanism rather than merely declaring success: Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit. The desired observed result is The team reports an $8,000 cost overrun relative to the value of work earned. The result is recorded in the project controls. [R158 R158-Q0386; case R158-C097; CAPM domain 2, task 2.3; source EVM.]
Incorrect Answers
A:This is a tempting but unsupported shortcut in this case: Calculating PV−EV would measure schedule variance, not the cost variance in this case. It does not show that The team reports an $8,000 cost overrun relative to the value of work earned. The result is recorded in the project controls. [R158 R158-Q0386; case R158-C097; CAPM domain 2, task 2.3; source EVM.]
B:The proposed verify (Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit.) comes from a different Predictive project controls situation: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. It does not resolve or independently test the stated issue: A construction update reports EV=$64,000 and AC=$72,000. Here, the relevant check is Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit. [R158 R158-Q0386; case R158-C097; CAPM domain 2, task 2.3; source EVM.]
D:This option concerns a different Predictive project controls situation: A cost report has three revised target budgets but no approvals or dates, making variance comparisons inconsistent. For the reported case, use this verification: Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit.
Question 387
Which statement most accurately flags a misleading shortcut to avoid in this Cost-variance-calculation case? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A construction update reports EV=$64,000 and AC=$72,000. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- The team reports an $8,000 cost overrun relative to the value of work earned. The result is recorded in the project controls.
- Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Record the rationale before the next commitment.
- Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit.
- Calculating PV−EV would measure schedule variance, not the cost variance in this case.
Explanation
Correct Answer
D:The shortcut is mistaken: Calculating PV−EV would measure schedule variance, not the cost variance in this case. The appropriate response is to calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Record the rationale before the next commitment.
Incorrect Answers
A:This is a relevant outcome to seek after the decision: The team reports an $8,000 cost overrun relative to the value of work earned. The result is recorded in the project controls. It is not an unsupported assumption.
B:This is a supported decision, not the unsupported claim: Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Record the rationale before the next commitment. It responds to the actual project issue: A construction update reports EV=$64,000 and AC=$72,000.
C:This is an appropriate independent test of the proposed decision: Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit. It is not the invalid shortcut.
Question 388
Select TWO case-specific elements of a justified Cost-variance-calculation resolution : the decision and its direct evidence. During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A construction update reports EV=$64,000 and AC=$72,000. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Record the rationale before the next commitment.
- Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit.
- Calculating PV−EV would measure schedule variance, not the cost variance in this case.
- Calculate EV−AC=+15 and EV−PV=−20 (thousands) before interpreting performance. Reconcile the result with the current approved decision baseline.
- Compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Record the rationale before the next commitment.
Explanation
Correct Answer
A:The case evidence identifies A construction update reports EV=$64,000 and AC=$72,000. The specified decision directly addresses it: Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Record the rationale before the next commitment. This can be checked using Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit. [R158 R158-Q0388; case R158-C097; CAPM domain 2, task 2.3; source EVM.]
B:This checks the actual mechanism rather than merely declaring success: Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit. The desired observed result is The team reports an $8,000 cost overrun relative to the value of work earned. The result is recorded in the project controls. [R158 R158-Q0388; case R158-C097; CAPM domain 2, task 2.3; source EVM.]
Incorrect Answers
C:This is a tempting but unsupported shortcut in this case: Calculating PV−EV would measure schedule variance, not the cost variance in this case. It does not show that The team reports an $8,000 cost overrun relative to the value of work earned. The result is recorded in the project controls. [R158 R158-Q0388; case R158-C097; CAPM domain 2, task 2.3; source EVM.]
D:The proposed verify (Calculate EV−AC=+15 and EV−PV=−20 (thousands) before interpreting performance. Reconcile the result with the current approved decision baseline.) comes from a different Predictive project controls situation: A team records EV=$180k, AC=$165k and PV=$200k but announces the project is simply ahead because spending is favorable. It does not resolve or independently test the stated issue: A construction update reports EV=$64,000 and AC=$72,000. Here, the relevant check is Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit. [R158 R158-Q0388; case R158-C097; CAPM domain 2, task 2.3; source EVM.]
E:This option concerns a different Predictive project controls situation: A controlled work package has EV=$120,000 and AC=$150,000 at review. For the reported case, use this verification: Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit.
Question 389
Which project-management decision best addresses the Cost-variance-calculation situation ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A construction update reports EV=$64,000 and AC=$72,000. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Document impacted stakeholders and the decision owner at the review.
- Calculating PV−EV would measure schedule variance, not the cost variance in this case.
- Maintain version-controlled, formally approved baselines and compare performance to the baseline authorized for the reporting period. Record the rationale before the next commitment.
- Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Record the rationale before the next commitment.
Explanation
Correct Answer
A:The case evidence identifies A construction update reports EV=$64,000 and AC=$72,000. The specified decision directly addresses it: Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Document impacted stakeholders and the decision owner at the review. This can be checked using Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline. [R158 R158-Q0389; case R158-C098; CAPM domain 2, task 2.3; source EVM.]
Incorrect Answers
B:This is a tempting but unsupported shortcut in this case: Calculating PV−EV would measure schedule variance, not the cost variance in this case. It does not show that The team reports an $8,000 cost overrun relative to the value of work earned. The decision can be traced to the review evidence. [R158 R158-Q0389; case R158-C098; CAPM domain 2, task 2.3; source EVM.]
C:The proposed action (Maintain version-controlled, formally approved baselines and compare performance to the baseline authorized for the reporting period. Record the rationale before the next commitment.) comes from a different Predictive project controls situation: A cost report has three revised target budgets but no approvals or dates, making variance comparisons inconsistent. It does not resolve or independently test the stated issue: A construction update reports EV=$64,000 and AC=$72,000. Here, the relevant check is Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline. [R158 R158-Q0389; case R158-C098; CAPM domain 2, task 2.3; source EVM.]
D:This option concerns a different Predictive project controls situation: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. For the reported case, use this verification: Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline.
Question 390
After a corrective decision on Cost-variance-calculation, which independent evidence most directly verifies the result ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A construction update reports EV=$64,000 and AC=$72,000. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit.
- Calculating PV−EV would measure schedule variance, not the cost variance in this case.
- Calculate EV−AC=+15 and EV−PV=−20 (thousands) before interpreting performance. Retain the initiating evidence for audit.
- Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline.
Explanation
Correct Answer
D:This checks the actual mechanism rather than merely declaring success: Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline. The desired observed result is The team reports an $8,000 cost overrun relative to the value of work earned. The decision can be traced to the review evidence. [R158 R158-Q0390; case R158-C098; CAPM domain 2, task 2.3; source EVM.]
Incorrect Answers
A:The proposed verify (Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit.) comes from a different Predictive project controls situation: A cost report has three revised target budgets but no approvals or dates, making variance comparisons inconsistent. It does not resolve or independently test the stated issue: A construction update reports EV=$64,000 and AC=$72,000. Here, the relevant check is Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline. [R158 R158-Q0390; case R158-C098; CAPM domain 2, task 2.3; source EVM.]
B:This is a tempting but unsupported shortcut in this case: Calculating PV−EV would measure schedule variance, not the cost variance in this case. It does not show that The team reports an $8,000 cost overrun relative to the value of work earned. The decision can be traced to the review evidence. [R158 R158-Q0390; case R158-C098; CAPM domain 2, task 2.3; source EVM.]
C:The proposed verify (Calculate EV−AC=+15 and EV−PV=−20 (thousands) before interpreting performance. Retain the initiating evidence for audit.) comes from a different Predictive project controls situation: A team records EV=$180k, AC=$165k and PV=$200k but announces the project is simply ahead because spending is favorable. It does not resolve or independently test the stated issue: A construction update reports EV=$64,000 and AC=$72,000. Here, the relevant check is Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline. [R158 R158-Q0390; case R158-C098; CAPM domain 2, task 2.3; source EVM.]