Question 400
Which observed result supports acceptance of the CPI-performance-interpretation corrective decision ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A controlled work package has EV=$120,000 and AC=$150,000 at review. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- The dashboard shows less budget-valued work completed than was planned by the data date. The decision can be traced to the review evidence.
- The dashboard shows less budget-valued work completed than was planned by the data date. The result is recorded in the project controls.
- The cost dashboard shows 80 cents of earned value per dollar of actual cost. The decision can be traced to the review evidence.
- Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency.
Explanation
Correct Answer
C:The stated result demonstrates the case acceptance condition: The cost dashboard shows 80 cents of earned value per dollar of actual cost. The decision can be traced to the review evidence. It depends on the decision Compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Document impacted stakeholders and the decision owner at the review.
Incorrect Answers
A:The proposed outcome (The dashboard shows less budget-valued work completed than was planned by the data date. The decision can be traced to the review evidence.) comes from a different Predictive project controls situation: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. It does not resolve or independently test the stated issue: A controlled work package has EV=$120,000 and AC=$150,000 at review. Here, the relevant check is Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Reconcile the result with the current approved decision baseline. [R158 R158-Q0400; case R158-C100; CAPM domain 2, task 2.3; source EVM.]
B:The proposed outcome (The dashboard shows less budget-valued work completed than was planned by the data date. The result is recorded in the project controls.) comes from a different Predictive project controls situation: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. It does not resolve or independently test the stated issue: A controlled work package has EV=$120,000 and AC=$150,000 at review. Here, the relevant check is Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Reconcile the result with the current approved decision baseline. [R158 R158-Q0400; case R158-C100; CAPM domain 2, task 2.3; source EVM.]
D:This is a tempting but unsupported shortcut in this case: Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency. It does not show that The cost dashboard shows 80 cents of earned value per dollar of actual cost. The decision can be traced to the review evidence. [R158 R158-Q0400; case R158-C100; CAPM domain 2, task 2.3; source EVM.]
Question 401
Which project-management decision best addresses the SPI-performance-interpretation situation ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Record the rationale before the next commitment.
- Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Document impacted stakeholders and the decision owner at the review.
- Dividing EV by AC would measure CPI rather than SPI.
- Maintain version-controlled, formally approved baselines and compare performance to the baseline authorized for the reporting period. Document impacted stakeholders and the decision owner at the review.
Explanation
Correct Answer
A:The case evidence identifies A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. The specified decision directly addresses it: Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Record the rationale before the next commitment. This can be checked using Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit. [R158 R158-Q0401; case R158-C101; CAPM domain 2, task 2.3; source EVM.]
Incorrect Answers
B:The proposed action (Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Document impacted stakeholders and the decision owner at the review.) comes from a different Predictive project controls situation: A construction update reports EV=$64,000 and AC=$72,000. It does not resolve or independently test the stated issue: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Here, the relevant check is Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit. [R158 R158-Q0401; case R158-C101; CAPM domain 2, task 2.3; source EVM.]
C:This is a tempting but unsupported shortcut in this case: Dividing EV by AC would measure CPI rather than SPI. It does not show that The dashboard shows less budget-valued work completed than was planned by the data date. The result is recorded in the project controls. [R158 R158-Q0401; case R158-C101; CAPM domain 2, task 2.3; source EVM.]
D:The proposed action (Maintain version-controlled, formally approved baselines and compare performance to the baseline authorized for the reporting period. Document impacted stakeholders and the decision owner at the review.) comes from a different Predictive project controls situation: A cost report has three revised target budgets but no approvals or dates, making variance comparisons inconsistent. It does not resolve or independently test the stated issue: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Here, the relevant check is Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit. [R158 R158-Q0401; case R158-C101; CAPM domain 2, task 2.3; source EVM.]
Question 402
After a corrective decision on SPI-performance-interpretation, which independent evidence most directly verifies the result ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline.
- Dividing EV by AC would measure CPI rather than SPI.
- Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit.
- Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit.
Explanation
Correct Answer
D:This checks the actual mechanism rather than merely declaring success: Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit. The desired observed result is The dashboard shows less budget-valued work completed than was planned by the data date. The result is recorded in the project controls. [R158 R158-Q0402; case R158-C101; CAPM domain 2, task 2.3; source EVM.]
Incorrect Answers
A:The proposed verify (Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline.) comes from a different Predictive project controls situation: A construction update reports EV=$64,000 and AC=$72,000. It does not resolve or independently test the stated issue: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Here, the relevant check is Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit. [R158 R158-Q0402; case R158-C101; CAPM domain 2, task 2.3; source EVM.]
B:This is a tempting but unsupported shortcut in this case: Dividing EV by AC would measure CPI rather than SPI. It does not show that The dashboard shows less budget-valued work completed than was planned by the data date. The result is recorded in the project controls. [R158 R158-Q0402; case R158-C101; CAPM domain 2, task 2.3; source EVM.]
C:The proposed verify (Verify the subtractive calculation and distinguish AC from the planned-value baseline. Retain the initiating evidence for audit.) comes from a different Predictive project controls situation: A construction update reports EV=$64,000 and AC=$72,000. It does not resolve or independently test the stated issue: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Here, the relevant check is Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit. [R158 R158-Q0402; case R158-C101; CAPM domain 2, task 2.3; source EVM.]
Question 403
Which statement most accurately flags a misleading shortcut to avoid in this SPI-performance-interpretation case? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- The dashboard shows less budget-valued work completed than was planned by the data date. The result is recorded in the project controls.
- Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Record the rationale before the next commitment.
- Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit.
- Dividing EV by AC would measure CPI rather than SPI.
Explanation
Correct Answer
D:The shortcut is mistaken: Dividing EV by AC would measure CPI rather than SPI. The appropriate response is to compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Record the rationale before the next commitment.
Incorrect Answers
A:This is a relevant outcome to seek after the decision: The dashboard shows less budget-valued work completed than was planned by the data date. The result is recorded in the project controls. It is not an unsupported assumption.
B:This is a supported decision, not the unsupported claim: Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Record the rationale before the next commitment. It responds to the actual project issue: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date.
C:This is an appropriate independent test of the proposed decision: Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit. It is not the invalid shortcut.
Question 404
Select TWO case-specific elements of a justified SPI-performance-interpretation resolution : the decision and its direct evidence. During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Dividing EV by AC would measure CPI rather than SPI.
- Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit.
- Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit.
- Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Record the rationale before the next commitment.
- Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Document impacted stakeholders and the decision owner at the review.
Explanation
Correct Answer
B:This checks the actual mechanism rather than merely declaring success: Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit. The desired observed result is The dashboard shows less budget-valued work completed than was planned by the data date. The result is recorded in the project controls. [R158 R158-Q0404; case R158-C101; CAPM domain 2, task 2.3; source EVM.]
D:The case evidence identifies A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. The specified decision directly addresses it: Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Record the rationale before the next commitment. This can be checked using Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit. [R158 R158-Q0404; case R158-C101; CAPM domain 2, task 2.3; source EVM.]
Incorrect Answers
A:This is a tempting but unsupported shortcut in this case: Dividing EV by AC would measure CPI rather than SPI. It does not show that The dashboard shows less budget-valued work completed than was planned by the data date. The result is recorded in the project controls. [R158 R158-Q0404; case R158-C101; CAPM domain 2, task 2.3; source EVM.]
C:The proposed verify (Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit.) comes from a different Predictive project controls situation: A cost report has three revised target budgets but no approvals or dates, making variance comparisons inconsistent. It does not resolve or independently test the stated issue: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Here, the relevant check is Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit. [R158 R158-Q0404; case R158-C101; CAPM domain 2, task 2.3; source EVM.]
E:The proposed action (Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Document impacted stakeholders and the decision owner at the review.) comes from a different Predictive project controls situation: A construction update reports EV=$64,000 and AC=$72,000. It does not resolve or independently test the stated issue: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Here, the relevant check is Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Retain the initiating evidence for audit. [R158 R158-Q0404; case R158-C101; CAPM domain 2, task 2.3; source EVM.]
Question 405
Which project-management decision best addresses the SPI-performance-interpretation situation ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Report favorable CV=+$15k and unfavorable SV=−$20k as separate facts requiring different explanations. Document impacted stakeholders and the decision owner at the review.
- Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Document impacted stakeholders and the decision owner at the review.
- Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Record the rationale before the next commitment.
- Dividing EV by AC would measure CPI rather than SPI.
Explanation
Correct Answer
B:The case evidence identifies A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. The specified decision directly addresses it: Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Document impacted stakeholders and the decision owner at the review. This can be checked using Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Reconcile the result with the current approved decision baseline. [R158 R158-Q0405; case R158-C102; CAPM domain 2, task 2.3; source EVM.]
Incorrect Answers
A:The proposed action (Report favorable CV=+$15k and unfavorable SV=−$20k as separate facts requiring different explanations. Document impacted stakeholders and the decision owner at the review.) comes from a different Predictive project controls situation: A team records EV=$180k, AC=$165k and PV=$200k but announces the project is simply ahead because spending is favorable. It does not resolve or independently test the stated issue: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Here, the relevant check is Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Reconcile the result with the current approved decision baseline. [R158 R158-Q0405; case R158-C102; CAPM domain 2, task 2.3; source EVM.]
C:This option concerns a different Predictive project controls situation: A construction update reports EV=$64,000 and AC=$72,000. For the reported case, use this verification: Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Reconcile the result with the current approved decision baseline.
D:This is a tempting but unsupported shortcut in this case: Dividing EV by AC would measure CPI rather than SPI. It does not show that The dashboard shows less budget-valued work completed than was planned by the data date. The decision can be traced to the review evidence. [R158 R158-Q0405; case R158-C102; CAPM domain 2, task 2.3; source EVM.]
Question 406
After a corrective decision on SPI-performance-interpretation, which independent evidence most directly verifies the result ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit.
- Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Reconcile the result with the current approved decision baseline.
- Dividing EV by AC would measure CPI rather than SPI.
- Calculate EV−AC=+15 and EV−PV=−20 (thousands) before interpreting performance. Retain the initiating evidence for audit.
Explanation
Correct Answer
B:This checks the actual mechanism rather than merely declaring success: Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Reconcile the result with the current approved decision baseline. The desired observed result is The dashboard shows less budget-valued work completed than was planned by the data date. The decision can be traced to the review evidence. [R158 R158-Q0406; case R158-C102; CAPM domain 2, task 2.3; source EVM.]
Incorrect Answers
A:The proposed verify (Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit.) comes from a different Predictive project controls situation: A cost report has three revised target budgets but no approvals or dates, making variance comparisons inconsistent. It does not resolve or independently test the stated issue: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Here, the relevant check is Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Reconcile the result with the current approved decision baseline. [R158 R158-Q0406; case R158-C102; CAPM domain 2, task 2.3; source EVM.]
C:This is a tempting but unsupported shortcut in this case: Dividing EV by AC would measure CPI rather than SPI. It does not show that The dashboard shows less budget-valued work completed than was planned by the data date. The decision can be traced to the review evidence. [R158 R158-Q0406; case R158-C102; CAPM domain 2, task 2.3; source EVM.]
D:The proposed verify (Calculate EV−AC=+15 and EV−PV=−20 (thousands) before interpreting performance. Retain the initiating evidence for audit.) comes from a different Predictive project controls situation: A team records EV=$180k, AC=$165k and PV=$200k but announces the project is simply ahead because spending is favorable. It does not resolve or independently test the stated issue: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Here, the relevant check is Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Reconcile the result with the current approved decision baseline. [R158 R158-Q0406; case R158-C102; CAPM domain 2, task 2.3; source EVM.]
Question 407
Which statement most accurately flags a misleading shortcut to avoid in this SPI-performance-interpretation case? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Dividing EV by AC would measure CPI rather than SPI.
- The dashboard shows less budget-valued work completed than was planned by the data date. The decision can be traced to the review evidence.
- Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Document impacted stakeholders and the decision owner at the review.
- Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Reconcile the result with the current approved decision baseline.
Explanation
Correct Answer
A:The shortcut is mistaken: Dividing EV by AC would measure CPI rather than SPI. The appropriate response is to compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Document impacted stakeholders and the decision owner at the review.
Incorrect Answers
B:This is a relevant outcome to seek after the decision: The dashboard shows less budget-valued work completed than was planned by the data date. The decision can be traced to the review evidence. It is not an unsupported assumption.
C:This is a supported decision, not the unsupported claim: Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Document impacted stakeholders and the decision owner at the review. It responds to the actual project issue: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date.
D:This is an appropriate independent test of the proposed decision: Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Reconcile the result with the current approved decision baseline. It is not the invalid shortcut.
Question 408
Select TWO case-specific elements of a justified SPI-performance-interpretation resolution : the decision and its direct evidence. At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Dividing EV by AC would measure CPI rather than SPI.
- Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Document impacted stakeholders and the decision owner at the review.
- Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Reconcile the result with the current approved decision baseline.
- Maintain version-controlled, formally approved baselines and compare performance to the baseline authorized for the reporting period. Record the rationale before the next commitment.
- Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Retain the initiating evidence for audit.
Explanation
Correct Answer
B:The case evidence identifies A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. The specified decision directly addresses it: Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Document impacted stakeholders and the decision owner at the review. This can be checked using Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Reconcile the result with the current approved decision baseline. [R158 R158-Q0408; case R158-C102; CAPM domain 2, task 2.3; source EVM.]
C:This checks the actual mechanism rather than merely declaring success: Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Reconcile the result with the current approved decision baseline. The desired observed result is The dashboard shows less budget-valued work completed than was planned by the data date. The decision can be traced to the review evidence. [R158 R158-Q0408; case R158-C102; CAPM domain 2, task 2.3; source EVM.]
Incorrect Answers
A:This is a tempting but unsupported shortcut in this case: Dividing EV by AC would measure CPI rather than SPI. It does not show that The dashboard shows less budget-valued work completed than was planned by the data date. The decision can be traced to the review evidence. [R158 R158-Q0408; case R158-C102; CAPM domain 2, task 2.3; source EVM.]
D:The proposed action (Maintain version-controlled, formally approved baselines and compare performance to the baseline authorized for the reporting period. Record the rationale before the next commitment.) comes from a different Predictive project controls situation: A cost report has three revised target budgets but no approvals or dates, making variance comparisons inconsistent. It does not resolve or independently test the stated issue: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. Here, the relevant check is Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Reconcile the result with the current approved decision baseline. [R158 R158-Q0408; case R158-C102; CAPM domain 2, task 2.3; source EVM.]
E:This option concerns a different Predictive project controls situation: A controlled work package has EV=$120,000 and AC=$150,000 at review. For the reported case, use this verification: Verify 56,000÷70,000=0.80 using matched status dates and budgeted values. Reconcile the result with the current approved decision baseline.
Question 409
Which project-management decision best addresses the Baseline-control-audit-trail situation ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A cost report has three revised target budgets but no approvals or dates, making variance comparisons inconsistent. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Document impacted stakeholders and the decision owner at the review.
- Report favorable CV=+$15k and unfavorable SV=−$20k as separate facts requiring different explanations. Record the rationale before the next commitment.
- Replacing the baseline after every adverse variance makes the report look favorable but destroys control history.
- Maintain version-controlled, formally approved baselines and compare performance to the baseline authorized for the reporting period. Record the rationale before the next commitment.
Explanation
Correct Answer
D:The case evidence identifies A cost report has three revised target budgets but no approvals or dates, making variance comparisons inconsistent. The specified decision directly addresses it: Maintain version-controlled, formally approved baselines and compare performance to the baseline authorized for the reporting period. Record the rationale before the next commitment. This can be checked using Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit. [R158 R158-Q0409; case R158-C103; CAPM domain 2, task 2.3; source ECO.]
Incorrect Answers
A:This option concerns a different Predictive project controls situation: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. For the reported case, use this verification: Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit.
B:The proposed action (Report favorable CV=+$15k and unfavorable SV=−$20k as separate facts requiring different explanations. Record the rationale before the next commitment.) comes from a different Predictive project controls situation: A team records EV=$180k, AC=$165k and PV=$200k but announces the project is simply ahead because spending is favorable. It does not resolve or independently test the stated issue: A cost report has three revised target budgets but no approvals or dates, making variance comparisons inconsistent. Here, the relevant check is Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit. [R158 R158-Q0409; case R158-C103; CAPM domain 2, task 2.3; source ECO.]
C:This is a tempting but unsupported shortcut in this case: Replacing the baseline after every adverse variance makes the report look favorable but destroys control history. It does not show that Reviewers can reproduce variances without silently switching the comparison basis. The result is recorded in the project controls. [R158 R158-Q0409; case R158-C103; CAPM domain 2, task 2.3; source ECO.]
Question 410
After a corrective decision on Baseline-control-audit-trail, which independent evidence most directly verifies the result ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A cost report has three revised target budgets but no approvals or dates, making variance comparisons inconsistent. Assume the named constraints and approvals are genuine and that no unrelated problem is present.
- Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline.
- Calculate EV−AC=+15 and EV−PV=−20 (thousands) before interpreting performance. Reconcile the result with the current approved decision baseline.
- Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit.
- Replacing the baseline after every adverse variance makes the report look favorable but destroys control history.
Explanation
Correct Answer
C:This checks the actual mechanism rather than merely declaring success: Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit. The desired observed result is Reviewers can reproduce variances without silently switching the comparison basis. The result is recorded in the project controls. [R158 R158-Q0410; case R158-C103; CAPM domain 2, task 2.3; source ECO.]
Incorrect Answers
A:The proposed verify (Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline.) comes from a different Predictive project controls situation: A construction update reports EV=$64,000 and AC=$72,000. It does not resolve or independently test the stated issue: A cost report has three revised target budgets but no approvals or dates, making variance comparisons inconsistent. Here, the relevant check is Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit. [R158 R158-Q0410; case R158-C103; CAPM domain 2, task 2.3; source ECO.]
B:The proposed verify (Calculate EV−AC=+15 and EV−PV=−20 (thousands) before interpreting performance. Reconcile the result with the current approved decision baseline.) comes from a different Predictive project controls situation: A team records EV=$180k, AC=$165k and PV=$200k but announces the project is simply ahead because spending is favorable. It does not resolve or independently test the stated issue: A cost report has three revised target budgets but no approvals or dates, making variance comparisons inconsistent. Here, the relevant check is Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit. [R158 R158-Q0410; case R158-C103; CAPM domain 2, task 2.3; source ECO.]
D:This is a tempting but unsupported shortcut in this case: Replacing the baseline after every adverse variance makes the report look favorable but destroys control history. It does not show that Reviewers can reproduce variances without silently switching the comparison basis. The result is recorded in the project controls. [R158 R158-Q0410; case R158-C103; CAPM domain 2, task 2.3; source ECO.]