PMI CAPM Exam Dumps, Practice Test Questions

100% Latest & Updated PMI CAPM Practice Test Questions, Exam Dumps & Verified Answers!
30 Days Free Updates, Instant Download!

PMI CAPM Premium Bundle
$79.97
$59.98

CAPM Premium Bundle

  • Premium File: 688 Questions & Answers. Last update: Nov 2, 2026
  • Training Course: 123 Video Lectures
  • Study Guide: 719 Pages
  • Latest Questions
  • 100% Accurate Answers
  • Fast Exam Updates

CAPM Premium Bundle

PMI CAPM Premium Bundle
  • Premium File: 688 Questions & Answers. Last update: Nov 2, 2026
  • Training Course: 123 Video Lectures
  • Study Guide: 719 Pages
  • Latest Questions
  • 100% Accurate Answers
  • Fast Exam Updates
$79.97
$59.98

PMI CAPM Practice Test 40

Question 390

After a corrective decision on Cost-variance-calculation, which independent evidence most directly verifies the result ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A construction update reports EV=$64,000 and AC=$72,000. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit.
  2. Calculating PV−EV would measure schedule variance, not the cost variance in this case.
  3. Calculate EV−AC=+15 and EV−PV=−20 (thousands) before interpreting performance. Retain the initiating evidence for audit.
  4. Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline.

Explanation

Correct Answer

D:

This checks the actual mechanism rather than merely declaring success: Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline. The desired observed result is The team reports an $8,000 cost overrun relative to the value of work earned. The decision can be traced to the review evidence. [R158 R158-Q0390; case R158-C098; CAPM domain 2, task 2.3; source EVM.]

Incorrect Answers

A:

The proposed verify (Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit.) comes from a different Predictive project controls situation: A cost report has three revised target budgets but no approvals or dates, making variance comparisons inconsistent. It does not resolve or independently test the stated issue: A construction update reports EV=$64,000 and AC=$72,000. Here, the relevant check is Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline. [R158 R158-Q0390; case R158-C098; CAPM domain 2, task 2.3; source EVM.]

B:

This is a tempting but unsupported shortcut in this case: Calculating PV−EV would measure schedule variance, not the cost variance in this case. It does not show that The team reports an $8,000 cost overrun relative to the value of work earned. The decision can be traced to the review evidence. [R158 R158-Q0390; case R158-C098; CAPM domain 2, task 2.3; source EVM.]

C:

The proposed verify (Calculate EV−AC=+15 and EV−PV=−20 (thousands) before interpreting performance. Retain the initiating evidence for audit.) comes from a different Predictive project controls situation: A team records EV=$180k, AC=$165k and PV=$200k but announces the project is simply ahead because spending is favorable. It does not resolve or independently test the stated issue: A construction update reports EV=$64,000 and AC=$72,000. Here, the relevant check is Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline. [R158 R158-Q0390; case R158-C098; CAPM domain 2, task 2.3; source EVM.]

Question 391

Which statement most accurately flags a misleading shortcut to avoid in this Cost-variance-calculation case? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A construction update reports EV=$64,000 and AC=$72,000. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline.
  2. Calculating PV−EV would measure schedule variance, not the cost variance in this case.
  3. The team reports an $8,000 cost overrun relative to the value of work earned. The decision can be traced to the review evidence.
  4. Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Document impacted stakeholders and the decision owner at the review.

Explanation

Correct Answer

B:

The shortcut is mistaken: Calculating PV−EV would measure schedule variance, not the cost variance in this case. The appropriate response is to calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Document impacted stakeholders and the decision owner at the review.

Incorrect Answers

A:

This is an appropriate independent test of the proposed decision: Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline. It is not the invalid shortcut.

C:

This is a relevant outcome to seek after the decision: The team reports an $8,000 cost overrun relative to the value of work earned. The decision can be traced to the review evidence. It is not an unsupported assumption.

D:

This is a supported decision, not the unsupported claim: Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Document impacted stakeholders and the decision owner at the review. It responds to the actual project issue: A construction update reports EV=$64,000 and AC=$72,000.

Question 392

Select THREE consistent elements of the Cost-variance-calculation case: appropriate decision, verification, and observable success condition. At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A construction update reports EV=$64,000 and AC=$72,000. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Calculating PV−EV would measure schedule variance, not the cost variance in this case.
  2. The team reports an $8,000 cost overrun relative to the value of work earned. The decision can be traced to the review evidence.
  3. Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline.
  4. Compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Document impacted stakeholders and the decision owner at the review.
  5. Decision makers see spending efficiency and schedule progress separately instead of a misleading single status. The decision can be traced to the review evidence.
  6. Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Document impacted stakeholders and the decision owner at the review.

Explanation

Correct Answer

B:

The stated result demonstrates the case acceptance condition: The team reports an $8,000 cost overrun relative to the value of work earned. The decision can be traced to the review evidence. It depends on the decision Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Document impacted stakeholders and the decision owner at the review.

C:

This checks the actual mechanism rather than merely declaring success: Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline. The desired observed result is The team reports an $8,000 cost overrun relative to the value of work earned. The decision can be traced to the review evidence. [R158 R158-Q0392; case R158-C098; CAPM domain 2, task 2.3; source EVM.]

F:

The case evidence identifies A construction update reports EV=$64,000 and AC=$72,000. The specified decision directly addresses it: Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Document impacted stakeholders and the decision owner at the review. This can be checked using Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline. [R158 R158-Q0392; case R158-C098; CAPM domain 2, task 2.3; source EVM.]

Incorrect Answers

A:

This is a tempting but unsupported shortcut in this case: Calculating PV−EV would measure schedule variance, not the cost variance in this case. It does not show that The team reports an $8,000 cost overrun relative to the value of work earned. The decision can be traced to the review evidence. [R158 R158-Q0392; case R158-C098; CAPM domain 2, task 2.3; source EVM.]

D:

This option concerns a different Predictive project controls situation: A controlled work package has EV=$120,000 and AC=$150,000 at review. For the reported case, use this verification: Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline.

E:

The proposed outcome (Decision makers see spending efficiency and schedule progress separately instead of a misleading single status. The decision can be traced to the review evidence.) comes from a different Predictive project controls situation: A team records EV=$180k, AC=$165k and PV=$200k but announces the project is simply ahead because spending is favorable. It does not resolve or independently test the stated issue: A construction update reports EV=$64,000 and AC=$72,000. Here, the relevant check is Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline. [R158 R158-Q0392; case R158-C098; CAPM domain 2, task 2.3; source EVM.]

Question 393

Which project-management decision best addresses the CPI-performance-interpretation situation ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A controlled work package has EV=$120,000 and AC=$150,000 at review. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency.
  2. Compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Record the rationale before the next commitment.
  3. Report favorable CV=+$15k and unfavorable SV=−$20k as separate facts requiring different explanations. Document impacted stakeholders and the decision owner at the review.
  4. Compute SPI=EV/PV=0.80 and recognize an unfavorable planned-versus-earned progress ratio. Record the rationale before the next commitment.

Explanation

Correct Answer

B:

The case evidence identifies A controlled work package has EV=$120,000 and AC=$150,000 at review. The specified decision directly addresses it: Compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Record the rationale before the next commitment. This can be checked using Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Retain the initiating evidence for audit. [R158 R158-Q0393; case R158-C099; CAPM domain 2, task 2.3; source EVM.]

Incorrect Answers

A:

This is a tempting but unsupported shortcut in this case: Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency. It does not show that The cost dashboard shows 80 cents of earned value per dollar of actual cost. The result is recorded in the project controls. [R158 R158-Q0393; case R158-C099; CAPM domain 2, task 2.3; source EVM.]

C:

The proposed action (Report favorable CV=+$15k and unfavorable SV=−$20k as separate facts requiring different explanations. Document impacted stakeholders and the decision owner at the review.) comes from a different Predictive project controls situation: A team records EV=$180k, AC=$165k and PV=$200k but announces the project is simply ahead because spending is favorable. It does not resolve or independently test the stated issue: A controlled work package has EV=$120,000 and AC=$150,000 at review. Here, the relevant check is Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Retain the initiating evidence for audit. [R158 R158-Q0393; case R158-C099; CAPM domain 2, task 2.3; source EVM.]

D:

This option concerns a different Predictive project controls situation: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. For the reported case, use this verification: Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Retain the initiating evidence for audit.

Question 394

After a corrective decision on CPI-performance-interpretation, which independent evidence most directly verifies the result ? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A controlled work package has EV=$120,000 and AC=$150,000 at review. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Verify the subtractive calculation and distinguish AC from the planned-value baseline. Reconcile the result with the current approved decision baseline.
  2. Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Retain the initiating evidence for audit.
  3. Inspect change authorization, baseline effective dates and reconciliation of reported values. Retain the initiating evidence for audit.
  4. Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency.

Explanation

Correct Answer

B:

This checks the actual mechanism rather than merely declaring success: Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Retain the initiating evidence for audit. The desired observed result is The cost dashboard shows 80 cents of earned value per dollar of actual cost. The result is recorded in the project controls. [R158 R158-Q0394; case R158-C099; CAPM domain 2, task 2.3; source EVM.]

Incorrect Answers

A:

This option concerns a different Predictive project controls situation: A construction update reports EV=$64,000 and AC=$72,000. For the reported case, use this verification: Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Retain the initiating evidence for audit.

C:

This option concerns a different Predictive project controls situation: A cost report has three revised target budgets but no approvals or dates, making variance comparisons inconsistent. For the reported case, use this verification: Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Retain the initiating evidence for audit.

D:

This is a tempting but unsupported shortcut in this case: Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency. It does not show that The cost dashboard shows 80 cents of earned value per dollar of actual cost. The result is recorded in the project controls. [R158 R158-Q0394; case R158-C099; CAPM domain 2, task 2.3; source EVM.]

Question 395

Which statement most accurately flags a misleading shortcut to avoid in this CPI-performance-interpretation case? During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A controlled work package has EV=$120,000 and AC=$150,000 at review. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Record the rationale before the next commitment.
  2. Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Retain the initiating evidence for audit.
  3. Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency.
  4. The cost dashboard shows 80 cents of earned value per dollar of actual cost. The result is recorded in the project controls.

Explanation

Correct Answer

C:

The shortcut is mistaken: Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency. The appropriate response is to compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Record the rationale before the next commitment.

Incorrect Answers

A:

This is a supported decision, not the unsupported claim: Compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Record the rationale before the next commitment. It responds to the actual project issue: A controlled work package has EV=$120,000 and AC=$150,000 at review.

B:

This is an appropriate independent test of the proposed decision: Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Retain the initiating evidence for audit. It is not the invalid shortcut.

D:

This is a relevant outcome to seek after the decision: The cost dashboard shows 80 cents of earned value per dollar of actual cost. The result is recorded in the project controls. It is not an unsupported assumption.

Question 396

Select THREE consistent elements of the CPI-performance-interpretation case: appropriate decision, verification, and observable success condition. During scope and delivery planning, the team must make a documented decision before significant work proceeds. Scenario: A controlled work package has EV=$120,000 and AC=$150,000 at review. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Report favorable CV=+$15k and unfavorable SV=−$20k as separate facts requiring different explanations. Record the rationale before the next commitment.
  2. Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency.
  3. Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Retain the initiating evidence for audit.
  4. Decision makers see spending efficiency and schedule progress separately instead of a misleading single status. The decision can be traced to the review evidence.
  5. Compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Record the rationale before the next commitment.
  6. The cost dashboard shows 80 cents of earned value per dollar of actual cost. The result is recorded in the project controls.

Explanation

Correct Answer

C:

This checks the actual mechanism rather than merely declaring success: Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Retain the initiating evidence for audit. The desired observed result is The cost dashboard shows 80 cents of earned value per dollar of actual cost. The result is recorded in the project controls. [R158 R158-Q0396; case R158-C099; CAPM domain 2, task 2.3; source EVM.]

E:

The case evidence identifies A controlled work package has EV=$120,000 and AC=$150,000 at review. The specified decision directly addresses it: Compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Record the rationale before the next commitment. This can be checked using Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Retain the initiating evidence for audit. [R158 R158-Q0396; case R158-C099; CAPM domain 2, task 2.3; source EVM.]

F:

The stated result demonstrates the case acceptance condition: The cost dashboard shows 80 cents of earned value per dollar of actual cost. The result is recorded in the project controls. It depends on the decision Compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Record the rationale before the next commitment.

Incorrect Answers

A:

The proposed action (Report favorable CV=+$15k and unfavorable SV=−$20k as separate facts requiring different explanations. Record the rationale before the next commitment.) comes from a different Predictive project controls situation: A team records EV=$180k, AC=$165k and PV=$200k but announces the project is simply ahead because spending is favorable. It does not resolve or independently test the stated issue: A controlled work package has EV=$120,000 and AC=$150,000 at review. Here, the relevant check is Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Retain the initiating evidence for audit. [R158 R158-Q0396; case R158-C099; CAPM domain 2, task 2.3; source EVM.]

B:

This is a tempting but unsupported shortcut in this case: Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency. It does not show that The cost dashboard shows 80 cents of earned value per dollar of actual cost. The result is recorded in the project controls. [R158 R158-Q0396; case R158-C099; CAPM domain 2, task 2.3; source EVM.]

D:

The proposed outcome (Decision makers see spending efficiency and schedule progress separately instead of a misleading single status. The decision can be traced to the review evidence.) comes from a different Predictive project controls situation: A team records EV=$180k, AC=$165k and PV=$200k but announces the project is simply ahead because spending is favorable. It does not resolve or independently test the stated issue: A controlled work package has EV=$120,000 and AC=$150,000 at review. Here, the relevant check is Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Retain the initiating evidence for audit. [R158 R158-Q0396; case R158-C099; CAPM domain 2, task 2.3; source EVM.]

Question 397

Which project-management decision best addresses the CPI-performance-interpretation situation ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A controlled work package has EV=$120,000 and AC=$150,000 at review. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency.
  2. Report favorable CV=+$15k and unfavorable SV=−$20k as separate facts requiring different explanations. Record the rationale before the next commitment.
  3. Compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Document impacted stakeholders and the decision owner at the review.
  4. Calculate cost variance CV=EV−AC=−$8,000 and identify an unfavorable cost position. Document impacted stakeholders and the decision owner at the review.

Explanation

Correct Answer

C:

Compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Document impacted stakeholders and the decision owner at the review. To verify the specified result, verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Reconcile the result with the current approved decision baseline.

Incorrect Answers

A:

This is a tempting but unsupported shortcut in this case: Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency. It does not show that The cost dashboard shows 80 cents of earned value per dollar of actual cost. The decision can be traced to the review evidence. [R158 R158-Q0397; case R158-C100; CAPM domain 2, task 2.3; source EVM.]

B:

The proposed action (Report favorable CV=+$15k and unfavorable SV=−$20k as separate facts requiring different explanations. Record the rationale before the next commitment.) comes from a different Predictive project controls situation: A team records EV=$180k, AC=$165k and PV=$200k but announces the project is simply ahead because spending is favorable. It does not resolve or independently test the stated issue: A controlled work package has EV=$120,000 and AC=$150,000 at review. Here, the relevant check is Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Reconcile the result with the current approved decision baseline. [R158 R158-Q0397; case R158-C100; CAPM domain 2, task 2.3; source EVM.]

D:

This option concerns a different Predictive project controls situation: A construction update reports EV=$64,000 and AC=$72,000. For the reported case, use this verification: Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Reconcile the result with the current approved decision baseline.

Question 398

After a corrective decision on CPI-performance-interpretation, which independent evidence most directly verifies the result ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A controlled work package has EV=$120,000 and AC=$150,000 at review. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency.
  2. Calculate EV−AC=+15 and EV−PV=−20 (thousands) before interpreting performance. Reconcile the result with the current approved decision baseline.
  3. Calculate EV−AC=+15 and EV−PV=−20 (thousands) before interpreting performance. Retain the initiating evidence for audit.
  4. Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Reconcile the result with the current approved decision baseline.

Explanation

Correct Answer

D:

Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Reconcile the result with the current approved decision baseline. The expected result is the cost dashboard shows 80 cents of earned value per dollar of actual cost. The decision can be traced to the review evidence.

Incorrect Answers

A:

This is a tempting but unsupported shortcut in this case: Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency. It does not show that The cost dashboard shows 80 cents of earned value per dollar of actual cost. The decision can be traced to the review evidence. [R158 R158-Q0398; case R158-C100; CAPM domain 2, task 2.3; source EVM.]

B:

The proposed verify (Calculate EV−AC=+15 and EV−PV=−20 (thousands) before interpreting performance. Reconcile the result with the current approved decision baseline.) comes from a different Predictive project controls situation: A team records EV=$180k, AC=$165k and PV=$200k but announces the project is simply ahead because spending is favorable. It does not resolve or independently test the stated issue: A controlled work package has EV=$120,000 and AC=$150,000 at review. Here, the relevant check is Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Reconcile the result with the current approved decision baseline. [R158 R158-Q0398; case R158-C100; CAPM domain 2, task 2.3; source EVM.]

C:

The proposed verify (Calculate EV−AC=+15 and EV−PV=−20 (thousands) before interpreting performance. Retain the initiating evidence for audit.) comes from a different Predictive project controls situation: A team records EV=$180k, AC=$165k and PV=$200k but announces the project is simply ahead because spending is favorable. It does not resolve or independently test the stated issue: A controlled work package has EV=$120,000 and AC=$150,000 at review. Here, the relevant check is Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Reconcile the result with the current approved decision baseline. [R158 R158-Q0398; case R158-C100; CAPM domain 2, task 2.3; source EVM.]

Question 399

Which statement most accurately flags a misleading shortcut to avoid in this CPI-performance-interpretation case? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A controlled work package has EV=$120,000 and AC=$150,000 at review. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency.
  2. Compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Document impacted stakeholders and the decision owner at the review.
  3. Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Reconcile the result with the current approved decision baseline.
  4. The cost dashboard shows 80 cents of earned value per dollar of actual cost. The decision can be traced to the review evidence.

Explanation

Correct Answer

A:

The shortcut is mistaken: Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency. The appropriate response is to compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Document impacted stakeholders and the decision owner at the review.

Incorrect Answers

B:

This is a supported decision, not the unsupported claim: Compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Document impacted stakeholders and the decision owner at the review. It responds to the actual project issue: A controlled work package has EV=$120,000 and AC=$150,000 at review.

C:

This is an appropriate independent test of the proposed decision: Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Reconcile the result with the current approved decision baseline. It is not the invalid shortcut.

D:

This is a relevant outcome to seek after the decision: The cost dashboard shows 80 cents of earned value per dollar of actual cost. The decision can be traced to the review evidence. It is not an unsupported assumption.

Question 400

Which observed result supports acceptance of the CPI-performance-interpretation corrective decision ? At a later governance checkpoint, conflicting stakeholder pressure makes a second, evidence-based decision necessary. Scenario: A controlled work package has EV=$120,000 and AC=$150,000 at review. Assume the named constraints and approvals are genuine and that no unrelated problem is present.

  1. The dashboard shows less budget-valued work completed than was planned by the data date. The decision can be traced to the review evidence.
  2. The dashboard shows less budget-valued work completed than was planned by the data date. The result is recorded in the project controls.
  3. The cost dashboard shows 80 cents of earned value per dollar of actual cost. The decision can be traced to the review evidence.
  4. Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency.

Explanation

Correct Answer

C:

The stated result demonstrates the case acceptance condition: The cost dashboard shows 80 cents of earned value per dollar of actual cost. The decision can be traced to the review evidence. It depends on the decision Compute CPI=EV/AC=0.80 and flag spending inefficiency rather than claiming a 20% calendar slip. Document impacted stakeholders and the decision owner at the review.

Incorrect Answers

A:

The proposed outcome (The dashboard shows less budget-valued work completed than was planned by the data date. The decision can be traced to the review evidence.) comes from a different Predictive project controls situation: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. It does not resolve or independently test the stated issue: A controlled work package has EV=$120,000 and AC=$150,000 at review. Here, the relevant check is Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Reconcile the result with the current approved decision baseline. [R158 R158-Q0400; case R158-C100; CAPM domain 2, task 2.3; source EVM.]

B:

The proposed outcome (The dashboard shows less budget-valued work completed than was planned by the data date. The result is recorded in the project controls.) comes from a different Predictive project controls situation: A supplier-installation stream has EV=$56,000 and PV=$70,000 for the same status date. It does not resolve or independently test the stated issue: A controlled work package has EV=$120,000 and AC=$150,000 at review. Here, the relevant check is Verify 120,000÷150,000=0.80 and compare it with the efficiency threshold of 1.0. Reconcile the result with the current approved decision baseline. [R158 R158-Q0400; case R158-C100; CAPM domain 2, task 2.3; source EVM.]

D:

This is a tempting but unsupported shortcut in this case: Using EV/PV would yield SPI, which is about budget-valued schedule efficiency rather than cost efficiency. It does not show that The cost dashboard shows 80 cents of earned value per dollar of actual cost. The decision can be traced to the review evidence. [R158 R158-Q0400; case R158-C100; CAPM domain 2, task 2.3; source EVM.]

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

UP

SPECIAL OFFER: GET 10% OFF

This is ONE TIME OFFER

ExamSnap Discount Offer
Enter Your Email Address to Receive Your 10% Off Discount Code

A confirmation link will be sent to this email address to verify your login. *We value your privacy. We will not rent or sell your email address.

Download Free Demo of VCE Exam Simulator

Experience Avanset VCE Exam Simulator for yourself.

Simply submit your e-mail address below to get started with our interactive software demo of your free trial.

Free Demo Limits: In the demo version you will be able to access only first 5 questions from exam.